Schedule 13.1 cls 13.9, 13.13, 13.38 and 13.64
Forms 1 to 9
Heading: amended, on 1 November 2022, by clause 153 of the Electricity Industry
Participation Code Amendment (Real Time Pricing) 2022.
Form
1
Generator offer
Date: _______________________________________
Generator
Participant Identifier: _______________________________________
Generator Name: _______________________________________
Grid Injection Point: _______________________________________
Generator Category
(clause 13.10 of the Code):¨ Unit ¨ Station
¨ Generator block (clauses 13.60 and 13.61 of
the Code)
Block Name (if
applicable): _______________________________________
Generator Maximum
Output (including overload): ____________________________________MW
Trading Period: _______ Starting at ________ :
_______ 0 hours
Maximum Generator Ramp
Up Rate: __________________________________MW/hr
Maximum Generator Ramp
Down Rate: __________________________________MW/hr
Offer is submitted by dispatch notification generator: o
Offer to sell electricity
Band
1: From 0 MW to ____________ MW
@ $ ____________ per MWh
Band 2: plus ____________ MW @ $ ____________ per MWh
Band 3: plus ____________ MW @ $
____________ per MWh
Band 4: plus ____________ MW @ $ ____________ per MWh
Band 5: plus ____________ MW @ $ ____________ per MWh
Compare: Electricity Governance Rules 2003 form 1
schedule G1 part G
Schedule 13.1, Form 1: amended, on 27 May 2015, by
clause 14 of the Electricity Industry Participation Code Amendment (Industrial
Co-generation Dispatch Arrangements) 2015.
Schedule 13.1, Form 1: amended, on 1 November 2022,
by clause 154 of the Electricity Industry Participation Code Amendment (Real
Time Pricing) 2022.
Form 2
Intermittent Generator Offer
Date: _______________________________________
Intermittent Generator Participant
Identifier: _______________________________________
Intermittent Generator Name: _______________________________________
Grid Injection Point: _______________________________________
Generator category (clause 13.10 of the
Code):¨ Station
Generator Installed Capacity: ____________________________________MW
Trading Period: _______ Starting at ________ : _______ 0 hours
Maximum Generator Ramp Up Rate: __________________________________MW/hr
Maximum Generator Ramp Down Rate: __________________________________MW/hr
Offer
to sell electricity
Band 1: From 0 MW to ____________ MW @
$ ____________ per MWh
Band 2: plus ____________ MW @ $ ____________ per MWh
Band 3: plus ____________ MW @ $ ____________ per MWh
Band 4: plus ____________ MW @ $ ____________ per MWh
Band 5: plus ____________ MW @ $ ____________ per MWh
Forecast of generation potential: ____________________________________MW
Compare: Electricity Governance
Rules 2003 form 2 schedule G1 part G
Schedule 13.1, Form 2:
amended, on 27 May 2015, by clause 15 of the Electricity Industry Participation
Code Amendment (Industrial Co-generation Dispatch Arrangements) 2015.
Schedule 13.1, Form 2:
amended, at 12.00 pm on 19 September 2019, by clause 29 of the Electricity
Industry Participation Code Amendment (Wind Offer Arrangements) 2019.
Form 3
Type A or Type B Co-generator Offer
Date:
_______________________________________
Type
A/Type B Co-generator
Participant Identifier: _______________________________________
Type
A/Type B Co-generator
Name: _______________________________________
Grid
Injection Point: _______________________________________
Generator
Category (clause 13.10 of the Code):
Unit Station
Type
A/Type B Co-generator Maximum Output (including overload):
____________________________________
MW
Trading
Period: _______
Starting at ________ : _______ 0 hours
Maximum
Generator Ramp Up Rate:
__________________________________
MW/hr
Maximum
Generator Ramp Down Rate:
__________________________________
MW/hr
Offer
to sell electricity
Band
1: From 0 MW to ____________
MW @ $ ____________ per MWh
Band 2: plus
____________ MW @ $ ____________ per
MWh
Compare: Electricity
Governance Rules 2003 form 2A schedule G1 part G
Schedule 13.1, Form 3
heading: amended, on 27 May 2015, by clause 16(1) of the Electricity Industry
Participation Code Amendment (Industrial Co-generation Dispatch Arrangements)
2015.
Schedule 13.1, Form 3:
amended, on 27 May 2015, by clause 16(2) of the Electricity Industry
Participation Code Amendment (Industrial Co-generation Dispatch Arrangements)
2015.
Form 4
Purchaser’s nominated bid for electricity
Date: _______________________________________
Purchaser: _______________________________________
Grid Exit Point: _______________________________________
Trading Period: ____ starting at
_________ : _________ 0 hours
Type of bid: Nominated
dispatch bid o
Nominated
non-dispatch bid o
Dispatch-capable load station identifier (if
applicable): ___________
Bid is submitted by dispatch notification purchaser: o
Nominated
bid to buy electricity
Band
1: From 0 MW to MW
below $ per MWh
Band
2: plus MW below $ per
MWh
Band
3: plus MW below $ per
MWh
Band
4: plus MW
below $ per MWh
Band
5: plus MW
below $ per MWh
Band
6: plus MW
below $ per MWh
Band
7: plus MW below $ per
MWh
Band
8: plus MW below $ per
MWh
Band
9: plus MW below $ per
MWh
Band
10: plus MW
below $ per MWh
Compare: Electricity Governance Rules 2003 form 3
schedule G1 part G
Schedule
13.1 Form 4: amended, on 28 June 2012, by clause 51 of the Electricity Industry
Participation (Demand-side Bidding and Forecasting) Code Amendment 2011.
Schedule
13.1 Form 4: substituted, on 15 May 2014, by clause 68 of the Electricity
Industry Participation (Modified Dispatchable Demand) Code Amendment 2013.
Schedule
13.1, Form 4: amended, on 1 November 2022, by clause 155 of the Electricity
Industry Participation Code Amendment (Real Time Pricing) 2022.
Form 4A
Purchaser’s difference bid for electricity
Date: _______________________________________
Purchaser: _______________________________________
Grid
Exit Point: _______________________________________
Trading Period: ________
starting at _________ : _________ 0 hours
Difference bid to increase/ decrease use of electricity
Increase electricity
Band 1: Increase MW below $
____________ per MWh
Band 2: plus MW below $
____________ per MWh
Band 3: plus MW below $
____________ per MWh
Band 4: plus MW below $
____________ per MWh
Band 5: plus MW below $
____________ per MWh
Decrease electricity
Band 1: Decrease_________ MW
above $ ____________ per MWh
Band 2: plus MW above $
____________ per MWh
Band 3: plus MW above $
____________ per MWh
Band 4: plus MW above $ ____________
per MWh
Band 5: plus MW above $
____________ per MWh
Schedule 13.1 Form 4A: inserted, on 28 June 2012, by clause 52 of the
Electricity Industry Participation (Demand-side Bidding and Forecasting) Code
Amendment 2011.
Generation
Reserve Offer
Date: ________________________________________________________
Ancillary Service Agent: ________________________________________________________
Generator Name: ________________________________________________________
Grid Injection Point: ________________________________________________________
Trading Period: ______________
Starting at _____________________ 0 hours
Offer to provide reserve
(1) Partly Loaded Spinning Reserve
Band 1:
____% of electricity (MW), up to a maximum of ____ MW
as Fast Instantaneous Reserve @
$ _____ per MW
____% of electricity (MW), up to a maximum of ____ MW
as Sustained Instantaneous
Reserve @ $
_____ per MW
Band 2:
____% of electricity (MW), up to a maximum of ____ MW
as Fast Instantaneous Reserve @
$ _____ per MW
____% of electricity (MW), up to a maximum of ____ MW
as Sustained Instantaneous
Reserve @ $ _____ per MW
Band 3:
____% of electricity (MW), up to a maximum of ____ MW
as Fast Instantaneous Reserve @
$ _____ per MW
____% of electricity (MW), up to a maximum of ____ MW
as Sustained Instantaneous
Reserve @ $
_____ per MW
(2) All other forms of generation reserve
Band 1:
Up to a maximum of _______MW @ $ _______ per MW as Fast Instantaneous
Reserve
Up to a maximum of _______ MW @ $ _______ per MW as Sustained
Instantaneous Reserve
Band 2:
Up to a maximum of _______MW @ $ _______ per MW as Fast
Instantaneous Reserve
Up to a maximum of _______ MW @ $ _______ per MW as Sustained
Instantaneous Reserve
Band 3:
Up to a maximum of _______MW @ $ _______ per MW as Fast
Instantaneous Reserve
Up to a maximum of _______ MW @ $ _______ per MW as Sustained
Instantaneous Reserve
Compare: Electricity Governance Rules 2003 form 4
schedule G1 part G
Schedule
13.1 Form 5: amended, on 15 May 2014, by clause 50 of the Electricity Industry
Participation (Minor Code Amendments) Code Amendment 2014.
Schedule
13.1 Form 5: amended, on 3 May 2022, by clause 9(1) and (2) of the Electricity
Industry Participation Code Amendment (Enabling Energy Storage Systems to Offer
Instantaneous Reserve) 2022.
Interruptible
Load Offer
Date: _______________________________________________________
Ancillary Service Agent: _______________________________________________________
Grid Exit Point or interruptible load group GXP: _______________________________________________________
Dispatch-capable load station identifier (if applicable):
___________
Instantaneous reserve capability
Holds a Reserve
Contract with the System Operator ¨ Yes
Fast
Instantaneous Reserve
Interruptible Load Available ¨ Yes
Sustained
Interruptible Load Available ¨ Yes
Trading Period: ___________ Starting at __________ :
____________ 0 hours
Offer to provide reserve
1 Interruptible load
Band 1:
Up
to a maximum of ______ MW @ $
_______ per MW as Fast Instantaneous Reserve
Up to a maximum of ______ MW
@ $ _______ per MW as Sustained Instantaneous Reserve
Band 2:
Up
to a maximum of ______ MW @ $
_______ per MW as Fast Instantaneous Reserve
Up to a maximum of ______ MW
@ $ _______ per MW as Sustained Instantaneous Reserve
Band 3:
Up
to a maximum of ______ MW @ $ _______
per MW as Fast Instantaneous Reserve
Up to a maximum of ______ MW
@ $ _______ per MW as Sustained Instantaneous Reserve
Compare: Electricity Governance Rules 2003 form 5
schedule G1 part G
Schedule 13.1 Form 6: amended,
on 15 May 2014, by clause 51 of the Electricity Industry Participation (Minor
Code Amendments) Code Amendment 2014.
Schedule
13.1, Form 6: amended, on 1 November 2022, by clause 156 of the Electricity
Industry Participation Code Amendment (Real Time Pricing) 2022.
Instantaneous
Reserve Parameters
Date: _________________________________________________________
Trading Period:________________ Starting at ___________ : ___________ 0
hours
North Island Fast
Instantaneous Reserve Adjustment
Factor _________________________
North Island Sustained
Instantaneous Reserve Adjustment
Factor _________________________
South Island Fast
Instantaneous Reserve Adjustment
Factor _________________________
South Island Sustained
Instantaneous Reserve Adjustment
Factor _________________________
Minimum Risk
North Island Minimum Risk _____________________
MW
South Island Minimum Risk _____________________
MW
Compare: Electricity Governance Rules 2003 form 6
schedule G1 part G
Schedule 13.1 Form 7: amended,
on 15 May 2014, by clause 52 of the Electricity Industry Participation (Minor
Code Amendments) Code Amendment 2014.
Form 8
Notice of Station Dispatch Group
Date:
Generator:
[Insert name of generator] hereby gives
the system operator notice pursuant
to clause 13.64 of the Code that the following group of generating units and/or generating
stations are to be treated as a station
dispatch group:
Name of Station Dispatch Group:
Station Identifier:
Constituent units:
Grid
Injection Point (GIP) |
Station/ generating unit name |
|
|
|
|
This notice is to be
effective from 0000 hours on [insert date], being at least 15 business days after the date of this
notice, and remains in force until cancelled in writing by [insert name of
generator].
Generator Control
centre:
Name: |
_________________________ |
Contact Number: |
Ph:
_____________________ Ph:
______________________ |
Address: |
__________________________________________________ |
|
__________________________________________________ |
Yours sincerely
[Name of sender]
[Generator name]
Compare: Electricity Governance Rules 2003 form 7
schedule G1 part G
Schedule
13.1, Form 8: amended, on 5 October 2017, by clause 483 of the Electricity
Industry Participation Code Amendment (Code Review Programme) 2017.
Form 9
Claim of pricing error
Compare: Electricity Governance Rules 2003 form 8 schedule G1 part G
Schedule 13.1 Form 9: amended,
on 15 May 2014, by clause 53 of the Electricity Industry Participation (Minor
Code Amendments) Code Amendment 2014.
Schedule
13.1, Form 9: revoked, on 1 November 2022, by clause 157 of the Electricity
Industry Participation Code Amendment (Real Time Pricing) 2022.