Tactical Transmission Upgrades - applications for amendment - history
Tactical Transmission Upgrades - application for amended approval costs 2009
Background
On 6 May 2009, Transpower New Zealand Limited (Transpower) applied to the Commission to amend the interim grid expenditure approved by the Commission in December 2005 in respect of a number of Tactical Transmission Upgrade (TTU) projects approved by the Commission.
Transpower sought approval under rule 16 of section III of part F of the Electricity Governance Rules 2003 (Rules)
Opportunity for comment
The Commission provided designated transmission customers and parties affected by Transpower's application, with an opportunity to provide written comments to assist the Commission in considering Transpower's application.
Comments were sought by the Commission by 5.00 pm on Friday, 22 May 2009. The Commission received three comments.
On 25 May 2009, the Commission referred the comments received to Transpower and requested a response.
Transpower responded to this on the 8th of October 2009.
Decision
On 24 November 2009, in accordance with the rule 16.2 of section III of part F, the Commission agreed to amend the interim grid expenditure previously approved by increasing it by:
- $853,205 from $2,300,000 to $3,153,205 for TTU 1;
- $154,335 from $1,400,000 to $1,554,335 for TTU 5;
- $65,495 from $260,000 to $325,495 for TTU 20;
- $843,398 from $2,700,000 to $3,543,398 for TTU 21; and
- $201,573 from $3,800,000 to $4,001,573 fro TTU 30.
The Commission published an explanation of its decisions.
2010 application for amended interim grid expenditure
Background
On 9 March 2010, Transpower applied to the Commission to amend the interim grid expenditure previously approved in respect of TTUs 18 and 21.
-
- $2,807,843 from $18,747,000 to $21,554,843 for TTU 18; and
- $926,784 from $3,543,398 to $4,470,182 for TTU 21.
Further information (TTU 21)
The Commission requested Transpower to analyse what affect the increased transformer cost would have on the West Coast Grid Upgrade Proposal GIT analysis.
Decision
On 19 May 2010, in accordance with rule 16.2 of section III of part F, the Commission agreed to amend the interim grid expenditure previously approved by increasing it by:
The Commission published an explanation of its decision.
Related Documents
Transpower's letter dated 6 May 2009
01TP-ltr-6May09.pdf | pdf | 200 KB | Last Changed: 07/09/2010 2:22pm
2009 application
Application to the Electricity Commission, Recovery of Overspend on Approved Projects (May 2009)
02Application.pdf | pdf | 134 KB | Last Changed: 07/09/2010 2:22pm
2009 application
Transpower's response to comments made during consultation, 8 October 2009
03TP-LTR-8Oct09.pdf | pdf | 2 MB | Last Changed: 07/09/2010 2:22pm
2009 application
Reasons for decision - 24 November 2009
04reasons-decision.pdf | pdf | 224 KB | Last Changed: 07/09/2010 2:22pm
2009 application
Transpower's letter dated 9 March 2010
05TP-ltr-9Mar10.pdf | pdf | 166 KB | Last Changed: 07/09/2010 2:22pm
2010 application
Transpower's letter dated 9 March 2010 Attachment: Response to MEUG's submission on the Recovery of Overspend in respect of TTU18
06TTU18-TP-response-2010.pdf | pdf | 959 KB | Last Changed: 07/09/2010 2:22pm
2010 application
Transpower's letter dated 9 March 2010 Attachment: Application to the Commission on the Recovery of Overspend on TTU21
07TTU21-revised-application-2010.pdf | pdf | 1.5 MB | Last Changed: 07/09/2010 2:22pm
2010 application
Transpower's response on request for further information on the effect on the West Coast GUP
08Effect-Dobson-transformer-price-2010.pdf | pdf | 94 KB | Last Changed: 07/09/2010 2:22pm
2010 application
Reasons for decision - 19 May 2010
09reasons-for-decision-May2010.pdf | pdf | 108 KB | Last Changed: 07/09/2010 2:22pm