Part 10 Implementation
Background
Part 10 of the Electricity Industry Participation Code 2010 (Code) establishes the regulatory framework for metering in the New Zealand electricity industry and deals with industry participants’ obligations for metering arrangements, such as their responsibilities for providing metering installations, testing facilities and equipment, and ensuring metering installations comply with metering standards.
The metering arrangements established through Part 10 were first introduced in 1994 and despite amendments made over the period, did not reflect emerging industry and metering practice. The Electricity Commission commenced a review of Part 10 in 2008 (then Part D) with the purpose of establishing a new set of metering arrangements that were fit for purpose and future proof, including facilitating the adoption of new metering technology such as smart meters.
The new Part 10 and consequential and parallel changes to Parts 1, 11 and 15 of the Code (referred to as the “new Part 10”) were Gazetted in January 2012. Parts 1, 10, 11 and 15 of the Code, incorporating these amendments, are available on the Future code page. Information on the development of the new Part 10 can be found on the Part 10 Review - Overview page.
The Authority has established a project, the Part 10 implementation project, to ensure a seamless transition for industry to the new metering arrangements.
The Authority’s role
The Authority’s role for the Part 10 implementation project is to:
- ensure the requirements placed on the market operation service providers are contracted for and delivered to agreed timelines and quality;
- develop and manage a communications plan designed to ensure that communications with industry participants are effective;
- provide information and education to industry participants to assist them in meeting the new Part 10 requirements by 6 June 2013;
- co-ordinate testing with participants;
- keep stakeholders informed of the Part 10 implementation timeline and progress against the timeline; and
- monitor industry readiness for the commencement of the new Part 10.
Project activities
Indicative dates for key Part 10 implementation activities are provided in the following table.
| # | Key milestone | Indicative dates | Status |
|---|---|---|---|
| PROJECT INITIATION and PLANNING | |||
| 1 | New Part 10 signed |
December 2011 | Completed |
| 2 | Part 10 implementation project webpage |
February 2012 |
Completed |
| 3 | Participant forum #1 | 22 February 2012 | Completed |
| 4 | Part 10 implementation project communications plan |
March 2012 | Completed |
| CONSTRUCTION | |||
| 5 |
Draft new guidelines and processes:
|
January 2012 – December 2012 | In progress |
| 6 | MEP workshop | 28 March 2012 | Completed |
| 7 | Update and publish registry functional specification for Part 10 requirements | March 2012 | In progress |
| 8 | Registry development | March 2012 – February 2013 | Not started |
| 9 | Participant system development | March 2012 – February 2013 | In progress |
| 10 | Reconciliation manager system development | January 2012 – April 2012 |
In progress |
| 11 | Review existing guidelines (ATH audit, reconciliation participant audit, in-situ testing) | March 2012 – December 2012 | Not started |
| 12 | Participant forum(s) / workshop(s) #2 (tentative) | June 2012 |
Not started |
| 13 | Establish data cleanup team + develop data cleanup plan | June 2012 – December 2012 | Not started |
| 14 | Selection of Electricity Authority’s Test Manager for participant registry UAT | October 2012 | Not started |
| 15 | Participant forum(s) / workshop(s) #3 (tentative) | October 2012 |
Not started |
| 16 | Data cleanup | January 2013 - 6 May 2013 |
Not started |
| 17 | Participant forum(s) / workshop(s) #4 (tentative) | February 2013 | Not started |
| 18 | MEP auditor examination, interviews and approvals | February 2013 - March 2013 | Not started |
| 19 | Any additional implementation Code amendments found to be required for transitional registry switching arrangements, MEP deemed contracts with component owners, implementation issues | February 2013 - May 2013 | Not started |
| 20 | Participant registry UAT (2 months) | 7 March 2013 - 7 May 2013 | Not started |
| 21 | Registry software audit | May 2013 | Not started |
| 22 | Registry acceptance | 7 May 3013 - 14 May 2013 | Not started |
| TRANSITION to PRODUCTION | |||
| 23 | Authority validation of registry data (1 week) |
7 May 3013 - 14 May 2013 | Not started |
| 24 | Retailer reports (1 day) | 15 May 2013 | Not started |
| 25 | Populate registry + switching moratorium (2 weeks) | 16 May 3013 - 30 May 2013 | Not started |
| 26 | Registry migration (4 days) | 31 May 3013 - 5 June 2013 | Not started |
| 27 | Review existing metering installation variations | May 2013 | Not started |
| 28 | Go-live for the new Part 10 | 6 June 2013 | Not started |
| 29 | Switch catchup | 6 June 2013 to 20 June 2013 | Not started |
| PROJECT CLOSE OUT & OPERATIONS | |||
| 30 | Project handover to Authority’s operations team |
June 2013 - July 2013 | Not started |
| 31 | Project closure | June 2013 - July 2013 | Not started |
| 32 | MEP audits | 6 June 2013 - 5 September 2013 | Not started |
Authority contact
If you have any questions regarding the project, please contact Lori Martin, the Part 10 Implementation project manager: lori.martin@ea.govt.nz or 04 471 8623.
Related Documents
Part 10 Implementation - FAQ
Part-10-implementation-FAQ.pdf | pdf | 60 KB | Modified: 30/04/2012 2:03pm
Part 10 Implementation - Communications Plan
Part-10-Implementation-Communications-Plan.pdf | pdf | 46 KB | Modified: 30/04/2012 2:03pm
Registry functional specification v19A.2
Registry-functional-specification-v19a2.pdf | pdf | 1.1 MB | Modified: 28/03/2012 9:40am
Code amendments - Metering arrangements (searchable version)
Code-amendments-Metering-arrangements.pdf | pdf | 479 KB | Modified: 17/02/2012 4:10pm
Faulty metering installation flow diagram
Faulty-metering-installation-flow-diagram.pdf | pdf | 136 KB | Modified: 20/02/2012 12:30pm
ICP livening process flow diagram
ICP-livening-process-flow-diagram.pdf | pdf | 210 KB | Modified: 20/02/2012 12:30pm




