Demand side participation - IGE application May 07 - history
Background
The IGE application was for expenditure on a trial by Transpower to test demand-side participation in the upper South Island and to develop a grid support contract.
Consultation
The Commission had previously signalled its intention to engage with stakeholders as much as possible within the confines of the transitional provisions contained within rule 16, the Commission sought submissions on the application, pursuant to rule 16.4.2 of section III of part F.
Submissions closed on 1 June 2007 and the Commission received 9 submissions.
Further information
Additional information was provided by Transpower in its letter dated 11 June 2007 and on the Commission's IGE Consultation page and on the Grid Owners website.
Decision
Having considered the views of submitters, the Commission finalised its decision on the IGE application at its 25/26 June 2007 Board meeting and authorised the publication of a final decision paper. The final decision paper summarised the submissions and explains the Commission's decision to approve the expenditure on the demand-side participation trial and development of a grid support contract product.
Related Documents
01DemandSideParticipationTrial GridSupportContractDevelopment
01DemandSideParticipationTrial-GridSupportContractDevelopment.pdf | pdf | 174 KB | Modified: 07/09/2010 2:34pm
This page is related to: Transmission.




