%20Amendment%202026.files/image002.png)
|
This
legislation is administered by the Electricity Authority. For more
information please see: Website: https://www.ea.govt.nz/ Contact
phone: +64 4 460 8860 Contact
address: PO Box 10041, Wellington 6143 |
Electricity Industry Participation Code (Connected Asset
Commissioning, Testing and Information Standard) Amendment 2026
This amendment to the Electricity Industry Participation Code 2010 (Code) is made under section 38 of the Electricity Industry Act 2010 (Act) by the Electricity Authority having complied with section 39 of the Act.
Amendment
1 Title
This is the Electricity Industry Participation Code (Connected Asset Commissioning, Testing and Information Standard) Amendment 2026.
2 Commencement
This amendment comes into force on 1 July 2026.
3 Code amended
This amendment amends the Electricity Industry Participation Code 2010.
Part 1
Amendments to Part 1 of the Electricity Industry
Participation Code
4 Clause 1.1 amended (Interpretation)
(1) In clause 1.1(1), insert in their appropriate alphabetical order:
connected asset commissioning, testing and information standard means the connected asset commissioning, testing and information standard that is incorporated by reference in this Code under clause 8.73
high-speed monitor means a device capable of capturing and storing high-resolution waveform data of voltage and current signals during power system events or disturbances, with sufficient sampling frequency and accuracy to support detailed analysis of power system behaviour
(2) In clause 1.1(1), definition of asset capability statement, replace “2(5)” with “2(2)”.
(3) In clause 1.1(1), definition of System operation document,—
(a) replace “System operation document” with “system operation document”; and
(b) insert after paragraph (f):
(g) the connected asset commissioning, testing and information standard
(4) In clause 1.1(1), revoke the definitions of maximum continuous rating and scaling factor.
Part 2
Amendments to Part 7 of the Electricity Industry
Participation Code
5 Clause 7.15 amended (Review of policy statement and procurement plan)
(1) In clause 7.15, replace subclause (1) with:
(1) The system operator must review the following system operation documents at least once every 2 years to identify whether the document should be amended:
(a) the connected asset commissioning, testing and information standard:
(b) the policy statement:
(c) the procurement plan.
(2) In clause 7.15, insert after subclause (1):
(1A) The system operator may review a system operation document not referred to in subclause (1) at any time.
(3) In clause 7.15(2):
(a) replace paragraph (a) with:
(a) if the previous review does not result in an amendment being made, the date the system operator advised the Authority of that decision under clause 7.15(3)(b); or
(b) in paragraph (b), replace “a review” with “the previous review”.
Part 3
Amendments to Part 8 of the Electricity Industry
Participation Code
6 Clause 8.4 amended (System operator may rely on information provided)
In clause 8.4(b), replace “and the technical codes” with “, the technical codes, and the connected asset commissioning, testing and information standard”:
7 Clause 8.7 amended (System operator must
not contract contrary to this arrangement)
In clause 8.7, replace “and the technical codes” with “, the technical codes, and the connected asset commissioning, testing and information standard”.
8 Clause 8.21 amended (Excluded generating
stations)
Replace clause 8.21(2) with:
(2) Whether likely to be an excluded generating station or not, a generator must provide the system operator with written advice of its intention to connect to the grid or directly or indirectly to a local network a generating station with one or more generating units with a rated net maximum capacity equal to or greater than 1 MW (alternating current (a.c.) capacity), together with the information relating to the generating unit or generating station in accordance with clause 8.25(4).
9 Clause 8.25 amended (Other asset owner
performance obligations and technical standards)
(1) Replace clause 8.25(3) with:
(3) Each asset owner and each purchaser must provide communication facilities that comply with the connected asset commissioning, testing and information standard.
(2) Replace clause 8.25(4) with:
(4) Each asset owner and each purchaser must provide information to the system operator that complies with the technical codes and the connected asset commissioning, testing and information standard.
(3) In clause 8.25(5)(a)(ii), replace “agreed between the system operator and the embedded generator” with “specified in the connected asset commissioning, testing and information standard”.
(4) Replace clause 8.25(7) with:
(7) If the Authority approves the system operator’s request under subclause (6), the embedded generator must provide the information in accordance with the connected asset commissioning, testing and information standard.
10 Clause 8.27 amended (System operator to monitor compliance)
(1) Replace clause 8.27(1) with:
(1) To the extent possible, given the
information made available by asset owners, the system operator must monitor, in the manner set out in the policy statement, which
for the avoidance of doubt, sets out the system operator’s only
monitoring obligations under this subpart, the ongoing compliance of asset owners with the asset
owner performance obligations, the technical codes, and the connected
asset commissioning, testing and information standard.
(2) In clause 8.27(2), insert “or
provisions of the connected asset commissioning, testing and information
standard” after “technical
codes” in each
place.
(3) In clause 8.27(3), insert
“or provisions of the connected asset commissioning, testing and
information standard”
after “technical codes” in each place.
11 Clause 8.28 amended (Responsibility for compliance)
(1) Replace clause 8.28(1) with:
(1) Each asset owner must
comply with the asset
owner performance obligations, technical codes, and the connected
asset commissioning, testing and information standard at all times and must satisfy the system operator,
whenever requested by the system
operator acting reasonably, that each of its assets or configuration of assets complies with the asset
owner performance obligations, technical codes, and provisions of the connected asset commissioning, testing and information standard that apply to that asset or configuration of assets.
(2) In clause 8.28(3), replace
“and technical codes” with “, technical codes, and the connected asset commissioning,
testing and information standard”.
12 Clause 8.29 amended (Right to apply for approval of equivalence arrangement or grant of dispensation)
In clause 8.29(1), replace “or a technical code obligation” with “, a technical code obligation, or a connected asset commissioning, testing and information standard obligation”.
13 Clause 8.30 amended (Approval of equivalence arrangements)
In clause 8.30, replace “or technical code” with “, technical code obligation, or connected asset commissioning, testing and information standard obligation”.
14 Clause 8.31 amended (Grant of dispensations)
In clause 8.31(1), replace “or technical code” with “, a technical code obligation, or connected asset commissioning, testing and information standard obligation”.
15 Clause 8.32 amended (Liability of asset owner pending decision)
In clause 8.32, replace “or the technical codes” with “, the technical codes, or the connected asset commissioning, testing and information standard”.
16 Clause 8.34 amended (Cancellation of equivalence arrangement or dispensation)
In clause 8.34(1), replace “or technical codes” with “, technical codes, or the connected asset commissioning, testing and information standard”.
17 Clause 8.37 amended (Other provisions relating to equivalence arrangements and dispensations)
In clause 8.37(3), replace “and technical codes” with “, technical codes, or the connected asset commissioning, testing and information standard”.
18 Clause 8.38 amended (Authority may require excluded generating stations to comply with certain clauses)
In clause 8.38(1), replace “and the provisions of the technical codes (or parts thereof)” with “the provisions of the technical codes (or parts thereof), and the connected asset commissioning, testing and information standard (or parts thereof)”.
19 New Subpart 7 inserted
Insert new Subpart 7 of Part 8 as set out in the Schedule of this amendment.
20 Schedule 8.1, clause 2 amended
In Schedule 8.1, clause 2(b), insert “obligation or connected asset commissioning, testing and information standard obligation” after “technical code”.
21 Schedule 8.3, Technical Code A, clause 2 amended
(1) In Schedule 8.3, Technical Code A, replace clause 2(1)(c) with:
(c) it meets any requirements of the system operator identified in the connected asset commissioning, testing and information standard.
(2) In Schedule 8.3, Technical Code A, revoke clause 2(2).
(3) In Schedule 8.3, Technical Code A, revoke clause 2(2A).
(4) In Schedule 8.3, Technical Code A, replace clause 2(3) with:
(3) On, or before, completion of commissioning of an asset or configuration of assets, the asset owner must obtain a final assessment of the asset or configuration of assets in writing from the system operator in accordance with the requirements set out in the connected asset commissioning, testing and information standard.
(5) In Schedule 8.3, Technical Code A, clause 2(4), delete the first sentence.
(6) In Schedule 8.3, Technical Code A, replace clause 2(5) with:
(5) Each asset owner must provide the system operator with an asset capability statement in accordance with the connected asset commissioning, testing and information standard―
(a) for each asset that is―
(i) proposed to be connected, or is connected to, or forms part of the grid; or
(ii) proposed to be connected, or is connected directly or indirectly to a local network; and
(b) for each asset, where the asset owner is a generator, that―
(i) forms part or all of a generating station with a capacity equal to or greater than the threshold specified in clause 8.21(1) at the point of connection to the network; or
(ii) forms part or all of a generating unit with a capacity equal to or greater than the threshold specified in clause 8.21(2) at the point of connection to the network.
(7) In Schedule 8.3, Technical Code A, revoke clause 2(5A).
(8) In Schedule 8.3, Technical Code A, replace clause 2(6) with:
(6) Each asset owner must provide a commissioning plan or test plan to the system operator in compliance with the connected asset commissioning, testing and information standard.
(9) In Schedule 8.3, Technical Code A, revoke clause 2(7).
(10) In Schedule 8.3, Technical Code A, revoke clause 2(8).
(11) In Schedule 8.3, Technical Code A, clause 2(9), insert “,” after “Once assessed by the system operator”.
(12) In Schedule 8.3, Technical Code A, insert after clause 2(9):
(10) Each asset owner must—
(a) carry out connection studies for each asset in accordance with the connected asset commissioning, testing and information standard; and
(b) provide connection study reports to the system operator in compliance with the connected asset commissioning, testing and information standard; and
(c) ensure that modelling information is provided to the system operator in compliance with the connected asset commissioning, testing and information standard; and
(d) provide a model to the system operator in compliance with the connected asset commissioning, testing and information standard that can be used for the network models in clause 8.25A(3)(a).
(11) The obligation in subclause (10)(c) to ensure that modelling information is provided to the system operator and any related obligation on an asset owner to provide modelling information to the system operator in the connected asset commissioning, testing and information standard may be met by the asset owner arranging for an original equipment manufacturer to provide the information to the system operator directly.
22 Schedule 8.3, Technical Code A, clause 3 amended
(1) In Schedule 8.3, Technical Code A, revoke clause 3(1).
(2) In Schedule 8.3, Technical Code A, insert after clause 3(2):
(2A) The system operator must―
(a) store the information provided under clause 2(10)(c) in a secure server that is accessible only to system operator employees, contractors or advisers that require access to the information to perform their roles; and
(b) treat the information provided under clause 2(10)(c) as confidential to the party that provided the information except as required by law; and
(c) ensure that it has systems, policies, procedures and confidentially obligations in place for the purpose of ensuring, as far as reasonably possible, that any person given or who has access to information in accordance with paragraph (a) does not disclose the information to any other person, except persons given access to that information in accordance with paragraph (a) or as required by law.
(3) In Schedule 8.3, Technical Code A, revoke clause 3(3).
23 Schedule 8.3, Technical Code A, clause 7 amended
(1) In Schedule 8.3, Technical Code A, replace clause 7(1) with:
(1) Subject to subclause (1B), assets that are modified, or are proposed to be modified, are—
(a) to be treated as new assets for the purposes of this Code and the connected asset commissioning, testing and information standard; and
(b) are subject to the requirements for connection to the grid and the requirements for commissioning assets in this Code and the connected asset commissioning, testing and information standard.
(1A) For the purposes of this Schedule, the following are considered to be modifications to assets, if the new connection or alteration may affect the capacity of the assets or may affect asset owner performance obligations, technical code requirements or requirements in the connected asset commissioning, testing and information standard:
(a) a new connection of assets to the grid or a local network:
(b) a new connection of assets to form part of the grid:
(c) a new connection of an embedded generator to a local network other than an excluded generator as defined in clause 8.21(1):
(d) an alteration to assets already connected to the grid or, in the case of an embedded generator, already connected to a local network.
(2) In Schedule 8.3, Technical Code A, insert before clause 7(2):
(1B) Subclause (1) does not apply in respect of the requirements in Chapter 4 of the connected asset commissioning, testing and information standard.
(1C) If an asset owner reasonably considers that a modification to an asset materially affects the asset’s capability, the asset owner must advise the system operator as soon as reasonably practicable.
(1D) If, in respect of an asset notified
under subclause (1C), the system operator reasonably considers it necessary,
the system operator―
(a) may require that an asset owner provide updated modelling information for that asset in accordance with the connected asset commissioning, testing and information standard; and
(b) must advise the asset owner in writing of this requirement as soon as it is made.
(3) In Schedule 8.3, Technical Code A, replace clause 7(2) with:
(2) If an asset owner proposes or intends to decommission an asset, the asset owner must provide the system operator with a decommissioning plan for that asset and give written notice to the system operator in accordance with the connected asset commissioning, testing and information standard.
24 Schedule 8.3, Technical Code A, clause 8 amended
(1) In Schedule 8.3, Technical Code A, clause 8(1), replace “and this technical code” with “, this technical code, and the connected asset commissioning, testing and information standard”.
(2) In Schedule 8.3, Technical Code A, in the chapeau of clause 8(2)—
(a) replace “2(6) to (8)” with “2(6), 2(8), and 2(10)”; and
(b) delete “carry out periodic testing”.
(3) In Schedule 8.3, Technical Code A, clause 8(2)(a)—
(a) insert “carry out periodic testing” before “of its assets”; and
(b) replace “Appendix B” with “the connected asset commissioning, testing and information standard; and”.
(4) In Schedule 8.3, Technical Code A, insert after clause 8(2)(b):
(c) provide high-speed monitors that comply with the requirements specified in the connected asset commissioning, testing and information standard.
(2A) Each asset owner with one or more generating units commissioned before 1 January 2016 for which wind is the primary power source must complete the first of each test required under subclause (2)(a) for those generating units no later than 31 December 2028.
(5) In Schedule 8.3, Technical Code A, replace clause 8(3) with:
(3) If the system operator advises an asset owner that it reasonably believes that an asset may not comply with an asset owner performance obligation or this technical code, the asset owner must advise the system operator and undertake remedial action or testing of its assets in accordance with the connected asset commissioning, testing and information standard.
25 Schedule 8.3, Technical Code A, Appendix B revoked
In Schedule 8.3, Technical Code A, revoke Appendix B: Routine testing of assets and automatic under-frequency load shedding systems.
26 Schedule 8.3, Technical Code B, clause 7 amended
(1) In Schedule 8.3, Technical Code B, clause 7(9), replace “clauses 6 and 7 of Appendix B of Technical Code A” with “Chapter 7 of the connected asset commissioning, testing and information standard”.
(2) In Schedule 8.3, Technical Code B, clause 7(9A), replace “clauses 6 and 7 of Appendix B of Technical Code A” with “Chapter 7 of the connected asset commissioning, testing and information standard”.
27 Schedule 8.3, Technical Code C revoked
In Schedule 8.3, revoke Technical Code C — Operational communications.
Part 4
Amendments to Part 12 of the Electricity Industry
Participation Code
28 Clause 12.112 amended (Exceptions to clause
12.111)
(1) In clause 12.112(1)(ea)(i)(A)—
(a) insert “provided to and” after “commissioning plan”; and
(b) replace “under clause 2(6) to (9)” with “in accordance with clause 2(6) and (9)”.
(2) In clause 12.112(1)(ea)(i)(B),—
(a) insert “and agreed with” after “provided to”; and
(b) replace “under clause 2(6) to (9)” with “in accordance with clause 2(6) and (9)”.
29 Schedule 12.4, clause 10 amended
In Schedule 12.4, clause 10(4)(e), replace “Technical Code C of Schedule 8.3 of this Code” with “under the connected asset commissioning, testing and information standard”.
30 Schedule 12.6, paragraph 37.3 amended
In Schedule 12.6, paragraph 37.3(b)(1), replace “clause 2(f)” with “clause 2(5)”.
Part 5
Amendments to Part 13 of the Electricity Industry
Participation Code
31 Clause 13.29 amended (Standing data on grid capability to be provided to system operator)
In clause 13.29—
(a) insert “the system operator with asset capability statement” after “obligations to provide”; and
(b) delete “clauses 2(5) and (6) and 3(1) of”; and
(c) insert “and the connected asset commissioning, testing and information standard” after “Schedule 8.3”.
32 Clause 13.30 amended (Standing data on HVDC capability to be provided to system operator)
(1) In clause 13.30(1)—
(a) insert “the system operator with asset capability statement” after “obligations to provide”; and
(b) delete “clauses 2(5) and (6), and 3(1) of”; and
(c) insert “and the connected asset commissioning, testing and information standard” after “Schedule 8.3”.
(2) In clause 13.30(3)(a), replace “clause 2(6) to (9)” with “clause 2(6) and (9)” in each place.
33 Clause 13.31 amended (Standing data on transformer capability to be provided to system operator)
In clause 13.31—
(a) insert “the system operator with asset capability statement” after “obligations to provide”; and
(b) delete “clauses 2(5) and (6), and 3(1) of”; and
(c) insert “and the connected asset commissioning, testing and information standard” after “Schedule 8.3”.
34 Clause 13.32 replaced (Transmission grid capability information to be updated)
Replace clause 13.32 with:
13.32 Transmission grid capability information to be updated
In addition to the asset owner obligations to provide the system operator with asset capability statement information under Technical Code A of Schedule 8.3 and the connected asset commissioning, testing and information standard, and subject to that standard, each grid owner must submit to the system operator for each trading period of a schedule period, or for such longer period of time as agreed between the system operator and each grid owner, any updates to the information described in clauses 13.29 to 13.31 and 13.33(d).
35 Clause 13.33 amended (Grid owners must submit revised information to system operator)
In clause 13.33, replace—
(a) “1 hour” with “one hour”; and
(b)
“any timetable agreed
with the system operator under clause 3(1) of Technical Code A of
Schedule 8.3” with “any timetable requirements in the connected asset
commissioning, testing and information standard”.
Part 6
Amendments to Part 17 of the Electricity Industry
Participation Code
36 Clause 17.47 amended (Specific requirements for document transmission communication)
Revoke clause 17.47(2).
Schedule
New Subpart 7 of Part 8 inserted
Subpart 7—Connected
asset commissioning, testing and information standard
8.71 Contents of this subpart
This subpart contains provisions relating to the connected asset commissioning, testing and information standard.
Connected asset commissioning,
testing and information standard
8.72 System operator to comply with connected asset commissioning, testing and information standard
The system operator must comply with the connected asset commissioning, testing and information standard.
8.73 Incorporation of connected asset commissioning, testing and information standard by reference
(1) The connected asset commissioning, testing and information standard is incorporated by reference in this Code.
(2) Clauses 7.13 to 7.22 apply to any amendment or replacement of the connected asset commissioning, testing and information standard.
8.74 Content of connected asset commissioning, testing and information standard
A connected asset commissioning, testing and information standard must set out the following requirements on asset owners which are to assist the system operator in planning to comply, and complying, with the principal performance obligations and achieving the dispatch objective:
(a) the information that an asset owner must provide to the system operator relating to commissioning a new or existing asset or configuration of assets or decommissioning assets; and
(b) the information, including any modelling information, that an asset owner must provide to the system operator in an asset capability statement; and
(c) requirements for carrying out connection studies for an asset or configuration of assets; and
(d) requirements for periodically testing an asset or configuration of assets; and
(e) minimum requirements for operational communications between asset owners and the system operator; and
(f) requirements for high-speed monitors; and
(g) requirements for asset owners to provide information to the system operator to enable the system operator to assess the grid interface;
(h) requirements for an asset owner to provide information to the system operator if an asset owner reasonably believes that an asset may not comply with an asset owner performance obligation or with Technical Code A of Schedule 8.3;
(i) requirements on an asset owner to undertake remedial action or testing of its assets if the situation described in paragraph (h) arises;
(j) time frames that an asset owner must meet in relation to any of the matters in paragraphs (a) to (i) or within which information must be provided under this Code; and
(k) the manner and form in which information must be provided to the system operator or requirements that information is provided in a manner and form that is compatible with the system operator’s systems, as advised by the system operator.
8.75 Transitional provisions for the connected asset commissioning, testing and information standard
(1) Subject to subclause (4) and clause 8.76, an asset that is first electrically connected to the grid or to a local network before 1 July 2026 meets the requirements of the connected asset commissioning, testing and information standard if―
(a) except as specified in any exemption, dispensation, equivalence arrangement, or in any agreement between the asset owner and the system operator made before 1 July 2026, the asset complied, and continues to comply, with the requirements in Part 8 of this Code as they applied immediately before this clause came into effect; and
(b) the asset is not able to comply, without modification, with one or more of the requirements in the connected asset commissioning, testing and information standard; and
(c) the asset owner updates the asset capability statement for the asset to record that this subclause applies to the asset.
(2) Subject to subclauses (3) and (4), and clause 8.76, an asset that is first electrically connected to the grid or to a local network on or after 1 July 2026 and before 1 July 2027 meets the requirements of the connected asset commissioning, testing and information standard if―
(a) except as specified in any exemption, dispensation, equivalence arrangement, or in any agreement between the asset owner and system operator made before 1 July 2026, the asset complies, and continues to comply, with the requirements in Part 8 of this Code as they applied immediately before this clause came into effect; and
(b) the asset is not able to comply, without modification, with one or more of the requirements in the connected asset commissioning, testing and information standard; and
(c) the asset owner updates the asset capability statement for the asset to record that this subclause applies to the asset.
(3) In order for subclause (2) to apply to an asset, the asset owner must confirm in writing to the system operator before 1 August 2026 that the following has occurred in respect of the asset―
(a) the asset owner has secured financing that enables the asset owner to develop and commission the asset; and
(b) the asset owner has obtained all consents necessary to enable the asset owner to develop and commission the asset; and
(c) the asset owner has obtained rights to use the land on which the asset is to be located.
(4) Subclauses (1) and (2) do not apply in respect of the following:
(a) the time frame requirements in Chapter 1 of the connected asset commissioning, testing and information standard:
(b) the requirement in the connected asset commissioning, testing and information standard for connected asset owners to provide the system operator with indications and measurements in Chapter 8 of the connected asset commissioning, testing and information standard:
(c) subject to subclause (5), an asset from the date a modification is made to the asset that results in a 5% or greater change to the asset’s―
(i) MW rating; or
(ii) frequency response curve for 100 milliseconds or longer; or
(iii) voltage response curve for 100 milliseconds or longer.
(5) Subclause (4)(c) does not apply if―
(a) the asset owner and the system operator, acting reasonably, agree that subclause (1) or (2) should continue to apply to an asset notwithstanding the modification; or
(b) the modification is made so that one or more generating units comply with the maximum dead band requirement in clause 5(1)(c) of Technical Code A.
(6) An asset owner must, as soon as practicable,
update the asset capability statement for an asset to record when subclause (1) or
(2) ceases to apply to the asset.
(7) Each connected asset owner must comply with any obligation to provide the system operator with indications and measurements in accordance with Chapter 8 of the connected asset commissioning, testing and information standard by 1 July 2027.
8.76 Determination that there is a public benefit in the connected asset commissioning, testing and information standard applying to an asset
(1) If there is a benefit to the public in the connected asset commissioning, testing and information standard (or any part thereof) applying to an asset that would otherwise not have to comply with the connected asset commissioning, testing and information standard due to clause 8.75, the system operator may apply to the Authority for a determination under this clause.
(2) The Authority must issue a determination under this clause if satisfied that there is a benefit to the public in the connected asset commissioning, testing and information standard (or any part thereof) applying to the asset that is subject to the application.
(3) If a determination is issued under this clause, the owner of the asset must comply with the connected asset commissioning, testing and information standard (or any part thereof) to the extent provided for, and with effect from the date specified, in the determination.
Made at Wellington on 26
May 2026
Erik Westergaard
Acting Chair
Electricity Authority
Certified in order for signature:
Nichola Lambie Nick Crang
Manager Legal –
Legislation Consultant
Electricity Authority Duncan
Cotterill
25 May 2026 25 May 2026
|
|
|
|
Explanatory Note
This note is not part of the amendment but is
intended to indicate its general effect.
This
amendment to the Electricity Industry Participation Code 2010 (Code) comes into
force on 1 July 2026.
The
amendment amends provisions in the Code relating to common quality and
incorporates a new system operation document into the Code, the Connected Asset
Commissioning, Testing and Information Standard. The Standard updates and
replaces existing obligations in the Code relating to technical specifications for
assets connected or connecting to the power system.
|
|
|
|
|
This is secondary legislation issued under the authority of the Legislation Act 2019. |
|
|
Title |
Electricity Industry Participation Code (Connected Asset Commissioning, Testing and Information Standard) Amendment 2026 |
|
Principal or amendment |
|
|
Consolidated version |
|
|
Empowering Act and provisions |
Electricity Industry Act 2010, section 38 |
|
Replacement empowering Act and provisions |
|
|
Maker name |
|
|
Administering agency |
|
|
Date made |
26 May 2026 |
|
Publication date |
27 May 2026 |
|
Notification date |
26 May 2026 |
|
Commencement date |
1 July 2026 |
|
End date (when applicable) |
Not applicable |
|
Consolidation as at date |
|
|
Related instruments |
|