This legislation is administered by the Electricity Authority. For more information please see: Website: https://www.ea.govt.nz/
Contact phone: +64 4 460 8860
Contact address: PO Box 10041, Wellington 6143
This amendment to the Electricity Industry Participation Code 2010 (Code) is made under section 38 of the Electricity Industry Act 2010 (Act) by the Electricity Authority having complied with section 39 of that Act.
Title 2
Commencement 2
Code amended 2
Clause 1.1 amended (Interpretation) 2
6
7
New clause 6.3A inserted (Limits on maximum export power and installed generation)
New clause 6.3B inserted (Requirements for inverters)
3
4
Clause 6.3 amended (Distributors must make information publicly available) 3
Clause 6.4 amended (Process for obtaining approval) 4
Schedule 6.1
New clause 1E of Schedule 6.1 inserted
New clause 1F of Scheule 6.1 inserted
5
6
Clause 1D of Schedule 6.1 amended 5
Clause 2 of Schedule 6.1 amended 7
Clause 9B of Schedule 6.1 amended 7
Clause 8 revoked 7
Clause 13 amended 7
Clause 26 amended 8
This is the Electricity Industry Participation Code (Export Limits) Amendment 2026.
This amendment comes into force on 11 May 2026.
Parts 1 and 2 of this amendment amend the Electricity Industry Participation Code 2010 (the Code).
Part 3 of this amendment amends the Electricity Industry Participation Code Amendment (Application for Distributed Generation) 2021.
Part 4 of this amendment amends the Electricity Industry Participation Code (Network Connections) Amendment 2026.
In clause 1.1(1), insert in their appropriate alphabetical order:
bespoke export limits assessment methodology for distributors means a methodology that all distributors have jointly adopted for the purposes of Part 6 that, if made, distributors must use to perform network studies that determine maximum export power, inverter settings, or other conditions that will apply to an ICP that is the subject of an application to connect distributed generation
dynamic export limit means an export limit for distributed generation under Part 6 that allows at least the maximum export power threshold when there is no export congestion and remotely adjusts the export limit of the smart inverter in real-time to continuously respond to network export congestion
export limits assessment methodology for distributors means a methodology that all
distributors have jointly adopted for the purposes of Part 6 that, if made, distributors
must use to perform network studies that determine the maximum export power
threshold, or inverter settings, that apply to an ICP or group of ICPs connected to a section of network, whether or not an application to connect distributed generation has been received for that ICP or one of those ICPs
flexible export limit means an export limit for distributed generation under Part 6 that allows at least the maximum export power threshold when there is no export congestion and adjusts the export limit based on predefined schedules, forecasts, or operating scenarios that are programmed into the inverter or remotely communicated to the smart inverter
Replace clause 6.3(2)(dc) with:
(dc) the maximum export power threshold and the export limits assessment methodology for distributors and the bespoke export limits assessment methodology for distributors used to determine that threshold, for locations at which the distributor has set a maximum export power threshold; and
6.3A Limits on maximum export power and installed generation
A distributor must not set a limit on the nameplate capacity of distributed generation that may be installed at an ICP for applications made under Part 1 or Part 1A.
A distributor may set a limit on the maximum export power that may be injected into the network from an ICP (the ‘maximum export power threshold’) for applications made under Part 1A, provided the maximum export power threshold is not set lower than 10kW except in accordance with subclause (3).
A distributor may set a limit on the maximum export power threshold that applies to an ICP or group of ICPs of lower than 10kW provided the distributor has undertaken a network study that—
shows a lower maximum export power threshold is necessary to maintain voltage within the allowable tolerances or network safety, including, but not limited to, any issues reasonably likely to affect power quality or reliability, such as thermal constraints, in the section of the network that carries electricity from the ICP or group of ICPs to the network; and
only takes into account distributed generation that is connected to, and applications that are being assessed to connect distributed generation to, the section of network that carries electricity from the ICP or group of ICPs to the network; and
After clause 6.3 insert:
if the lower maximum export power threshold is part of a dynamic export limit
or a flexible export limit—
the lower maximum export power threshold is only active during the time periods when the network study has identified that the lower maximum export power threshold is necessary; and
the dynamic export limit or a flexible export limit does not operate when the network is not constrained.
From 11 November 2026 any network study undertaken under subclause (3) must use the export limits assessment methodology for distributors.
The distributor must—
publish any network study undertaken under subclause (3); and
publish easily accessible lists or maps of areas on the network where the lower
maximum export power threshold or different settings applies; and
repeat the network study where there has been a change on the network likely to alter the outcome of network study.
Before clause 6.4, insert:
6.3B Requirements for inverters
From 11 September 2026 subject to subclause (2), a distributor must require a distributed generator that injects electricity at low voltage to use an inverter that is compliant with, and applies, the “Australia A” inverter settings specified in, AS/NZS477.2:2020 incorporating Amendments No. 1 and 2.
A distributor may specify different inverter settings to those required by subclause (1) in its connection and operating standards if—
the distributor has undertaken a network study that shows different settings are necessary to maintain voltage within the allowable tolerances and/or network safety, including any issues reasonably likely to affect power quality or reliability, such as thermal constraints, in the section of network for or an ICP or group of ICPs; and
any alternative inverter settings are consistent with the “allowed range” in Tables 3.6, 3.7, 3.8, and 4.3 of AS/NZS 4777.2:2020 incorporating Amendments No. 1
and 2.
From 11 November 2026 any network study undertaken under subclause (2) must use the export limits assessment methodology for distributors.
The distributor must—
publish any network study undertaken under subclause (2); and
repeat the network study where there has been a change on the network likely to alter the outcome of network study.
In clause 6.4(1)(d), insert “, maximum export power,” after “nameplate capacity,”.
Schedule 6.1
In clause 1D(1) of Schedule 6.1—
in paragraph (a), replace “2016” with “2024”; and
in paragraph(b)(i), insert “incorporating Amendments No. 1 and 2” after “AS/NZS 4777.2:2020”; and
after paragraph (b), insert:
(c) will inject electricity less than or equal to the maximum export power threshold set by the distributor in clause 6.3A(2).
In clause 1D(2) of Schedule 6.1—
in the chapeau, replace “Until 1 September 2026, a” with “A”; and
in paragraph (c), replace “meet the distributor’s connection and operation standards” with “comply with clause 6.3B(1) or meet the distributor’s inverter settings specified in accordance with clause 6.3B(2)”; and
in paragraph (d), delete “in its connection and operation standards”.
After clause 1D of Schedule 6.1, insert:
(1) Despite clause 6.3A or 6.3B, a distributed generator may submit an application to connect distributed generation that has greater capacity than the distributor’s maximum export power threshold or has different inverter settings than those specified in accordance with clause 6.3B(2), and the distributor must assess that application in good faith, under—
Part 1 or Part 2 of Schedule 6.1 for distributed generation greater than the
Part 1 or Part 2 of Schedule 6.1 for distributed generation using different inverter settings.
From 11 November 2026, any network study undertaken for a Part 2 application as part of the assessment under subclause (1)—
must use the bespoke export limits assessment methodology for distributors; and
must, if it contains an analysis which deviates from the bespoke export limits assessment methodology for distributors, include the reasons for the deviation; and
must be provided to the distributed generator before determining the application; and
must be published by the distributor unless the distributed generator does not give consent to publish.
Unless the distributed generator agrees otherwise, where practicable, the distributor
must provide the distributed generator with the following:
alternative export limits:
the conditions the distributed generator must meet in order for the distributor
to approve those alternative export limits:
the associated costs if the distributed generator chooses an alternative export limit.
(4) If an application is approved, the distributor will adjust the maximum export power threshold for that ICP to the new maximum export power threshold determined during the application process.
Before clause 2 of Schedule 6.1, insert:
A distributed generator may dispute any limit set by a distributor on maximum export power or inverter settings that operate to limit maximum export power, or associated conditions set by the distributor, arising from a network study using the bespoke export limits assessment methodology for distributors by providing written notice of the dispute to the distributor.
A distributed generator may not dispute the bespoke export limits assessment methodology for distributors itself.
A dispute may only be raised up to 30 days after the distributor has notified the distributed generator of the results or the limit on maximum export power or inverter settings that operate to limit maximum export power set by a distributor or associated conditions set by the distributor.
If a distributed generator notifies the distributor of a dispute under subclause (1), the
must attempt to resolve the dispute in good faith and without unreasonable delay; and
may escalate the dispute to their chief executive officer, or a person holding the equivalent position, if the dispute cannot be resolved in good faith and without unreasonable delay; and
the chief executive officer, or person holding the equivalent position, may—
refer the dispute to mediation with costs to lie where they fall; and
if the parties cannot agree to a mediator within 5 business days of referring the dispute to mediation, the parties must submit a request to AMINZ (or its replacement organisation) to select a mediator and determine the mediator’s fee; and
if the dispute cannot be resolved the distributor and the distributed generator
must—
refer the dispute to arbitration under the Arbitration Act 1996; and
if the parties cannot agree to an arbitrator within 5 business days of referring the dispute to arbitration, the parties must submit a request to AMINZ (or its replacement organisation) to select an arbitrator and determine the arbitrator’s fee.
If the parties refer the dispute to arbitration, either party may commission an independent engineering review of the issues being disputed, in which case—
the review must be conducted by a suitable engineering consultant nominated by the Electricity Engineers Association (or its replacement organisation); and
the party commissioning the review must initially pay the cost of the review, with the final allocation of the costs between the parties determined by the arbitrator.
In clause 2(3)(aa)(iv) of Schedule 6.1, insert “, maximum export power,” after “nameplate capacity”.
In clause 2(3)(b) of Schedule 6.1, insert “or maximum export power,” after “nameplate capacity”.
In clause 2(3)(ba) of Schedule 6.1, in the chapeau, insert “, maximum export power,” after “nameplate capacity”.
In clause 2(3)(ba)(i) of Schedule 6.1, insert “and maximum export power” after “nameplate capacity”.
In clause 9B(1)(d) of Schedule 6.1, insert “, maximum export power,” after “nameplate capacity”.
In clause 9B(2)(f) of Schedule 6.1, insert “incorporating Amendments No.1 and 2” after “AS/NZS 4777.2:2020”.
In clause 9B(2A) of Schedule 6.1—
in the chapeau, replace “Until 1 September 2026, an” with “An”; and
(a) confirmation the inverter conforms with the inverter settings specified in clause
6.3B(1) or 6.3B(2); and
replace paragraph (a) with:
in paragraph (b), delete “in its connection and operation standards”.
Revoke clause 8.
(dc) the maximum export power threshold and the export limits assessment methodology for distributors and the bespoke export limits assessment
Replace the amendments to clause 6.3(2)(dc) of the Code in clause 13 by replacing that subparagraph with:
methodology for distributors used to determine that threshold, for locations at which the distributor has set a maximum export power threshold; and
4 When application may be made under Process 1A
A distributed generator may elect to apply to a distributor under Process 1A instead of Process 1 if the distributed generation to which the application relates—
is designed and installed in accordance with AS/NZS 4777.1:2024; and
incorporates an inverter that—
has been tested and issued a Declaration of Conformity with AS/NZS 4777.2:2020 incorporating Amendments No. 1 and 2 by a laboratory with accreditation issued or recognised by International Accreditation New Zealand; and
has settings that meet the distributor’s connection and operation standards; and
will inject electricity less than or equal to the maximum export power threshold set by the distributor in clause 6.3A(2).
A distributed generator may only elect to apply to a distributor under Process 1A instead of Process 1, if the distributed generation to which the application relates has, in addition to the requirements in subclause (1)—
a volt-watt response mode; and
a volt-var response mode; and
control settings and volt response mode settings that comply with clause 6.3B(1) or meet the distributor’s inverter settings specified in accordance with clause
6.3B(2); and
(d) a maximum export power limit at the ICP of the distributed generator that does not exceed the maximum export power threshold, if any, specified by the distributor.
Replace the amendments to clause 4 of Schedule 6.1 of the Code in clause 26 by replacing clause 4 with:
4A Applications that do not comply with distributor thresholds or inverter settings
(1) Despite clause 6.3A or 6.3B, a distributed generator may submit an application to connect distributed generation that has greater capacity than the distributor’s maximum export power threshold or has different inverter settings than those specified in accordance with clause 6.3B(2), and the distributor must assess that application in good faith, under—
Process 1 of Schedule 6.1 for distributed generation greater than the maximum export power threshold; or
Process 1 or Process 2 of Schedule 6.1 for distributed generation using different inverter settings.
(2) From 11 November 2026, any network study undertaken for a Process 2 application as part of the assessment under subclause (1)—
Amend clause 26 by inserting a new clause 4A to be inserted in the Code after clause 4 of Schedule 6.1 as follows:
must use the bespoke export limits assessment methodology for distributors; and
must, if it contains any analysis which deviates from the bespoke export limits assessment methodology for distributors, include the reasons for the deviation; and
must be provided to the distributed generator before determining the application; and
must be published by the distributor unless the distributed generator does not give consent to publish.
Unless the distributed generator agrees otherwise, where practicable, the distributor
must provide the distributed generator with the following:
alternative export limits:
the conditions the distributed generator must meet in order for the distributor
to approve those alternative export limits:
the associated costs if the distributed generator chooses an alternative export limit.
If an application is approved, the distributor will adjust the maximum export power threshold for that ICP to the new maximum export power threshold determined during the application process.
Amend clause 26 by inserting a new clause 4B in the Code before the cross heading “Confidentiality” in Schedule 6.1 as follows:
A distributed generator may dispute any limit set by a distributor on maximum export power or inverter settings that operate to limit maximum export power, or associated conditions set by the distributor, arising from a network study using the bespoke export limits assessment methodology for distributors by providing written notice of the dispute to the distributor.
A distributed generator may not dispute the bespoke export limits assessment methodology for distributors itself.
A dispute may only be raised up to 30 days after the distributor has notified the distributed generator of the results or the limit on maximum export power or inverter settings that operate to limit maximum export power set by a distributor or associated conditions set by the distributor.
If a distributed generator notifies the distributor of a dispute under subclause (1), the
must attempt to resolve the dispute in good faith and without unreasonable delay; and
may escalate the dispute to their chief executive officer, or a person holding the equivalent position, if the dispute cannot be resolved in good faith and without unreasonable delay; and
the chief executive officer, or person holding the equivalent position, may—
refer the dispute to mediation with costs to lie where they fall; and
if the parties cannot agree to a mediator within 5 business days of referring the dispute to mediation, the parties must submit a request to AMINZ (or its
replacement organisation) to select a mediator and determine the mediator’s fee; and
if the dispute cannot be resolved the distributor and the distributed generator
must—
refer the dispute to arbitration under the Arbitration Act 1996; and
if the parties cannot agree to an arbitrator within 5 business days of referring the dispute to arbitration, the parties must submit a request to AMINZ (or its replacement organisation) to select an arbitrator and determine the arbitrator’s fee.
If the parties refer the dispute to arbitration, either party may commission an independent engineering review of the issues being disputed, in which case—
the review must be conducted by a suitable engineering consultant nominated by the Electricity Engineers Association (or its replacement organisation); and
the party commissioning the review must initially pay the cost of the review, with the final allocation of the costs between the parties determined by the arbitrator.
Amend clause 26 by making the following amendments to new clause 2(2) of Schedule 6.1, Appendix 1, Process 1 of the Code:
in paragraph (b)(iv), insert “nameplate capacity,” before “maximum export power”; and
in paragraph (c), insert “nameplate capacity or” before “maximum export power”; and
in the chapeau of paragraph (d), insert “nameplate capacity,” before “maximum export power”; and
in paragraph (d)(i), insert “nameplate capacity or” before “maximum export power”; and
in paragraph (d)(ii), insert “nameplate capacity or” before “maximum export power”.
Amend clause 26 by making the following amendments to new clause 2 of Schedule 6.1, Appendix 1A, Process 1A of the Code:
in clause 2(1)(d), insert “nameplate capacity,” before “maximum export power”; and
in clause 2(2)(f), insert “incorporating Amendments No.1 and 2” after “AS/NZS 4777.2:2020”; and
in clause 2, replace subclause (3) with:
An application must also include—
confirmation the inverter conforms with the inverter settings specified in clause
6.3B(1) or 6.3B(2); and
confirmation that the distributed generation has a maximum export power limit that does not exceed the maximum export power threshold, if any, specified by the distributor; and
the maximum export power of the distributed generation.
Made at Wellington on 9 April 2026
Erik Westergaard Acting Chair Electricity Authority
Certified in order for signature:
Amy Williams Nick Crang
Senior Legal Counsel Consultant
Electricity Authority Duncan Cotterill
9 April 2026 8 April 2026
This note is not part of the amendment, but is intended to indicate its general effect.
This amendment to the Electricity Industry Participation Code 2010 comes into force on 11 May 2026, except for clauses 15 to 20, which come into force on 1 December 2026, immediately after the Electricity Industry Participation Code (Network Connections) Amendment 2026 comes into force.
The amendment amends Parts 1 and 6 of the Electricity Industry Participation Code 2010 (“Code”) to maximise the benefits from distributed generation by:
introducing a default static export limit of 10kW for applications under the Part 1A process in the Code for straightforward, small-scale DG connections up to 10kW, or offer a dynamic or flexible export limit (with a minimum 10kW limit when the export is not being controlled during congested periods), or apply lower static limits where justified, after a standardised network assessment;
introducing:
a standardised Export Limits Assessment Methodology for small scale DG where distributors propose limits below 10kW for individual installation control points (ICPs) or small groups of ICPs connected to the same section of
low voltage line, or to assess alternative dynamic or flexible limits as noted above; and
a Bespoke Export Limits Assessment Methodology for larger scale DG greater than 10kW, under the Part 2 DG Code application process;
updating inverter standards and settings to require:
default adoption of ‘Australia A’ voltage response, frequency and protection settings in the inverter performance standard AS/NZS 4777.2:2020;
adherence to the inverter installation standard AS/NZS 4777.1:2024 for Part 1A DG applications; and
adherence to the inverter performance standard AS/NZS 4777.2:2020 (including amendments 1 and 2) for all low voltage DG applications;
making further consequential amendments to reflect these changes.
The amendment also amends the Electricity Industry Participation Code Amendment (Application for Distributed Generation) 2021 to revoke clause 8 of that instrument, removing the automatic revocation of the amendments made in clauses 4, 5, 6(2) and 7(3) of that instrument.
This is secondary legislation issued under the authority of the Legislation Act 2019. | |
Title | Electricity Industry Participation (Export Limits) Amendment 2026 |
Principal or amendment | Principal |
Consolidated version | No |
Empowering Act and provisions | Electricity Industry Act 2010, section 38 |
Replacement empowering Act and provisions | Not applicable |
Maker name | Electricity Authority |
Administering agency | Electricity Authority |
Date made | 09 April 2026 |
Publication date | 13 April 2026 |
Notification date | 13 April 2026 |
Commencement date | 11 May 2026 |
End date (when applicable) | Not applicable |
Consolidation as at date | Not applicable |
Related instruments | Electricity Industry Participation Code 2010 |