Wairakei Ring economic investment - history
Final decision
No request for a public conference was received on the Wairakei Ring Investment Proposal; therefore the Commission’s decision to approve the Wairakei Ring Investment Proposal was final.
Background
Transpower analysed the scope for economic investment in the lower South Island (enabling renewable generation for the lower South Island) and the central North Island (enabling renewable generation in the Wairakei Ring) also known as the Transmission to Enable Renewable investments (TER).
The Commission and Transpower met to discuss how to approach the grid investment test for these projects. Following the meeting, the Commission’s Board was presented with a paper seeking the Board’s guidance as to how generation scenarios could be developed and the economic analysis undertaken. An interested party asked for this paper to be provided.
Following the January 2008 Board meeting, the Commission wrote to Transpower to provide high-level guidance on these projects.
Timetable and amendments
A timeline for development and consideration of these two projects was proposed by Transpower and agreed by the Commission in February 2008.
In April 2008, Transpower wrote to the Commission, providing an updated process and timeframe for consideration and approval of the TER proposals.
The Commission agreed to this revised timetable (“the May 2008 timetable”) which anticipated Transpower submitting the TER proposals on 28 October 2008 and the Commission releasing a notice of intention in December 2008.
In August 2008, Transpower wrote to the Commission advising that it was intending to proceed with the Wairakei Ring project, but wished to defer the Lower South Island project for further investigation. Transpower advised that it now expects to submit the Lower South Island project to the Commission in mid 2009.
Transpower further advised that it now intended to submit the Wairakei Ring project on 17 December 2008. Accordingly, a further revised timetable (“the September 2008 timetable”) was agreed to.
The September 2008 timetable lapsed as the Commission’s review of the investment required more work than was originally anticipated. Accordingly, on 28 January 2009, the Commission and Transpower agreed to an amended timetable (“January 2009 timetable”).
Transpower's application
On 17 December 2008, Transpower submitted to the Commission a new Grid Upgrade Plan (2008 GUP), under rule 12 of section III of part F of the Electricity Governance Rules 2003.
The 2008 GUP includes Transpower’s Wairakei Ring Investment Proposal to facilitate connection of renewable generation in the central North Island. Transpower’s proposal was to build a new double circuit 220kV line connecting directly from Wairakei to Whakamaru. This new line would approximately parallel the existing Wairakei-Whakamaru “B” line, which would be decommissioned and removed.
Transpower submitted the Wairakei Ring proposal as an economic investment and seeks approval of up to $141 million for the proposal. As an economic investment, Transpower had already consulted with the public on the proposal.
Notice of Intention
On 20 February 2009, the Commission published a notice of intention to approve the Wairakei Ring Investment Proposal.
Reasons for decision
The Reasons for Decision document presents the Commission’s analysis of the Wairakei Ring Investment Proposal and explains the reasons supporting the Commissions intention to approve the proposal.
Supporting analysis
The Commission was assisted in its decision making by further analysis undertaken by Transpower, its staff and external advisers.
Opportunity for comment
Under rule 15.2 of section III of part F of the Electricity Governance Rules 2003, a designated transmission customer, an authorised representative of parties substantially affected by the Grid Upgrade Plan, or Transpower, may, within 10 working days of the date of publication of the notice of intention (that is, by 5pm on 6 March 2009), request that the Commission hold a public conference if they consider that:
- The interests of end use customers are materially adversely affected by the cost or the service outcome of the reliability investment to which the notice relates; or
- The Grid Investment Test has not been applied properly to the Grid Upgrade Plan
The purpose of a public conference is to provide a final opportunity for comment on the reliability investment to which the notice relates.
If no request to hold a public conference is received, or if the Electricity Commission determines not to hold a public conference, the Electricity Commission’s decision, as set out in this notice of intention, is final.
Related Documents
Commission's Board paper date 30/31 January 2008 on lower South Island and central North Island economic investments
boardpaper-30Jan08.pdf | pdf | 90 KB | Modified: 07/09/2010 11:39am
Commission's letter dated 8 February 2008 re high-level guidance
letter-8Feb08.PDF | PDF | 162 KB | Modified: 07/09/2010 11:39am
Transpower's letter dated 17 December 2008 re proposal
TP-ltr-17Dec08.pdf | pdf | 79 KB | Modified: 07/09/2010 11:39am
Proposal
Part B - Attachment A - GIT results
AttachmentA.pdf | pdf | 417 KB | Modified: 07/09/2010 11:39am
Proposal
Part B - Attachment B - Analysis assumptions and methodology
AttachmentB.pdf | pdf | 345 KB | Modified: 07/09/2010 11:39am
Proposal
Part B - Attachment C - Power Systems Analysis
AttachmentC.pdf | pdf | 907 KB | Modified: 07/09/2010 11:39am
Proposal
Part B - Attachment D - Cost Report
AttachmentD.pdf | pdf | 505 KB | Modified: 07/09/2010 11:39am
Proposal
Part B - Attachment E - Final Long-list and Short-list criteria
AttachmentE.pdf | pdf | 123 KB | Modified: 07/09/2010 11:39am
Proposal
Part B - Attachment F - Models and data
AttachmentF.pdf | pdf | 71 KB | Modified: 07/09/2010 11:39am
Proposal
Part B - Attachment G - Summary of Submissions from GIT consultation
AttachmentG.pdf | pdf | 93 KB | Modified: 07/09/2010 11:39am
Proposal
Transpower's 16 April 2008 letter re May timetable
letter-16Apr08.PDF | PDF | 362 KB | Modified: 07/09/2010 11:39am
Attachment A - Proposed consultation process and timeframe dated 19 May 2008 (revised)
Revised-Attachment-A.pdf | pdf | 14 KB | Modified: 07/09/2010 11:39am
Commission's letter dated 21 May 2008 re May timetable
letter-21May08.pdf | pdf | 225 KB | Modified: 07/09/2010 11:39am
Reasons for Decision - 20 February 2009
reasons-for-decision.pdf | pdf | 347 KB | Modified: 07/09/2010 11:39am
Technical review of Wairakei Ring Upgrade Investment Proposal
technical-review.pdf | pdf | 1.3 MB | Modified: 07/09/2010 11:39am
Attachment to Reasons for Decision
Transmission Line Cost Review Wairakei Ring Upgrade Plan
ConnellWagner-report.pdf | pdf | 120 KB | Modified: 07/09/2010 11:39am
Supporting Analysis - external Advice from Connell Wagner
16 January 2009 - letter from Transpower to the Commission
16Jan09-ltr-TP-EC.pdf | pdf | 1.3 MB | Modified: 07/09/2010 11:39am
Supporting analysis - key correspondence
22 January 2009 - sensitivity analysis on constraint equations
22Jan09-sensitivity-analysis.pdf | pdf | 39 KB | Modified: 07/09/2010 11:39am
Supporting analysis - key correspondence
26 January 2009 - further analysis on geothermal costs
26Jan09-further-analysis.pdf | pdf | 32 KB | Modified: 07/09/2010 11:39am
Supporting analysis - key correspondence
29 January 2009 - costs of reconductoring options
RE-Wairakei-Ring.pdf | pdf | 54 KB | Modified: 07/09/2010 11:39am
Supporting analysis - key correspondence
10 February 2009 - associated costs of a double circuit line into Ohakuri
10Feb09-associated-costs-2.pdf | pdf | 714 KB | Modified: 07/09/2010 11:39am
Supporting analysis - key correspondence
Attachment to 10 February 2009 email - Wairakei Ring additional Information
FW-Wairakei-Ring-additional-Information.pdf | pdf | 4 MB | Modified: 07/09/2010 11:39am
Supporting analysis - key correspondence
This page is related to: Transmission.