Woodville-Mangamaire-Masterton transmission investment proposal - history

Final decision

No request for a public conference was received on the Woodville - Mangamaire - Masterton Transmission Investment Proposal; therefore the Commission's decision to approve the Woodville - Mangamaire - Masterton Transmission Investment Proposal was final.

Transpower's application

Transpower submitted the Woodville-Mangamaire-Masterton Transmission Investment Proposal as a reliability investment. The proposal involved the replacement of the conductors on these 110kV single circuit transmission lines. Transpower sought approval of up to $17.4 million for the proposal.

Opportunity for comment

Under rule 13.3.2 and rule 13.3.5 of section III of part F of the Electricity Governance Rules 2003, the Commission gave notice to provide designated transmission customers and parties affected by the proposals with an opportunity to:

  • Provide written comments on Transpower's proposals; and
  • Request that the Commission consider alternatives to Transpower's proposals.

Comments and/or requests were sought by the Commission by 12.00 pm on Friday, 30 January 2009. The Commission received five submissions.

Timetable

On 17 December 2008, the Commission and Transpower agreed on a timetable for consultation and approval of the three reliability investments.

The December 2008 timetable lapsed as the Commission's review of the Wairakei Ring investment proposal required more work than was anticipated. Accordingly, on 30 January 2009, the Commission and Transpower agreed to an amended timetable (“January 2009 timetable”).

Notice of Intention

On 13 March 2009, the Commission published a notice of intention to approve the Woodville - Mangamaire - Masterton Transmission Investment Proposal.

Reasons for decision

The Reasons for Decision document presents the Commission's analysis of the Woodville - Mangamaire - Masterton Transmission Investment Proposal and explains the reasons supporting the Commissions intention to approve the proposal.

Key correspondence and supporting analysis

The Commission was assisted in its decision making by analysis of the information provided by Transpower undertaken by its staff.

Opportunity for comment

Under rule 15.2 of section III of part F of the Electricity Governance Rules 2003, a designated transmission customer, an authorised representative of parties substantially affected by the Grid Upgrade Plan, or Transpower, may, within 10 working days of the date of publication of the notice of intention (that is, by 5pm on 27 March 2009), request that the Commission hold a public conference if they consider that:

  • The interests of end use customers are materially adversely affected by the cost or the service outcome of the reliability investment to which the notice relates; or
  • The Grid Investment Test has not been applied properly to the Grid Upgrade Plan

The purpose of a public conference is to provide a final opportunity for comment on the reliability investment to which the notice relates.

If no request to hold a public conference is received, or if the Electricity Commission determines not to hold a public conference, the Electricity Commission's decision, as set out in this notice of intention, is final.

Related Documents

Email from Transpower (6 March 2009)

email-6Mar09.pdf | pdf | 19 KB | Last Changed: 07/09/2010 11:50am

Key correspondence and supporting analysis

Reasons for Decision - 13 March 2009

reason-decision.pdf | pdf | 377 KB | Last Changed: 07/09/2010 11:50am

Notice of Intention - 13 March 2009

Noi.pdf | pdf | 102 KB | Last Changed: 07/09/2010 11:50am

Timetable - 30 January 2009 (current)

timetable-Jan09.pdf | pdf | 21 KB | Last Changed: 07/09/2010 11:50am

Timetable - 17 December 2009 (original)

timetable.pdf | pdf | 21 KB | Last Changed: 07/09/2010 11:50am

Conductor condition report - Mangamaire-Woodville

Conductor-Condition-Report-MGM-WDV.pdf | pdf | 309 KB | Last Changed: 07/09/2010 11:50am

Proposal

Conductor condition report - Mangamaire-Masterton

Conductor-Condition-Report-MGM-MST.pdf | pdf | 298 KB | Last Changed: 07/09/2010 11:50am

Proposal

Attachment B - Technical cost report

AttachmentB.pdf | pdf | 237 KB | Last Changed: 07/09/2010 11:50am

Proposal

Attachment A - Economic report

AttachmentA.pdf | pdf | 344 KB | Last Changed: 07/09/2010 11:50am

Proposal

Woodville-Mangamaire-Masterton Investment Proposal

Investment-Proposal.pdf | pdf | 492 KB | Last Changed: 07/09/2010 11:50am

Proposal

Transpower's letter dated 19 December 2008 re proposal

letter.pdf | pdf | 37 KB | Last Changed: 07/09/2010 11:50am

Proposal

This page is related to: Transmission.