Meridian has written to the Authority seeking clarification on the timing of the implementation of the avoided cost of transmission (ACOT) Code amendment of December 2016. The Authority has responded to Meridian, clarifying the matters that were the subject of Meridian’s letter.
-
8 June 2017 - Meridian letter to Authority re timing clarification
Last updated: 15th August 2017
-
14 August 2017 - Authority letter to Meridian re timing clarification
Last updated: 15th August 2017
-
-
Correspondence with Transpower
Feb – Mar 2017
Transpower requested an extension from 15 March 2017 to 21 April 2017 for it to provide a report to the Authority that identifies which existing distributed generation in the Lower South Island is required for Transpower to meet the grid reliability standards. The Authority has granted the extension.
-
16 February 2017 - Transpower letter to EA
16Feb17-Transpower-ltr-to-EA.pdf (PDF, 405 KB)
Last updated: 17th March 2017
-
15 March 2017 - EA Letter to Alison Andrew, CEO Transpower
15March17-Letter-to-Alison-Andrew-Transpower.pdf (PDF, 397 KB)
Last updated: 17th March 2017
-
Contact Us
EMAIL: info@ea.govt.nz
Sign up to our newsletter
Subscribe to the Electricity Authority newsletters
© 2019 Copyright material on this site is protected by copyright owned by the Electricity Authority or its licensors. Full copyright statement.