This legislation is administered by the Electricity Authority. For more information please see: Website: https://www.ea.govt.nz/
Contact phone: +64 4 460 8860
Contact address: PO Box 10041, Wellington 6143
This amendment to the Electricity Industry Participation Code 2010 (Code) is made under section 38 of the Electricity Industry Act 2010 (Act) by the Electricity Authority having complied with section 39 of that Act.
Title 1
Commencement 1
Code amended 1
Clause 9.18 amended (Provision of information) 1
This is the Electricity Industry Participation Code (Provision of Information to System Operator) (No 2) Amendment 2025.
This amendment comes into force on 1 December 2025.
This amendment amends the Electricity Industry Participation Code 2010.
In clause 9.18(1),—
in paragraph (e), replace “; and” with “; and”; and
(f)
the system operator’s implementation of and compliance with the security of supply forecasting and information policy or emergency management policy.
replace paragraph (f) with:
In clause 9.18(2)(a), replace “this Part, to implement or comply with the security of supply forecasting and information policy or emergency management policy,” with “this Part, to implement or comply with the security of supply forecasting and information policy or emergency management policy,”.
Made at Wellington on 23rd October 2025
Anna Kominik Chair
Electricity Authority
Certified in order for signature:
Nicholai Mumford Olivia Lund
Senior Legal Counsel Partner
Electricity Authority Duncan Cotterill
22 October 2025 21 October 2025
This note is not part of the amendment but is intended to indicate its general effect.
This amendment to the Electricity Industry Participation Code 2010 (Code) comes into force on 1 December 2025.
The amendment amends clause 9.18 of the Code to enable the system operator to require
participants to provide information to the system operator that is relevant to the system operator’s implementation of and compliance with the security of supply forecasting and information policy or emergency management policy.
The amendment makes permanent changes to the Code previously made urgently by the Electricity Industry Participation Code (Provision of Information to System Operator) Amendment 2025 which would otherwise expire nine months after the date on which that amendment came into force.
More information about the amendment is available on the Electricity Authority’s website at: https://www.ea.govt.nz
This is secondary legislation issued under the authority of the Legislation Act 2019. | |
Title | Electricity Industry Participation Code (Provision of Information to System Operator) (No 2) Amendment 2025 |
Principal or amendment | Amendment |
Consolidated version | No |
Empowering Act and provisions | Electricity Industry Act 2010, section 38 |
Replacement empowering Act and provisions | Not applicable |
Maker name | Electricity Authority |
Administering agency | Electricity Authority |
Date made | 23 October 2025 |
Publication date | 30 October 2025 |
Notification date | 30 October 2025 |
Commencement date | 1 December 2025 |
End date (when applicable) | Not applicable |
Consolidation as at date | Not applicable |
Related instruments | |