Part 10 review project (metering Code) overview

Project purpose

The purpose of the Part 10 Review project is to:

  1. fix the problems with the current Code;
  2. update the current Code to allow for and keep pace with the adoption of new metering technology; and
  3. future proof the Code to enable innovation.

Implementation of any new regulatory framework will proceed only after substantial consultation with the industry and recommendations are provided to the Authority Board for approval.

If and when any Code changes are approved, an implementation project will be undertaken to ensure the new regulatory framework is implemented in an appropriate timeframe and in a coordinated manner.

Project scope

The project will:

  1. review the existing regulatory framework for metering as contained in Part 10 of the Code to ensure that it is fit for purpose; and
  2. examine the market developments in metering and infrastructure to determine what, if any, impact these developments have on the regulatory framework contained in Part 10 and develop proposed Code, where necessary, to manage impacts that cannot be left to Guidelines to ensure
  1. metering technology does not become a barrier to customer switching;
  2. technology being currently installed is appropriate;
  3. information is secure and privacy is maintained;
  4. AMI complements the current load management infrastructure; and
  5. open access to metering information is achieved.

The Part 10 Code structure document contains the extent of the Code being reviewed.

Project timeline

 The key stages of the Part 10 Review project are outlined in the following table:

Project Stage

Timeline

Status

Stage 1: Consultation & Project Approval
1 Initial Consultation with industry and Board Approval
Submissions
August - December 2008 Complete
Stage 2: Planning and Project Establishment
2 Planning and Project Establishment January - February 2009 Complete
Stage 3: Issues and Options Investigation (new rules principles developed)
3

Development of options to address the issues identified from the August consultation

February - July 2009 Complete
4 Reviewing these options with an industry reference group May - July 2009 Complete
Stage 4: Consultation on Proposed New Rules Principles
5 Development of proposed options, based on the options identified. This includes consideration of both regulatory and non-regulatory solutions (consultation preparation) July - September 2009 Complete
6 Board approval of proposed new rules principles September 2009 Complete
7 Second Consultation with industry
Submissions
Late September - November 2009 Complete
8 Industry forum to introduce the proposed options 30 September 2009 Complete
9 Review submissions and seek Board approval to commence new rules principles drafting November 2009 - January 2010 Complete
Stage 5: Rules Drafting & Consultation
10 New regulatory framework development (Rules drafting) January - June 2010 Complete
11 Third Consultation on proposed new regulatory framework (including the industry forum held on 10 June 2010, and participant-focused workshops held on 26 and 27 July 2010). Note: the consultation closing date was extended by two months at participants' repeated requests. June - September 2010 Complete
12 Review submissions from Third Consultation

October 2010 - July 2011

Complete
13 Fourth Consultation on nomination of the MEP and access to data including the public briefing on 7 June 2011

 

May - June 2011 Complete
14 Review submissions from Fourth Consultation June - July 2011 Complete
15 Fifth Consultation on proposed new Code (excluding nomination of the MEP and access to data) including the forum on 18 October 2011
September - November 2011
Complete
16 Review submissions from Fifth Consultation November - December 2011 Complete
17

Consider and consult on nomination of the MEP and access to data
A forum was held on 30 November 2011

October 2011 - March 2012 In progress
Stage 6: Code Approval
18

Authority consideration of the proposed new Code.

In parallel, the implementation timeline will be confirmed. The implementation of the proposed new Code will be a separate project

December 2011
Completed
Stage 7: Project Closure
19 Part 10 Review project completion Subject to item 17
Not started