%20Amendment%202025(50036838).files/image002.png)
|
This
legislation is administered by the Electricity Authority. For more
information please see: Website: https://www.ea.govt.nz/ Contact
phone: +64 4 460 8860 Contact
address: PO Box 10041, Wellington 6143 |
Electricity
Industry Participation Code (Transmission Pricing Methodology Related
Amendments) Amendment 2025
This amendment to the Electricity
Industry Participation Code 2010 (Code) is made under section 38 of the
Electricity Industry Act 2010 (Act) by the Electricity Authority, having
complied with section 39 of that Act.
Amendment
1 Title
This is the Electricity Industry Participation
Code (Transmission Pricing Methodology Related Amendments) Amendment 2025.
2 Commencement
(1) Clauses 6(1), 6(3), 8, 9(1), 10, 11, 12, and 13 come into force
on 15 December 2025.
(2) The remaining clauses in this amendment come into force on 1
April 2027.
3 Code
amended
This amendment amends the
Electricity Industry Participation Code 2010.
4 Clause
3 of Schedule 12.4 amended (General Definitions)
In
clause 3 of Schedule 12.4, insert in its appropriate alphabetical order:
revaluation means—
(a) for a connection asset
or anticipatory connection asset and financial year, the amount
calculated under clause 27A for the asset and financial year; and
(b) for an asset comprised in a BBI
(other than an anticipatory BBI) and a financial year, the amount
calculated under subclause 39(2A) for the asset and financial year
5 Clause 26 of Schedule 12.4 amended (Asset
Component)
In clause 26 of Schedule 12.4, replace
subclauses (7) and (8) with:
(7) The
connection asset return rate for a pricing
year (ARR) is calculated as follows:
![]()
where
|
r |
is Transpower’s
PQ WACC (pre-tax) for the pricing
year |
|
|
|
|
Vtotal |
is the total closing
RAB value of all connection assets
for the preceding financial year |
|
|
|
|
Vtotal anticipatory |
is the part of Vtotal attributable to anticipatory connection assets, as
determined by Transpower |
|
|
|
|
Dtotal |
is total depreciation
of all connection assets other
than investment agreement assets
during the preceding financial year, excluding accelerated depreciation |
|
|
|
|
Dtotal anticipatory |
is the part of Dtotal attributable to anticipatory connection assets, as
determined by Transpower |
|
|
|
|
RVtotal |
is total revaluation for all connection
assets and the preceding financial year |
|
|
|
|
RVtotal anticipatory |
is the part of RVtotal
attributable to anticipatory connection assets, as determined by Transpower |
|
|
|
|
RCtotal |
is the total replacement
cost of all connection assets
other than investment agreement assets
and anticipatory connection assets at
the end of the preceding financial
year. |
%20Amendment%202025(50036838).files/image007.png)
(8) The
discounted connection asset return
rate for a pricing year (DARR) is
calculated as follows:
![]()
where
|
r |
is Transpower’s PQ WACC (pre-tax) for
the pricing year |
|
|
|
|
|
|
Vtotal
anticipatory |
is the
part of the total closing RAB value
of all connection assets for the
preceding financial year
attributable to anticipatory
connection assets, as determined by Transpower |
|
|
|
|
|
|
Dtotal
anticipatory |
is the
part of total depreciation of all connection assets other than investment agreement assets during
the preceding financial year, excluding accelerated depreciation, attributable to anticipatory connection assets, as determined by Transpower |
|
|
|
|
|
|
RVtotal anticipatory |
is
total revaluation for all anticipatory connection assets and
the preceding financial year |
|
|
|
|
|
|
RC′total |
is the
total replacement cost of all connection assets (including connection assets that are investment agreement assets) other
than anticipatory connection assets
at the end of the preceding financial
year. |
|
6 Clause 27 of Schedule 12.4 amended (Anticipatory
BBIs)
(1) In clause 27(2)(b) of Schedule 12.4,
replace “CVC” with “COVC” in each place.
(2) In clause 27(2) of Schedule 12.4, replace
paragraph (b) with:
(b) that has a covered cost for the pricing
year (COVC) calculated as follows:
![]()
where
|
r |
|
|
|
|
|
|
|
Vanticipatory |
is the part of the total closing RAB value for the preceding financial year attributable to the anticipatory connection asset, as determined by Transpower |
|
|
|
|
|
|
Danticipatory |
is the part of total depreciation during the preceding financial year, excluding accelerated
depreciation, attributable to the anticipatory
connection asset, as determined by Transpower |
|
|
|
|
|
|
RVanticipatory |
|
|
(3) In clause 27(2)(d), replace “cand” with
“and”.
7 New clause 27A of Schedule 12.4 inserted
(Revaluation for Connection Assets and Anticipatory Connection Assets)
After clause 27 of Schedule 12.4, insert:
27A Revaluation for Connection
Assets and Anticipatory Connection Assets
Revaluation
for a connection asset or anticipatory connection asset and financial
year (RV) is calculated as follows:
![]()
where
|
RVIM |
is revaluation for the asset and financial
year calculated under the Transpower IMs, as determined by Transpower |
|
|
|
|
FRR |
is the forecast revaluation rate used to
calculate the forecast revaluation component of maximum revenue for
the pricing year starting immediately before the start of the financial
year |
|
|
|
|
RR |
is the revaluation rate for the financial year
calculated under the Transpower IMs |
|
|
|
|
r |
is the corporate tax rate, as defined in the Transpower
IMs, at the start of the financial year. |
8 Clause 35 of Schedule 12.4 amended (Calculation
of Benefit-based Charges)
In clause 35(2) of
Schedule 12.4, replace “CC” with “COVC” in each place.
9 Clause 39 of Schedule 12.4 amended (Covered
Cost)
(1) In clause 39(1) of Schedule 12.4,
replace “CC” with “COVC” in each place.
(2) In clause 39 of Schedule 12.4, replace
subclause (2) with:
(2) The capital charge for an asset and financial year (C) is calculated—
(a) if the asset had an opening RAB value for the financial
year, as follows:
![]()
where
|
r |
is Transpower’s
PQ WACC (vanilla) at the start of the financial year |
|
|
|
|
V |
is, subject to subclause 7, the opening RAB value for the asset and financial year |
|
|
|
|
RV |
is revaluation for the asset and financial
year; or |
(b) if the
asset was commissioned during the financial year, as follows:
![]()
where
|
V |
is, subject to subclause (7), the asset’s value of commissioned asset |
|
|
|
|
r |
is Transpower’s
PQ WACC (vanilla) at the start of the financial year |
|
|
|
|
m |
is the month of the financial year during which the asset was commissioned (for example, m = 3 for September). |
(2A) Revaluation for an asset comprised in a BBI and a financial
year (RV) is calculated as follows:
![]()
where
|
RVIM |
is revaluation for the asset and financial
year calculated under the Transpower IMs, as determined by Transpower |
|
|
|
|
FRR |
is the forecast revaluation rate used to
calculate the forecast revaluation component of maximum revenue for
the pricing year starting immediately before the start of the financial
year |
|
|
|
|
RR |
is the revaluation rate for the financial year
calculated under the Transpower IMs. |
10 Clause 83 of Schedule 12.4 amended
(Benefit-based Charge Adjustment Event: New Customer)
(1) In clause 83 of Schedule 12.4, replace
subclause (5B) with:
(5B) Subject to subclause
(9A), the new customer’s simple method
BBC cap (SMBC) is calculated as follows:
![]()
where
|
E |
is Transpower’s estimate of the value of the new customer’s intra-regional allocator
for the relevant regional customer
group under paragraph 83(3)(a) |
|
|
|
|
J |
is the number of customers of the same type as the new
customer (generator or connected
asset owner) as at the later of 1 April 2023 and the start of the
relevant simple method period— (a)
at
the new
customer’s connection location; or (b)
if
there
are no such customers at the new customer’s connection location, at
the connection location
electrically closest to the new customer’s
connection location at which there is or was 1 or more such customers, as determined by Transpower, each such customer being customer
j |
|
|
|
|
BBCj
total |
is:
where CAij is customer j’s BBI customer allocation, as at the later of 1
April 2023 and the start of the relevant simple method period, for post-2019 BBIs under the simple
method for the regional customer group in which customer j’s connection
location is located and in respect of investment region i COVCi
total is
the total covered cost of all post-2019 BBIs
under the simple method in investment
region i at the time the new customer connected to the grid |
|
|
|
|
Ej |
is the value of customer j’s intra-regional allocator,
as at the later of 1 April 2023 and the start of the relevant simple method period, for the regional
customer group in
which customer j’s connection location is located. |
(2) In clause 83(5C)(a)
of Schedule 12.4, definition of BBC(3) total, replace “BBIs” with “post-2019 BBIs”.
(3) In clause 83(5C) of
Schedule 12.4, replace paragraph (b) with:
(b) calculate
the new customer’s BBI customer
allocation for each relevant post-2019
BBI (CA) as follows:
![]()
where
|
SMBCregion |
is
the part of the new customer’s simple
method benefit cap attributed to the investment
region in which the relevant post-2019
BBI is located under paragraph (a) |
|
|
|
|
COVCregion total |
is
the total covered cost of all
relevant post-2019 BBIs under the simple method located in the investment region at the
time the new customer connected to the grid; and |
11 Clause 97 of Schedule 12.4 amended
(Reassignment Amount)
In clause 97 of Schedule 12.4, replace “CC” with “COVC”
in each place.
12 Clause 102
of Schedule 12.4 amended (Forecast Peak Loading and Reassignment Factors)
In clause
102(4) of Schedule 12.4:
(a) replace “CCtotal” with “COVCtotal” in each place; and
(b) replace “CCi” with “COVCi” in each place.
13 Clause 110
of Schedule 12.4 amended (Cap and Cap Condition)
In clause
110(2) of Schedule 12.4, replace “CC” with “CAPC” in each place.
Made at Wellington on November 2025
Anna Kominik
Chair
Electricity Authority
Certified in order for signature:
Nicholai Mumford Rachael
Brown
Senior Legal Counsel Partner
Electricity Authority Bell
Gully
November
2025 November
2025
Explanatory Note
This note is not
part of the amendment but is intended to indicate its general effect.
Clauses 6(1), 6(3), 8,
9(1), 10, 11, 12, and 13 of this amendment to the Electricity Industry
Participation Code 2010 (Code) come into force on 15 December 2025. The
remaining clauses come into force on 1 April 2027.
The
amendment amends Schedule 12.4 of the Code (the
transmission pricing methodology (TPM)) to:
·
incorporate indexation to ensure that
costs recovered through the TPM remain broadly aligned with the way costs are
calculated for Transpower under Part 4 of the Commerce Act;
·
standardise the allocators used in the
simple method benefit-based charges (BBC) cap formula to ensure a consistent
calculation of the cap in any pricing period; and
·
make minor editorial changes to make the TPM
clearer.
|
|
|
|
|
This is secondary legislation issued under the authority of the Legislation Act 2019. |
|
|
Title |
|
|
Principal or amendment |
|
|
Consolidated version |
|
|
Empowering Act and provisions |
|
|
Replacement empowering Act and provisions |
|
|
Maker name |
|
|
Administering agency |
|
|
Date made |
6 November 2025 |
|
Publication date |
11 November 2025 |
|
Notification date |
11 November 2025 |
|
Commencement date |
|
|
End date (when applicable) |
Not applicable |
|
Consolidation as at date |
Not applicable |
|
Related instruments |
|