Explanatory note

This note is not part of the amendment but is intended to indicate its general effect.

This amendment to the Electricity Industry Participation Code 2010 (Code) comes into force on 1 April 2026.

The amendment inserts a new Part 6B into the Code to implement requirements on distributors to comply with mandatory connection pricing methodologies, information requirements and other requirements for load connections. The requirements consist of:

  • Enhancement cost allocation requirements. This requires connection charges to be determined with reference to a “relevant minimum scheme”, with enhancement costs (if any) allocated to the party that seeks the enhancement.
  • Capacity costing requirements. This requires that any upstream costs allocated to access seekers, use published rates to allocate costs as capacity headroom is consumed (not as it is built).
  • Pioneer scheme requirements. This requires rebates to be paid to the “pioneers” that fund network extensions as subsequent parties connect.
  • Connection charge reconciliation requirement. This requires distributors to prepare and provide a standardised breakdown of connection charges into incremental and network cost components.

Legislative information

Title Electricity Industry Participation Code (Connection Pricing Requirements) Amendment 2025
Principal or amendment Amendment
Consolidated version No
Empowering Act and provisions Electricity Industry Act 2010, section 38
Replacement empowering Act and provisions Not applicable
Maker name Electricity Authority
Administering agency Electricity Authority
Date made 4 September 2025
Publication date 8 September 2025
Notification date Not applicable
Commencement date 1 April 2026
End date Not applicable
Consolidation as at date Not applicable
Related instruments Electricity Industry Participation Code 2010