Marsden Substation investment proposal - history
Final decision
No request for a public conference was received on the Marsden Substation Investment Proposal, therefore the Commission's decision is to approve the Marsden Substation Investment proposal was final.
Transpower's application
Transpower submitted the Marsden Substation Investment Proposal as a reliability investment. The proposal involves the upgrading of the Marsden 220kV and 110kV buses with bus couplers and duplicate two-zone protection. Transpower sought approval of up to $6.4 million for the proposal.
Opportunity for comment
Under rule 13.3.2 and rule 13.3.5 of section III of part F of the Electricity Governance Rules 2003, the Commission gave notice to provide designated transmission customers and parties affected by the proposals with an opportunity to:
- Provide written comments on Transpower's proposals; and
- Request that the Commission consider alternatives to Transpower's proposals.
Comments and/or requests were sought by the Commission by 5.00 pm on Friday, 26 June 2009. The Commission received three submissions.
Timetable
On 8 June 2009, the Commission and Transpower agreed on a timetable for consultation and approval of the Marsden Substation investment proposal
Notice of Intention
On 3 July 2009, the Commission published a notice of intention to approve the Marsden Substation Investment Proposal.
Reasons for decision
The Reasons for Decision document presented the Commission's analysis of the Marsden Substation Investment Proposal and explained the reasons supporting the Commissions intention to approve the proposal.
Public conference
Under rule 15.2 of section III of part F of the Electricity Governance Rules 2003, a designated transmission customer, an authorised representative of parties substantially affected by the Grid Upgrade Plan, or Transpower, may, within 10 working days of the date of publication of the notice of intention (that is, by 5pm on 17 July 2009), request that the Commission hold a public conference if they consider that:
- The interests of end use customers are materially adversely affected by the cost or the service outcome of the reliability investment to which the notice relates; or
- The Grid Investment Test has not been applied properly to the Grid Upgrade Plan.
The purpose of a public conference is to provide a final opportunity for comment on the reliability investment to which the notice relates.
If no request to hold a public conference is received, or if the Electricity Commission determines not to hold a public conference, the Electricity Commission's decision, as set out in this notice of intention, is final.
Related Documents
Reasons for Decision - 3 July 2009
reasons-decision.pdf | pdf | 220 KB | Last Changed: 07/09/2010 1:14pm
Attachment A - P90 funding calculation
MDN-P90-3.xls | xls | 298 KB | Last Changed: 07/09/2010 1:14pm
Proposal
Marsden Substation Investment Proposal
Marsden-GUP.pdf | pdf | 437 KB | Last Changed: 07/09/2010 1:14pm
Proposal
Transpower's letter dated 29 May 2009 re proposal
GUP-Cover-Letter.pdf | pdf | 187 KB | Last Changed: 07/09/2010 1:14pm
Proposal
This page is related to: Transmission.