Electricity Industry Participation Code 2010

Electricity Industry Participation Code 2010

Part 10: Metering

10.1

Contents of this Part

This Part provides for—

  • (a) ensuring the accuracy of the clearing and settlement of electricity trading in the wholesale electricity market by regulating how existing and new metering installations are used to accurately measure and record electricity conveyed; and
  • (b) the responsibility for ensuring a metering installation is in place; and
  • (c) the responsibility for ensuring the compliance of metering installations; and
  • (d) the processes and procedures that apply to testing, calibrating, and certifying metering installations; and
  • (e) [Revoked]
  • (f) the processes and procedures that apply to approving ATHs; and
  • (g) regulating the data use, handling, storage, and transmission processes associated with metering installations and metering data; and
  • (h) regulating metering installations that are used for electricity trading; and
  • (i) the processes and procedures relating to the registry and information for the purposes of Part 15; and
  • (j) related matters, processes, and procedures.

Clause 10.1(e): revoked, on 1 June 2017, by clause 5 of the Electricity Industry Participation Code Amendment (Requirements and Processes for Audits) 2016.

Subpart 1—Preliminary provisions

10.2

Authority’s discretion and powers

  • (1) A clause in this Part that gives the Authority a discretion or power—
    • (a) confers an absolute discretion to the Authority
      • (i) taking into account any specific requirements set out in the clause; and
      • (ii) observing the principles of natural justice; and
    • (b) to approve an application by a person to carry out an activity under this Part, may be exercised by—
      • (i) granting the application; or
      • (ii) declining the application; or
      • (iii) granting the application with any conditions that the Authority considers appropriate in the circumstances.
  • (2) The Authority, when exercising a discretion or power under this Part, must act in a timely manner.
  • (3) The Authority must give an applicant reasons for its decision if the Authority
    • (a) declines an application for approval to carry out an activity under this Part; or
    • (b) grants an application for approval to carry out an activity under this Part with any conditions that the Authority considers appropriate in the circumstances.
  • (4) Nothing in this Part limits any of the Authority’s rights and obligations under the Act.

Heading: amended, on 5 October 2017, by clause 157(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

Clause 10.2(1), (2) and (3): amended, on 5 October 2017, by clause 157(2) and (3) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

10.3

Use of contractors

  • (1) A participant may perform its obligations and exercise its rights under this Part by using a contractor.
  • (2) A participant who uses a contractor to perform the participant’s obligation under this Part—
    • (a) remains responsible and liable for, and is not released from, the obligation, or any other obligation under this Part; and
    • (b) cannot assert that it is not responsible or liable for the obligation on the ground that the contractor—
      • (i) has done or not done something; or
      • (ii) has failed to meet a relevant standard; and
    • (c) must ensure that the contractor has at least the specified level of skill, expertise, experience, or qualification that the participant would be required to have if it were performing the obligation itself.
  • (3) If a participant is a party to a contract or arrangement containing a provision, or part of a provision, which is inconsistent with this Part, the provision, or part of the provision, has no effect.

10.4

Participant obligations

  • (1) If this Part provides that a participant must obtain a consumer’s consent, approval, or authorisation, the participant must, if relevant, ensure that the consent, approval, or authorisation extends, for the full term of the contract or arrangement in relation to which the consent, approval, or authorisation is given, to any participant who may be expected to rely on that consent, approval, or authorisation to remain in compliance with this Part.
  • (2) If a participant (participant A) incorrectly populates the registry, causing another participant (participant B) to breach an obligation under this Code, and participant B relies, in good faith, on the incorrect information in the registry, participant B has not breached its obligation.
  • (3) A participant must comply with all applicable enactments.
  • (4) A participant is, unless it is specified otherwise in this Part, responsible for all costs of its compliance with this Part.
  • (5) A reference in this Part to a participant knowing, or being or becoming aware of, a fact, includes reference to when a participant should have, in the circumstances, known, or been or become aware of, the fact.

Clause 10.4(2): amended, on 5 October 2017, by clause 158 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

10.5

References to timing

  • (1) If an event is described in this Part as taking place on, or an obligation becoming effective from, a date, it takes place on, or becomes effective from, the beginning of the first trading period on the date, unless specified otherwise.
  • (2) If a time period is expressed in this Part as—
    • (a) commencing on a date, it commences at the beginning of the first trading period on the date, unless specified otherwise:
    • (b) ending on a date, it ends at the close of the final trading period on the date, unless specified otherwise.

10.6

Participant to provide accurate information

  • (1) A participant must take all practicable steps to ensure that information that it provides under this Part is—
    • (a) complete and accurate:
    • (b) not misleading or deceptive:
    • (c) not likely to mislead or deceive.
  • (2) If a participant becomes aware that the information the participant provided under this Part does not comply with subclause (1)(a) to (c), even if the participant has taken all practicable steps to ensure that the information complies, the participant must, except if clause 10.43 applies, as soon as practicable provide such further information, or corrected information, as is necessary to ensure that the information complies with subclause (1)(a) to (c).

Clause 10.6(2): substituted, on 19 December 2014, by clause 20 of the Electricity Industry Participation Code Amendment (Minor Code Amendments) (No 3) 2014.

10.7

Access to premises in which metering installation located

  • (1) In this clause, access to a metering installation
    • (a) means physical access to the premises in which the metering installation is located; but
    • (b) does not include access to the following, which are dealt with in Schedule 10.6:
      • (i) raw meter data from the metering installation; and
      • (ii) the metering installation itself and its metering components.
  • (2) A reconciliation participant must, upon receiving a request from 1 of the following parties, arrange access to a metering installation for which it is responsible:
    • (a) the Authority:
    • (b) an ATH:
    • (c) an auditor:
    • (d) a metering equipment provider:
    • (e) a gaining metering equipment provider.
  • (3) A party listed in subclause (2) may only request access to the metering installation for the purposes of exercising the party’s rights and performing the party’s obligations under this Code or any relevant regulations in relation to 1 or more of the following:
    • (a) the party’s audit functions:
    • (b) the party’s administration functions:
    • (c) the party’s testing functions:
    • (d) the provision of metering components.
  • (4) A reconciliation participant who is required to give a party listed in subclause (2) access to a metering installation must use its best endeavours to do so—
    • (a) in accordance with the authorisation, and any conditions or restrictions contained in the authorisation, referred to in subclause (5); and
    • (b) subject to and to the extent allowed by the authorisation, in a manner and within a timeframe which are appropriate in the circumstances, to enable the party to exercise the party’s rights, or perform the party’s obligations, that are dependent, either directly or indirectly, on access being given.
  • (5) If the reconciliation participant referred to in subclause (2) is a trader responsible for an ICP that—
    • (a) has a consumer, the trader must have obtained the authorisation from the consumer to access the metering installation before arranging access; or
    • (b) does not have a consumer, the trader must arrange for access to the metering installation.
  • (6) The reconciliation participant must arrange for the party listed in subclause (2) to be provided with any necessary facilities, codes, keys, or other means to enable the party to obtain access to the metering installation by the most practicable means.

Clause 10.7(3): amended, on 5 October 2017, by clause 159 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

Clause 10.7(3): amended, on 20 December 2021, by clause 26 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.

10.8

Requirements for information to be recorded, given, produced, or received

  • (1) In this Part, a participant who must record, give, produce, or receive information, must do so in accordance with 1 or more of the following requirements published or notified by the Authority:
    • (a) requirements providing for particular electronic technology:
    • (b) requirements providing for the use of a particular kind of data storage device:
    • (c) requirements providing for the use of a particular kind of electronic communication.
  • (2) Subpart 3 of Part 4 of the Contract and Commercial Law Act 2017 does not, because of section 218(2)(a) of that Act, apply to this Part.
  • (3) The Authority must act reasonably when determining the requirements referred to in subclause (1).

Clause 10.8(2): amended, on 1 November 2018, by clause 20(a) and (b) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.

10.9

Demarcation of responsibility between metering equipment provider and reconciliation participant

  • (1) The demarcation of the responsibility of a metering equipment provider under this Part and a reconciliation participant under Part 15, is at the services access interface.
  • (2) A metering equipment provider is responsible for providing and maintaining the services access interface.
  • (3) The services access interface for a metering installation is—
    • (a) determined by the ATH certifying the metering installation under clause 10 of Schedule 10.4; and
    • (b) recorded in the metering installation certification report under clause 10 of Schedule 10.4.

10.10

Standards used

In this Part a reference to compliance with a standard, including an AS/NZS or IEC standard, is a reference to—

  • (a) the version of the standard existing as at 29 August 2013; or
  • (b) any amendment to or replacement of the standard incorporated by the Authority in accordance with section 131B of the Act; or
  • (c) any equivalent standard incorporated by reference in this Code by the Authority.

Clause 10.10(a): amended, on 29 August 2013, by clause 11 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 10.10(b): amended, on 1 August 2023, by clause 38(1) of the Electricity Industry Participation Code Amendment (System Operation Documents) 2023.

Clause 10.10(c): amended, on 1 August 2023, by clause 38(2) of the Electricity Industry Participation Code Amendment (System Operation Documents) 2023.

Metering installations

10.11

Categories of metering installation

  • (1) An ATH must, before it certifies a metering installation, determine the category of the metering installation by reference to the characteristics of the metering installation, in accordance with clauses 5 and 6 of Schedule 10.7.
  • (2) A metering installation used solely for unmetered load is category 0.
  • (3) The category of each metering installation, other than a category 0 metering installation, is for all purposes of this Part—
    • (a) determined by the ATH certifying the metering installation under clauses 5 and 6 of Schedule 10.7; and
    • (b) recorded in the metering installation certification report under clause 8(4) of Schedule 10.7.

10.12

Interference with metering installation

Subject to clause 48 of Schedule 10.7, a participant must not directly or indirectly interfere with a metering installation for which it is not the metering equipment provider, unless—

  • (a) it is instructed or permitted to do so by the metering equipment provider responsible for the metering installation; or
  • (b) the participant has an arrangement with the trader responsible for the metering installation as the gaining metering equipment provider who will be responsible for the metering installation.

Clause 10.12: amended, on 1 February 2021, by clause 5 of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

10.13

Electricity conveyed

  • (1) A participant must use the quantity of electricity measured by a metering installation for a point of connection as the raw meter data for the quantity of electricity conveyed through the point of connection.
  • (2) Subclause (1) does not apply to electricity that is—
    • (a) estimated in accordance with this Code; or
    • (b) supplied by an embedded generator who has given notice to the reconciliation manager under clause 15.13.
  • (3) A metering equipment provider must, for each point of connection at which it is the metering equipment provider, ensure that all electricity conveyed through the point of connection is measured by a metering installation or metering installations, in accordance with this Part.
  • (4) Despite subclause (3), a metering equipment provider is not required to measure electricity conveyed through a point of connection if the electricity is—
    • (a) unmetered load; or
    • (b) supplied by an embedded generator who has given notice to the reconciliation manager under clause 15.13.

Clause 10.13(2)(b): amended, on 1 November 2018, by clause 21(a) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.

Clause 10.13(4)(b): amended, on 1 November 2018, by clause 21(b) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.

10.13A

Metering installation must record imported electricity separately from exported electricity

  • (1) A metering equipment provider must, for each point of connection at which it is the metering equipment provider, ensure that, if a category 1 metering installation or category 2 metering installation is capable of importing and exporting electricity,—
    • (a) the metering installation measures and records the imported electricity separately from the exported electricity; and
    • (b) the metering installation measures and records the imported electricity and exported electricity separately for each connected phase if the metering installation contains multiple phases.
  • (2) A metering equipment provider for a category 3 or higher metering installation must ensure that the metering installation measures and records the imported electricity separately from the exported electricity.
  • (3) Despite subclauses (1) and (2), if the metering installation contains multiple phases, the metering equipment provider for the metering installation
    • (a) may aggregate together—
      • (i) the amounts of imported electricity recorded on different phases; or
      • (ii) the amounts of exported electricity recorded on different phases; but
    • (b) must not aggregate together imported and exported electricity.

Clause 10.13A: inserted, on 1 February 2021, by clause 6 of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Unmetered load

10.14

Unmetered load

  • (1) This clause applies to a retailer who is recorded in the registry as being responsible for an ICP.
  • (2) A retailer
    • (a) must quantify any unmetered load at the ICP in accordance with Parts 11 and 15; and
    • (b) may, subject to subclause (3), only treat load as unmetered load if it reasonably expects, in any rolling 12 month period, the load to be not greater than—
      • (i) 3,000 kWh; or
      • (ii) 6,000 kWh if the load is predictable load of a type approved and published by the Authority.
  • (3) Subclause (2)(b) does not apply to distributed unmetered load managed in accordance with Part 15.
  • (4) If the load during a rolling 12 month period exceeds the applicable limit under subclause (2)(b), the retailer breaches this clause from the date on which the limit was, or was calculated or estimated to have been, first exceeded.
  • (5) A retailer described in subclause (4) must—
    • (a) as soon as reasonably practicable, but no later than 20 business days after the limit was calculated or estimated to have been first exceeded, commence corrective measures to ensure that it complies with this Part; and
    • (b) within 20 business days of commencing the corrective measures referred to in paragraph (a), complete the corrective measures so that it complies with this Part; and
    • (c) as soon as reasonably practicable, but no later than 10 business days after it becomes aware of the limit having been calculated or estimated to have been first exceeded, advise each participant who is, or would reasonably be expected to be, affected, of—
      • (i) the date on which the limit was calculated or estimated to have been first exceeded; and
      • (ii) the details of the corrective measures that the retailer proposes to take, has taken, or is taking, to reduce the unmetered load.

Clause 10.14(5)(c)(ii): amended, on 29 August 2013, by clause 12 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Metering data

10.15

Security of metering data

  • (1) This clause applies to—
    • (a) a participant who has the right to collect, obtain, use, or store metering data; and
    • (b) the Authority.
  • (2) A person to whom this clause applies must take security measures, as are reasonable in the circumstances, to protect metering data against loss or unauthorised access, use, modification, or disclosure.
  • (3) Subclause (2) is subject to—
    • (a) the person's obligations under any other enactment; and
    • (b) the person being otherwise compelled by law; and
    • (c) any applicable material that the Authority incorporates by reference into this Code.

Clause 10.15(3): amended, on 1 August 2023, by clause 39 of the Electricity Industry Participation Code Amendment (System Operation Documents) 2023.

10.16

Metering data exchange timing and formats

  • (1) A participant (other than a market operation service provider) must, if it is under an obligation to provide metering data under this Part, provide the metering data to the relevant person—
    • (a) in the absence of any timeframe specified in this Code, within a reasonable timeframe specified by the Authority; and
    • (b) in the format the Authority specifies to participants from time to time.
  • (2) The Authority must provide reasonable notice of any changes to the format the Authority specifies under subclause (1)(b).
  • (3) Despite subclause (1)(b), a participant may provide the metering data in an alternative format if it has an arrangement with the recipient to use the alternative format.
  • (4) Despite subclause (3), the participant must be able to comply with any format requirements the Authority specifies under subclause (1)(b), within 1 business day of ceasing to have an arrangement with the recipient under subclause (3).
  • (5) Despite using an alternative format under subclause (3), a participant must still comply with all other obligations in this Code.

Clause 10.16(1)(a): amended, on 1 November 2018, by clause 22(a) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.

Clause 10.16(1)(b): amended, on 1 November 2018, by clause 22(b) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.

Clause 10.16(2): amended, on 1 November 2018, by clause 22(c) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.

Clause 10.16(4): amended, on 1 November 2018, by clause 22(d) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.

Audits

10.17

[Revoked]

Clause 10.17(1): revoked, on 1 February 2016, by clause 25 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2015.

Clause 10.17(1): inserted, on 1 May 2016, by clause 5(1) of the Electricity Industry Participation Code Amendment (Minor Code Amendments) 2016.

Clause 10.17(2): revoked, on 1 May 2016, by clause 5(2) of the Electricity Industry Participation Code Amendment (Minor Code Amendments) 2016.

Clause 10.17: revoked, on 1 June 2017, by clause 6 of the Electricity Industry Participation Code Amendment (Requirements and Processes for Audits) 2016.

10.17A

Metering equipment providers and ATHs to arrange for regular audits

Each metering equipment provider and each ATH must arrange to be audited regularly in accordance with Part 16A in respect of the metering equipment provider's or ATH's obligations under this Part.

Clause 10.17A: inserted, on 1 June 2017, by clause 7 of the Electricity Industry Participation Code Amendment (Requirements and Processes for Audits) 2016.

10.17B

Authority and participant requested audits

  • (1) The Authority may at any time carry out, or appoint an auditor to carry out, an audit of a participant in respect of the participant's obligations under this Part.
  • (2) If a participant considers that another participant may not have complied with this Part, the participant may request that the Authority carry out, or appoint an auditor to carry out, an audit of the other participant.
  • (3) Part 16A applies to an audit carried out under this clause.

Clause 10.17B: inserted, on 1 June 2017, by clause 7 of the Electricity Industry Participation Code Amendment (Requirements and Processes for Audits) 2016.

Subpart 2—Ongoing obligations

Metering equipment providers

10.18

Category 1 metering installations and higher categories of metering installations must have metering equipment provider

  • (1) A participant who is responsible under Part 15 for providing submission information to the reconciliation manager for a point of connection must ensure that, for each metering installation for the point of connection used for an activity regulated under this Code, there is a metering equipment provider.
  • (2) A participant must not use, and must not permit any person to use, a category 1 metering installation, or higher category of metering installation, for a point of connection for an activity regulated under this Code unless, at the time of such use, there is a metering equipment provider for the metering installation.
  • (3) Despite subclauses (1) and (2), a point of connection at which all electricity conveyed is unmetered load
    • (a) does not require a metering equipment provider; and
    • (b) may be used for an activity regulated under this Code.
  • (4) If there is more than 1 metering installation for a point of connection, the metering equipment provider for each metering installation must be the same participant.

10.19

Metering equipment provider

  • (1) The metering equipment provider for each existing category 1 metering installation, or higher category of metering installation, being used on 29 August 2013 for an activity regulated under this Code, for a point of connection
    • (a) that is an ICP and not also an NSP, is the participant, or a consumer, who is identified in the registry as being the primary metering contact at 2400 hours on 28 August 2013:
    • (b) that is an NSP and not also a point of connection to the grid
      • (i) is the participant who owns the meter for the point of connection:
      • (ii) if there is more than 1 meter for the point of connection, is the participant who is appointed by the meter owners for the point of connection, or failing agreement, appointed by the Authority:
    • (c) to the grid, is the participant responsible for metering as set out in the NSP table on the Authority’s website at 2400 hours on 28 August 2013.
  • (2) The metering equipment provider for each category 1 metering installation, or higher category of metering installation for a point of connection, other than a metering installation referred to in subclause (1),—
    • (a) that is an ICP and not also an NSP, is the person recorded in the registry as accepting responsibility as the metering equipment provider under clause 1(1)(a)(ii) of Schedule 11.4:
    • (b) that is an NSP and not also a point of connection to the grid, is—
      • (i) the network owner referred to in clause 10.25(2)(a)(i); or
      • (ii) if a person has contracted with the network owner under clause 10.25(2)(a)(ii), that person:
    • (c) that is a point of connection to the grid, is—
      • (i) the participant referred to in clause 10.26(7)(b); or
      • (ii) if a person has contracted with the participant responsible for providing a metering installation under clause 10.26(7)(b), that person.

Clause 10.19(1): amended, on 29 August 2013, by clause 13(1) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 10.19(1)(a): amended, on 29 August 2013, by clause 13(2) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 10.19(1)(b)(ii): amended, on 5 October 2017, by clause 160(a) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

Clause 10.19(1)(c): amended, on 29 August 2013, by clause 13(3) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 10.19(2)(a): amended, on 5 October 2017, by clause 160(b) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

10.20

Obligations of metering equipment provider

A metering equipment provider must—

  • (a) [Revoked]
  • (b) comply with all of its obligations in this Code including the obligations under Schedules 10.6, 10.7, and 10.8.

Clause 10.20(a): revoked, on 1 June 2017, by clause 8 of the Electricity Industry Participation Code Amendment (Requirements and Processes for Audits) 2016.

10.21

When metering equipment provider’s obligations come into effect

  • (1) The obligations under this Part of a person who assumes responsibility, or is appointed to be responsible, as the metering equipment provider, under clauses 10.19(2) or 10.22, for a metering installation, commence,—
    • (a) for an ICP that is not also an NSP, on the date that is recorded in the registry as being the date on which the metering installation equipment was installed; or
    • (b) for an NSP, on the effective date set out in the NSP table on the Authority’s website.
  • (2) Despite subclause (1), if a person fails to become the metering equipment provider due solely to an administrative failure or similar reason, the Authority may determine the date that the person becomes the metering equipment provider.

Clause 10.21(1)(a): substituted, on 29 August 2013, by clause 14 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

10.22

Change of metering equipment provider

  • (1) The metering equipment provider for a metering installation may change only if the participant responsible for ensuring there is a metering installation under clause 10.24, 10.25, or 10.26 enters into an arrangement with another person to become the metering equipment provider for the metering installation and—
    • (a) in the case of a metering installation for an ICP that is not also an NSP
      • (i) the trader for the metering installation records the name of the gaining metering equipment provider in the registry in accordance with Part 11; and
      • (ii) the gaining metering equipment provider records in the registry that it accepts becoming the metering equipment provider (including the effective date from which the gaining metering equipment provider assumes its responsibility as metering equipment provider for the metering installation) in accordance with Part 11; or
    • (b) in the case of a metering installation for an NSP, the participant responsible for the provision of the metering installation under clause 10.25 advises the reconciliation manager of the gaining metering equipment provider.
  • (1A) The losing metering equipment provider must within 40 business days of the gaining metering equipment provider assuming responsibility for a metering installation
    • (a) calculate any proportion of costs described in subclauses (3) and (4); and
    • (b) notify the gaining metering equipment provider in writing of those costs.
  • (1B) The losing metering equipment provider does not need to comply with subclause (1A) if the losing metering equipment provider does not wish to charge the gaining metering equipment provider a proportion of costs.
  • (1C) If the losing metering equipment provider does not carry out the calculation and notify the gaining metering equipment provider under subclause 1(A) within the time frame in that subclause, the gaining metering equipment provider does not need to comply with subclause (2).
  • (2) The gaining metering equipment provider must, within 20 business days of receiving a notice provided under subclause (1A), pay the losing metering equipment provider the proportion of the costs described in subclause (3) and subclause (4).
  • (3) The costs payable under subclause (2) are those directly and solely attributable to the certification tests and calibration tests of—
    • (a) the metering installation; or
    • (b) any metering components in the metering installation.
  • (4) However, when calculating the costs payable under subclause (2)—
    • (a) no costs are payable for a metering component in a metering installation if the gaining metering equipment provider, within three business days of assuming responsibility for the metering installation,—
      • (i) replaces the metering component; or
      • (ii) removes the metering component from use; or
      • (iii) recertifies the metering component; and
    • (b) no costs are payable for a metering installation if the gaining metering equipment provider, within three business days of assuming responsibility for the metering installation,—
      • (i) replaces the metering installation; or
      • (ii) removes the metering installation from use; or
      • (iii) recertifies the metering installation; and
    • (c) the costs for a metering component must be prorated for the remainder of the certification validity period for the metering component; and
    • (d) the costs for a metering installation are the sum of the prorated costs payable under this clause for each metering component in the metering installation.
  • (5) Despite subclause (2), a gaining metering equipment provider is not required to pay the costs if—
    • (a) it has agreed in writing with the losing metering equipment provider that the gaining metering equipment provider is not required to pay costs under this clause; or
    • (b) the losing metering equipment provider has failed to provide notice of the costs to the gaining metering equipment provider in accordance with subclause (1A).

Clause 10.22(1)(a)(i) and (ii): amended, on 5 October 2017, by clause 161(a) and (b) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

Clause 10.22(1A), (1B) and (1C): inserted, on 1 February 2021, by clause 7(1) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 10.22(2): amended, on 1 February 2021, by clause 7(2) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 10.22(3): replaced, on 1 February 2021, by clause 7(3) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 10.22(4) and (5): inserted, on 1 February 2021, by clause 7(4) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

10.23

Termination of metering equipment provider responsibility

  • (1) Subject to subclause (2), a metering equipment provider’s obligations under this Part for a metering installation terminate only when—
    • (a) for an ICP that is not also an NSP, the metering equipment provider changes under clause 10.22(1)(a), in which case the metering equipment provider’s obligations terminate from the date on which the gaining metering equipment provider assumes responsibility, set out in clause 10.21(1)(a); or
    • (b) for an NSP, the metering equipment provider changes under clause 10.22(1)(b), in which case the metering equipment provider’s obligations terminate from the date on which the gaining metering equipment provider assumes responsibility, set out in clause 10.21(1)(b); or
    • (c) the metering installation is no longer required for the purposes of Part 15 and the point of connection for the metering installation has been decommissioned; or
    • (d) the ICP for the metering installation is converted to be used solely for unmetered load in accordance with this Code.
  • (2) Despite subclause (1), a metering equipment provider must either—
    • (a) comply with its continuing obligations, including record keeping obligations, which—
      • (i) are expressed in this Part as having minimum time periods, until that period expires; or
      • (ii) by their nature extend beyond the date or event referred to in subclause (1); or
    • (b) before its obligations terminate under subclause (1), enter into an arrangement with a participant to assume its obligations referred to in paragraph (a).

10.23A

Decommissioning of metering installation at ICP

  • (1) If a metering installation at an ICP is to be decommissioned, but the ICP is not being decommissioned, the metering equipment provider that is responsible for decommissioning the metering installation must,—
    • (a) if the metering equipment provider is responsible for interrogating the metering installation
      • (i) arrange for a final interrogation to take place before the metering installation is decommissioned; and
      • (ii) provide the raw meter data from the interrogation to the trader that is recorded in the registry as being responsible for the ICP; or
    • (b) if another participant is responsible for interrogating the metering installation, advise the other participant not less than 3 business days before the decommissioning
      • (i) of the date and time of the decommissioning; and
      • (ii) that the participant must carry out a final interrogation.
  • (2) To avoid doubt, if a metering installation at an ICP is to be decommissioned because the ICP is being decommissioned
    • (a) the metering equipment provider is not responsible for arranging a final interrogation of the metering installation; and
    • (b) the trader that is recorded in the registry as being responsible for the ICP must arrange for a final interrogation of the metering installation under clause 11.18(3).

Clause 10.23(A): inserted, on 1 November 2018, by clause 23 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.

Responsibility for ensuring there are metering installations

10.24

Responsibility for ensuring there is metering installation for ICP that is not also NSP

  • A trader must, for each electrically connected ICP that is not also an NSP, and for which it is recorded in the registry as being responsible, ensure that—
    • (a) there is 1 or more metering installations; and
    • (b) all electricity conveyed is quantified in accordance with this Code; and
    • (c) it does not use subtraction to determine submission information for the purposes of Part 15.

Clause 10.24: amended, on 5 October 2017, by clause 162 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

10.25

Responsibility for ensuring there is metering installation for NSP that is not point of connection to grid

  • (1) A distributor must, for each NSP that is not a point of connection to the grid, and for which it is recorded in the NSP table on the Authority’s website as being responsible, ensure that—
    • (a) there is 1 or more metering installations; and
    • (b) all electricity conveyed is quantified in accordance with this Code:
  • (2) A distributor must, if it proposes the creation of a new NSP that is not a point of connection to the grid,—
    • (a) for each metering installation for the NSP, either—
      • (i) assume responsibility for being the metering equipment provider; or
      • (ii) contract with a person who, in that contract, assumes responsibility for being the metering equipment provider; and
    • (b) within 20 business days after assuming responsibility or entering into the contract under paragraph (a), advise the reconciliation manager of—
      • (i) the reconciliation participant for the NSP;
      • (ii) [Revoked]
    • (c) within 5 business days after the date of certification of each metering installation, advise the reconciliation manager of—
      • (i) the participant identifier of the metering equipment provider for the metering installation; and
      • (ii) the certification expiry date of the metering installation.
  • (3) In relation to an NSP of the type described in subclause (1), a distributor must, no later than 20 business days after a metering installation for such an NSP is recertified, advise the reconciliation manager of the following:
    • (a) the reconciliation participant for the NSP:
    • (b) the participant identifier of the metering equipment provider for the metering installation:
    • (c) the certification expiry date of the metering installation.

Clause 10.25(1): amended, on 29 August 2013, by clause 15(1) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 10.25(2): amended, on 29 August 2013, by clause 15(2) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 10.25(2)(b)(ii): amended, on 29 August 2013, by clause 15(3) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 10.25(2)(b)(ii): amended, on 1 February 2016, by clause 26(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2015.

Clause 10.25(2)(c): amended, on 1 February 2016, by clause 26(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2015.

Clause 10.25(3): inserted, on 1 February 2016, by clause 26(3) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2015

Clause 10.25(2)(b): amended, on 1 February 2021, by clause 8(1)(a) and (b) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 10.25(2)(b)(ii): revoked, on 1 February 2021, by clause 8(1)(c) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 10.25(2)(c): replaced, on 1 February 2021, by clause 8(2) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 10.25(2)(c) and (2)(c)(ii): amended, on 1 March 2024, by clause 36 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2024.

10.26

Responsibility for ensuring there is metering installation for point of connection to grid

  • (1) A grid owner must, for each GXP which connects to its grid, ensure that there is 1 or more certified metering installations for the GXP.
  • (2) An asset owner must, for each GIP which connects to the grid, ensure that there is 1 or more certified metering installations for the GIP.
  • (3) A participant who proposes to connect to the grid at a new point of connection must take all practicable steps and use its best endeavours to agree with the grid owner and any other affected participants, on which participant will provide the metering installation for the proposed new point of connection.
  • (4) If the participants cannot agree, within 60 business days of the grid owner first being advised of the proposed new point of connection to the grid, on the participant to be responsible for providing the metering installation,—
    • (a) any affected participant may advise the Authority
      • (i) that agreement has not been reached; and
      • (ii) of the identity of all affected participants; and
      • (iii) of the reasons (if and to the extent known) that agreement was not reached; and
    • (b) the Authority must determine which participant must provide the metering installation; and
    • (c) the Authority must advise—
      • (i) the relevant participant of its responsibility to provide the metering installation; and
      • (ii) the participant intending to connect to the grid of its determination; and
      • (iii) the grid owner of its determination.
  • (5) When determining which participant is responsible for providing the metering installation, the Authority must, unless it is satisfied that there is good reason not to do so, do so on the basis that—
    • (a) the grid owner is responsible if the Authority anticipates that the point of connection is a GXP; and
    • (b) the participant connecting assets to the grid at the point of connection is responsible if the Authority anticipates that the point of connection is a GIP.
  • (6) The participant responsible for providing the metering installation (unless the participant is a grid owner) must also, for each proposed new metering installation
    for a point of connection to the grid,—
    • (a) provide a copy of the metering installation design to the grid owner before ordering equipment; and
    • (b) provide the grid owner with at least 3 months to review and comment on the metering installation design; and
    • (c) respond, within 3 business days of receipt, to any request from the grid owner for additional details or required changes to the metering installation; and
    • (d) ensure that any reasonable changes to the metering installation or the metering installation configuration requested by the grid owner are carried out.
  • (7) The participant responsible for providing the metering installation must—
    • (a) advise the reconciliation manager of the certification expiry date of the metering installation no later than 10 business days after certification of the metering installation; and
    • (b) assume responsibility for being the metering equipment provider for the metering installation or contract with a person to assume responsibility for being
      the metering equipment provider for the metering installation; and
    • (c) advise the reconciliation manager of the participant identifier of the metering equipment provider under paragraph (b) by no later than 20 business days after,—
      • (i) if it is appointed under a contract, entering into the contract under paragraph (b); or
      • (ii) if it assumes responsibility for being the metering equipment provider, other than under a contract, assuming responsibility.
  • (8) The participant responsible for providing the metering installation (unless the
    participant is a grid owner) must, in the case of a proposed modification to an existing metering installation under clause 19 of Schedule 10.7—
    • (a) provide a copy of the metering installation design to the grid owner before ordering equipment or carrying out the modification to the metering installation design; and
    • (b) provide the grid owner with at least 3 months to review and comment on the metering installation design; and
    • (c) respond, within 3 business days of receipt, to any request from the grid owner for additional details or required changes to the metering installation or its
      configuration; and
    • (d) ensure that any reasonable changes to the metering installation or the metering installation configuration requested by the grid owner are carried out.
  • (9) If the grid owner considers, acting reasonably, that a proposed new metering installation, or a proposed change to an existing metering installation, or its configuration, requires subtraction or a loss compensation or error compensation process to determine submission information for the purposes of Part 15, the grid owner must, unless an error compensation process is to be applied to the metering installation that is already within the applicable accuracy tolerances set out in Table 1
    of Schedule 10.1—
    • (a) provide all relevant details to the Authority, in the prescribed form, at least 20
      business days before—
      • (i) the proposed date for installing the metering installation; or
      • (ii) the proposed date for changing the metering installation or metering installation’s configuration; and
    • (b) respond, within 3 business days of receipt, to any request from the Authority for additional details; and
    • (c) ensure that any reasonable changes to the metering installation or its configuration requested by the Authority are carried out.
  • (10) A metering equipment provider must ensure that the quantity of electricity conveyed through a point of connection to the grid for which there is a metering installation for which it is responsible is measured using a half-hour metering installation.
  • (11) If a metering installation for a point of connection to the grid is recertified, the participant responsible for providing the metering installation must, within 10 business days of the date of recertification, advise the reconciliation manager of the metering installation’s new certification expiry date.

Clause 10.26(1): amended, on 29 August 2013, by clause 16(1) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 10.26(2): amended, on 29 August 2013, by clause 16(2) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 10.26(3): amended, on 23 February 2015, by clause 75 of the Electricity Industry Participation Code Amendment (Distributed Generation) 2014.

Clause 10.26(4)(c)(ii): amended, on 23 February 2015, by clause 75 of the Electricity Industry Participation Code Amendment (Distributed Generation) 2014.

Clause 10.26(5)(b): amended, on 23 February 2015, by clause 75 of the Electricity Industry Participation Code Amendment (Distributed Generation) 2014.

Clause 10.26(3), (4), (5) and 9: amended, on 5 October 2017, by clause 163 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

10.27

Change in responsibility for ensuring metering installation for point of connection to grid

(1) If a participant considers, on the basis of historical metering data, that there has been a change in the overall net flow of electricity at a point of connection to the grid over any 12 month period, the participant who is responsible for ensuring there is a metering installation may initiate the process under clauses 10.26(3) to 10.26(5) with all necessary amendments, in order to change the participant responsible for providing the metering installation.
(2) If the participant who is responsible for ensuring there is a metering installation changes under subclause (1), the responsibility for providing submission information to the reconciliation manager under Part 15 changes.

Connecting and electrically connecting points of connection

Heading: amended, on 29 August 2013, by clause 17(1) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Heading: amended, on 5 October 2017, by clause 164 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

10.28

[Revoked]

Clause 10.28: substituted, on 29 August 2013, by clause 17 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 10.28(2)(a), (2)(b) and (3): amended, on 23 February 2015, by clause 75 of the Electricity Industry Participation Code Amendment (Distributed Generation) 2014.

Clause 10.28: revoked, on 5 October 2017, by clause 165 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

10.29

When grid owner may connect point of connection to grid

  • (1A) Only a grid owner may connect a point of connection to the grid.
  • (1) Despite subclause (1A), a grid owner must not connect a point of connection to the grid unless it has—
    • (a) ensured that the processes described in clause 10.26 have been carried out; and
    • (b) requested, in the prescribed form, not less than 20 business days before the proposed connection date, authorisation from the Authority, to connect the point of connection; and
    • (c) obtained the authorisation referred to in paragraph (b) from the Authority.
  • (2) The grid owner must, within 5 business days of connecting a point of connection to the grid, advise the reconciliation manager of—
    • (a) the point of connection that has been connected; and
    • (b) the connection date.

Heading: amended, on 5 October 2017, by clause 166(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

Clause 10.29(1A): inserted, on 5 October 2017, by clause 166(2)(a) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

Clause 10.29(1) and (2): amended, on 5 October 2017, by clause 166(2)(b) to (d) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

Clause 10.29: substituted, on 29 August 2013, by clause 18 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 10.29: amended, on 23 February 2015, by clause 75 of the Electricity Industry Participation Code Amendment (Distributed Generation) 2014.

10.29A

When grid owner may temporarily electrically connect point of connection to grid

  • (1) Subject to clause 10.33, only a grid owner may temporarily electrically connect a point of connection to the grid.
  • (2) A grid owner may temporarily electrically connect a point of connection to the grid that is to be quantified with a category 1 metering installation, or higher category of metering installation, only if a metering equipment provider requests that the grid owner temporarily electrically connect the point of connection to the grid for the purposes of—
    • (a) certifying a metering installation at the point of connection to the grid; or
    • (b) maintaining, repairing, testing, or commissioning a metering installation at the point of connection to the grid.
  • (3) Despite subclause (2), a metering equipment provider must not request that a grid owner temporarily electrically connect a point of connection to the grid unless—
    • (a) the grid owner responsible for the point of connection has authorised the metering equipment provider to do so; and
    • (b) the metering equipment provider has an arrangement with that grid owner to provide metering services.

Clause 10.29A: inserted, on 5 October 2017, by clause 167 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

10.29B

Grid owner may electrically connect point of connection to grid

  • (1) Subject to clause 10.33A, only a grid owner may electrically connect a point of connection to the grid that it owns or operates.
  • (2) A grid owner may only electrically connect a point of connection under subclause (1) if—
    • (a) in the case of the electrical connection of a direct consumer or grid connected generator, there is a trader identified as responsible under Part 15 for the delivery of submission information for the electricity conveyed at the point of connection from the time of electrical connection; or
    • (b) in the case of the electrical connection of a local network that has one or more consumers connected to the local network or to an embedded network that is connected to the local network (either directly or through another embedded network), one or more traders are identified as responsible under Part 15 for the delivery of submission information for the electricity conveyed at the point of connection from the time of electrical connection; or
    • (c) in the case of the electrical connection of a local network that has no consumers connected to the local network or to any embedded network that is connected to the local network (either directly or through another embedded network), if the distributor for that local network is identified as responsible under Part 15 for the delivery of submission information for the electricity conveyed at the point of connection from the time of electrical connection.

Clause 10.29B: inserted, on 1 February 2021, by clause 9 of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Disconnecting and electrically disconnecting points of connection to the grid

10.29C

Grid owner may electrically disconnect or disconnect point of connection to grid

  • (1) Subject to subclause (2), only a grid owner may—
    • (a) electrically disconnect a point of connection to the grid; or
    • (b) disconnect a point of connection to the grid.
  • (2) A grid owner may disconnect or electrically disconnect a point of connection to the grid that it owns or operates only if the action is required for the grid owner to meet its obligations—
    • (a) under an enactment, including this Code; or
    • (b) under its contract with the party identified in clause 10.29B(2) as responsible in accordance with Part 15 for the delivery of submission information for the electricity conveyed at the point of connection to the grid.

Clause 10.29C: inserted, on 1 February 2021, by clause 9 of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

10.30

When local network owner or embedded network owner may connect NSP that is not point of connection to grid

  • (1A) Only a local network owner that initiates, under Part 11, the creation of an NSP on its local network that is not a point of connection to the grid may connect the NSP to—
    • (a) an embedded network, but only if the embedded network owner has agreed to the connection; or
    • (b) another local network, but only if the owner of the other local network has agreed to the connection.
  • (1B) Only an embedded network owner that initiates, under Part 11, the creation of an NSP on its embedded network
    • (a) may connect the NSP to another embedded network; but
    • (b) can only do so if the other embedded network owner has agreed to the connection.
  • (1) A local network owner or an embedded network owner must not connect an NSP on its network under subclause (1A) or (1B) unless requested to do so by the reconciliation participant responsible for ensuring there is a metering installation for the NSP.
  • (2) A local network owner or an embedded network owner that initiates the creation of an NSP under Part 11 on the owner’s network and connects the NSP under this clause must, within 5 business days of connecting the NSP, advise the reconciliation manager of the following:
    • (a) that the NSP has been connected; and
    • (b) the connection date; and
    • (c) the participant identifier of the metering equipment provider for each metering installation for the NSP; and
    • (d) the certification expiry date of each metering installation for the NSP.

Clause 10.30: substituted, on 29 August 2013, by clause 19 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 10.30: amended, on 23 February 2015, by clause 75 of the Electricity Industry Participation Code Amendment (Distributed Generation) 2014.

Clause 10.30: replaced, on 5 October 2017, by clause 168 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

Clause 10.30: replaced, on 1 February 2021, by clause 10 of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

10.30A

When local network owner or embedded network owner may temporarily electrically connect NSP that is not point of connection to grid

  • (1) Subject to clause 10.33, only a local network owner that initiates, under Part 11, the creation of an NSP on its local network that is not a point of connection to the grid may temporarily electrically connect the NSP to—
    • (a) an embedded network, but only if the embedded network owner has agreed to the temporary electrical connection; or
    • (b) another local network, but only if the owner of the other local network has agreed to the temporary electrical connection.
  • (2) Subject to clause 10.33, only an embedded network owner that initiates, under Part 11, the creation of an NSP on its embedded network
    • (a) may temporarily electrically connect the NSP to another embedded network; but
    • (b) can only do so if the other embedded network owner has agreed to the temporary electrical connection.
  • (3) A local network owner or an embedded network owner may only temporarily electrically connect an NSP under subclause (1) or (2) if a metering equipment provider requests that the local network owner or embedded network owner temporarily electrically connect the NSP for the purposes of—
    • (a) certifying a metering installation at the NSP; or
    • (b) maintaining, repairing, testing, or commissioning a metering installation at the NSP.
  • (4) Despite subclause (3), a metering equipment provider must not request that a local network owner or an embedded network owner temporarily electrically connect an NSP under subclause (1) or (2) unless—
    • (a) the reconciliation participant responsible for the NSP authorises the metering equipment provider to do so; and
    • (b) the metering equipment provider has an arrangement with that reconciliation participant to provide metering services.

Clause 10.30A: inserted, on 5 October 2017, by clause 169 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

Clause 10.30A: replaced, on 1 February 2021, by clause 10 of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

10.30B

When distributor may electrically connect NSP that is not point of connection to grid

  • (1) Subject to clause 10.33A, only a distributor may, on its network, electrically connect an NSP that is not a point of connection to the grid.
  • (2) A distributor may only electrically connect an NSP under subclause (1) that is not an interconnection point between two local networks if—
    • (a) each distributor whose network is directly connected to the NSP has agreed to the electrical connection; and
    • (b) 1 or more traders are identified as responsible under Part 15 for the delivery of submission information for the electricity conveyed at the NSP from the time of electrical connection and that trader or those traders have—
      • (i) requested the electrical connection; and
      • (ii) confirmed to the distributor that the metering installation at the NSP is certified and operational.
  • (3) A distributor may only electrically connect an NSP under subclause (1) that is an interconnection point between two local networks if the reconciliation participant responsible for the delivery of submission information for the NSP
    • (a) has requested the electrical connection; and
    • (b) has confirmed the metering installation at the NSP is certified and operational.

Clause 10.30B: inserted, on 1 February 2021, by clause 11 of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Disconnecting and electrically disconnecting NSPs

10.30C

Distributor may electrically disconnect or disconnect NSP that is not point of connection to grid

  • (1) Subject to subclause (2), only a distributor may, on its network
    • (a) electrically disconnect an NSP that is not a point of connection to the grid; or
    • (b) disconnect an NSP that is not a point of connection to the grid.
  • (2) A distributor may take one of the actions under subclause (1) only if the action is required for the distributor to meet its obligations—
    • (a) under an enactment, including this Code; or
    • (b) under its contract with the trader or traders responsible for the delivery of submission information under Part 15 for the electricity conveyed at the NSP.

Clause 10.30C: inserted, on 1 February 2021, by clause 11 of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

10.31

When distributor may connect ICP that is not NSP

  • (1) Only a distributor may, on its network, connect an ICP that is not an NSP.
  • (2) Despite subclause (1), a distributor must not connect an ICP that is not an NSP unless—
    • (a) the trader trading at the ICP has requested the connection; or
    • (b) in the following circumstances:
      • (i) there is only shared unmetered load at the ICP; and
      • (ii) in accordance with clause 11.14, the distributor has—
        • (A) assigned the shared unmetered load; and
        • (B) advised each trader, that is responsible under clause 11.18(1) for the ICPs across which the unmetered load is shared, of that assignment.

Clause 10.31: substituted, on 29 August 2013, by clause 20 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 10.31(a): amended, on 23 February 2015, by clause 75 of the Electricity Industry Participation Code Amendment (Distributed Generation) 2014.

Clause 10.31: replaced, on 5 October 2017, by clause 170 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

Clause 10.31(1): amended, on 1 November 2018, by clause 24(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.

Clause 10.31(2): replaced, on 1 November 2018, by clause 24(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.

10.31A

When distributor may temporarily electrically connect ICP that is not NSP

  • (1) Subject to clause 10.33, only a distributor may, on its network, temporarily electrically connect an ICP that is not an NSP.
  • (2) A distributor may only temporarily electrically connect an ICP that is not an NSP
    • (a) if a metering equipment provider requests that the distributor temporarily electrically connect the ICP for the purposes of—
      • (i) certifying a metering installation at the ICP; or
      • (ii) maintaining, repairing, testing, or commissioning a metering installation at the ICP; or
    • (b) in the following circumstances:
      • (i) there is only shared unmetered load at the ICP; and
      • (ii) in accordance with clause 11.14, the distributor has—
        • (A) assigned the shared unmetered load; and
        • (B) advised each trader, that is responsible under clause 11.18(1) for the ICPs across which the unmetered load is shared, of that assignment; and
      • (iii) the distributor has advised those traders of the distributor's intention to temporarily electrically connect the ICP.
  • (3) Despite subclause (2)(a), a metering equipment provider must not request that a distributor temporarily electrically connect an ICP that is not an NSP unless—
    • (a) the trader responsible for the ICP has authorised the metering equipment provider to do so; and
    • (b) the metering equipment provider has an arrangement with that trader to provide metering services.
  • (4) Despite subclause (2)(b), the distributor need not advise the traders of the distributor's intention to temporarily electrically connect the ICP if—
    • (a) advising all traders would impose a material cost on the distributor; and
    • (b) in the distributor's reasonable opinion, advising the traders would not result in any material benefit to any of the traders.

Clause 10.31A: inserted, on 5 October 2017, by clause 171 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

Clause 10.31A(1): amended, on 1 November 2018, by clause 25(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.

Clause 10.31A(2): replaced, on 1 November 2018, by clause 25(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.

Clause 10.31A(3): amended, on 1 November 2018, by clause 25(3) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.

Clause 10.31A(4): inserted, on 1 November 2018, by clause 25(4) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.

10.31B

When distributor may electrically connect ICP that is not NSP

  • (1) A distributor may electrically connect an ICP that is not an NSP only if—
    • (a) there is only shared unmetered load at the ICP; and
    • (b) in accordance with clause 11.14, the distributor has—
      • (i) assigned the shared unmetered load; and
      • (ii) advised each trader, that is responsible under clause 11.18(1) for the ICPs across which the unmetered load is shared, of that assignment; and
    • (c) the distributor has advised those traders of the distributor’s intention to electrically connect the ICP.
  • (2) Despite subclause (1)(c), the distributor need not advise the traders of the distributor’s intention to electrically connect the ICP if—
    • (a) the distributor is doing so following a maintenance outage; and
    • (b) advising all traders would impose a material cost on the distributor; and
    • (c) in the distributor’s reasonable opinion, advising the traders would not result in any material benefit to any of the traders.

Clause 10.31B: inserted, on 1 November 2018, by clause 26 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.

Clause 10.31B(2): amended, on 20 December 2021, by clause 27 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.

Disconnecting and electrically disconnecting ICPs

10.31C

Distributor may electrically disconnect or disconnect ICP that is not an NSP

  • (1) Subject to subclause (2), only a distributor may, on its network,—
    • (a) electrically disconnect an ICP that is not an NSP; or
    • (b) disconnect an ICP that is not an NSP.
  • (2) A distributor may take one of the actions under subclause (1) only if the action is required for the distributor to meet its obligations—
    • (a) under an enactment, including this Code; or
    • (b) under its contract with the trader recorded in the registry as being responsible for the ICP; or
    • (c) under its contract with the consumer at the ICP.

Cross heading and clause 10.31C: inserted, on 1 February 2021, by clause 12 of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

10.32

Reconciliation participant requesting connection of point of connection

For the purposes of clauses 10.30(1) and 10.31(2), a reconciliation participant must only request the connection of a point of connection if the reconciliation participant

  • (a) accepts responsibility for the reconciliation participant’s obligations in this Part and Parts 11 and 15 for the point of connection; and
  • (b) has an arrangement with a metering equipment provider to provide 1 or more metering installations for the point of connection.

Clause 10.32 Heading: amended, on 29 August 2013, by clause 21(1) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 10.32 Heading: amended, on 5 October 2017, by clause 172(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

Clause 10.32: amended, on 29 August 2013, by clause 21(2) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 10.32: amended, on 5 October 2017, by clause 172(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

10.33

When trader may temporarily electrically connect a point of connection

  • (1) A trader may temporarily electrically connect a point of connection, or a metering equipment provider authorised by a trader under subclause (2) may temporarily electrically connect a point of connection only if—
    • (aa) for an NSP that is a point of connection to the grid, the grid owner has approved—
      • (i) the trader temporarily electrically connecting the point of connection; or
      • (ii) the trader authorising the temporary electrical connection of the point of connection:
    • (ab) for an NSP that is not a point of connection to the grid, the distributor that gave notice to the reconciliation manager under clause 25 of Schedule 11.1 has approved—
      • (i) the trader temporarily electrically connecting the point of connection; or
      • (ii) the trader authorising the temporary electrical connection of the point of connection:
    • (a) for a point of connection that is an ICP, but which is not an NSP,—
      • (i) either:
        • (A) the trader is recorded in the registry as being responsible for the ICP; or
        • (B) if the ICP has been electrically disconnected, the trader
          • (1) has an arrangement with a customer or embedded generator at the ICP; and
          • (2) initiates a switch under one of clauses 2, 9, or 14 of Schedule 11.3 within 2 business days of the date of electrical connection; and
          • (3) accepts responsibility to provide submission information under Part 15 or for the losing trader’s direct costs for the electricity conveyed at the ICP, from the date of electrical connection; and
        • (ii) if the ICP has metered load, 1 or more operational certified metering installations are connected at the ICP in accordance with this Part; and
        • (iii) if the ICP has not previously been electrically connected, the owner of the network to which the point of connection is connected has given written approval to the temporary electrical connection.
    • (b) [Revoked]
    • (c) [Revoked]
  • (2) A trader described in subclause (1) may authorise a metering equipment provider, with which the trader has an arrangement, to request the temporary electrical connection of a point of connection only for the purposes of—
    • (a) certifying a metering installation at the point of connection; or
    • (b) maintaining, repairing, testing, or commissioning a metering installation at the point of connection.
  • (3) [Revoked]
  • (4) [Revoked]

Clause 10.33: replaced, on 1 February 2021, by clause 13 of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Heading: amended, on 5 October 2017, by clause 173(a) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

Clause 10.33: substituted, on 29 August 2013, by clause 22 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 10.33(1): amended, on 5 October 2017, by clause 173(b) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

Clause 10.33(1)(aa) and (ab): inserted, on 1 November 2018, by clause 27(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.

Clause 10.33(1)(a): replaced, on 1 November 2018, by clause 27(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.

Clause 10.33(1)(b) and (c): revoked, on 1 November 2018, by clause 27(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.

Clause 10.33(1)(c): amended, on 23 February 2015, by clause 75 of the Electricity Industry Participation Code Amendment (Distributed Generation) 2014.

Clause 10.33(1)(c): amended, on 1 February 2016, by clause 27 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2015.

Clause 10.33(2): replaced, on 5 October 2017, by clause 173(c) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

Clause 10.33(2): amended, on 1 November 2018, by clause 27(3) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.

Clause 10.33(3) and (4): revoked, on 5 October 2017, by clause 173(d) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

10.33A

When trader may electrically connect point of connection

  • (1) A trader may electrically connect a point of connection, or another participant authorised by a trader may electrically connect a point of connection, only if—
    • (aa) for an NSP that is a point of connection to the grid, the grid owner has approved—
      • (i) the trader electrically connecting the point of connection to the grid that the grid owner owns or operates; or
      • (ii) the trader authorising the electrical connection of the point of connection to the grid that the grid owner owns or operates:
    • (ab) for an NSP that is not a point of connection to the grid, the distributor that gave notice to the reconciliation manager under clause 25 of Schedule 11.1 has approved—
      • (i) the trader electrically connecting the point of connection to the network that the distributor owns or operates; or
      • (ii) the trader authorising the electrical connection of the point of connection to the network that the distributor owns or operates:
    • (a) for a point of connection that is an ICP, but which is not an NSP,—
      • (i) either—
        • (A) the trader is recorded in the registry as being responsible for the ICP; or
        • (B) if the ICP has been electrically disconnected, the trader
          • (1) has an arrangement with a customer or embedded generator at the ICP; and
          • (2) initiates a switch under clause 2, 9, or 14 of Schedule 11.3 within 2 business days of the date of electrical connection; and
          • (3) accepts responsibility to provide submission information in accordance with Part 15 or for the losing trader’s direct costs for the electricity conveyed at the ICP from the date of electrical connection; and
      • (ii) if the ICP has metered load, 1 or more operational certified metering installations are connected at the ICP in accordance with this Part; and
      • (iii) if the ICP has not previously been electrically connected, the owner of the network to which the point of connection is connected has given written approval of the electrical connection:
    • (b) [Revoked]
    • (c) [Revoked]
    • (d) the point of connection supplies electricity to a load that is assigned to multiple ICPs as shared unmetered load and the distributor to whose network the point of connection is connected has advised all traders that are assigned the shared unmetered load of the trader’s intention to electrically connect the point of connection.
  • (2) Further to subclause (1), a trader described in subclause (1)(a)(i)—
    • (a) may authorise the electrical connection of an ICP if—
      • (i) a metering installation is in place at the ICP; and
      • (ii) the metering installation is operational but not certified; and
      • (iii) the trader arranges for the certification of the metering installation to be completed within 5 business days of the ICP being electrically connected; or
    • (b) may electrically connect an ICP if the point of connection is solely for unmetered load.
  • (3) A trader must not electrically connect or authorise the electrical connection of a point of connection in any of the following circumstances—
    • (a) a distributor has electrically disconnected the point of connection for safety reasons, and has not subsequently approved the electrical connection of the point of connection:
    • (b) electrically connecting the point of connection would breach the Electricity (Safety) Regulations 2010:
    • (c) a switch described in subclause (1)(a)(i)(B)(2) has been withdrawn or reversed.
  • (4) No participant may electrically connect a point of connection, or authorise the electrical connection of a point of connection, other than—
    • (a) a trader in the circumstances described in subclauses (1) to (3); or
    • (b) a distributor in the circumstances described in clause 10.31B.
  • (5) Under subclause (1)(a)(i), if a trader or a person authorised by a trader electrically connects an electrically disconnected point of connection in error, or prior to the switch being withdrawn or reversed, the trader must—
    • (a) electrically disconnect the ICP
      • (i) using the same method of electrical disconnection as the losing trader used; or
      • (ii) by, if the method of electrical connection was bypass, removing the bypass; and
    • (b) reimburse the losing trader for any direct costs the losing trader incurred because of the electrical connection of the point of connection
      • (i) in error; or
      • (ii) prior to the switch being withdrawn or reversed.

Clause 10.33A: replaced, on 1 February 2021, by clause 13 of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 10.33A: inserted, on 5 October 2017, by clause 174 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

Clause 10.33A(1)(aa) and (ab): inserted, on 1 November 2018, by clause 28(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.

Clause 10.33A(1)(a): replaced, on 1 November 2018, by clause 28(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.

Clause 10.33A(1)(b) and (c): revoked, on 1 November 2018, by clause 28(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.

Clause 10.33A(2): amended, on 1 November 2018, by clause 28(3) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.

Clause 10.33A(4): replaced, on 1 November 2018, by clause 28(4) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.

Disconnecting and electrically disconnecting points of connection

10.33B

Trader must not disconnect or electrically disconnect ICP for which it is not responsible

Unless a trader is recorded in the registry as being responsible for an ICP or is meeting its obligation under clause 10.33A(5)(a) in respect of an ICP, the trader must not—

  • (a) electrically disconnect the ICP; or
  • (b) disconnect the ICP; or
  • (c) authorise a metering equipment provider
    • (i) to electrically disconnect the ICP; or
    • (ii) to disconnect the ICP.

Cross Heading and Clause 10.33B: inserted, on 1 February 2021, by clause 14 of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 10.33B(a): amended, on 1 March 2024, by clause 37 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2024.

10.33C

When trader may bridge meter at ICP

  • (1) Subject to subclause (2), only a trader that is responsible for an ICP or a metering equipment provider authorised by the trader or a distributor authorised by the trader, in electrically connecting an ICP, may electrically connect the ICP in a way that bypasses the meter or meters that are in place to record the electricity flowing through the ICP (“bridge” a meter).
  • (2) A trader may authorise a metering equipment provider or distributor under subclause (1)—
    • (a) generally for all or some of the ICPs that the trader is responsible for; or
    • (b) for a specific ICP that the trader is responsible for.
  • (3) A trader that is responsible for an ICP, or a metering equipment provider authorised by the trader or a distributor authorised by the trader, may only bridge a meter at the ICP if—
    • (a) the metering equipment provider responsible for the meter, despite best endeavours,—
      • (i) is unable to remotely electrically connect the ICP so that electricity flows through the meter; or
      • (ii) cannot, because of safety issues, repair a fault with the meter that prevents electricity flowing through the meter at the ICP; and
    • (b) the consumer at the ICP will likely be without electricity for a period of time that will cause significant disadvantage to the consumer.
  • (4) If a meter is bridged under subclause (1) by the metering equipment provider or distributor, the metering equipment provider or distributor (as the case may be) must, within 1 business day, advise the trader responsible for the ICP that the meter is bridged and include the date that bridging occurred in its advice.
  • (5) If a meter is bridged under subclause (1), in all cases, the trader responsible for the ICP must—
    • (a) determine, in accordance with clause 2A of Schedule 15.2, the quantity of electricity conveyed through the ICP for the period of time the meter is bridged; and
    • (b) submit that estimated quantity of electricity to the reconciliation manager in accordance with clause 15.4; and
    • (c) within 1 business day of being advised that the meter is bridged, notify the metering equipment provider responsible for the bridged meter that it is required to reinstate the meter so that all electricity flowing into the ICP flows through a certified metering installation.
  • (6) The metering equipment provider receiving the notice under subclause (5)(c) must reinstate the meter so that all electricity flowing into the ICP flows through a certified metering installation within 5 business days of receiving the notice.

Clause 10.33C: inserted, on 1 February 2021, by clause 14 of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

General metering installation requirements

10.34

Installation and modification of metering installations

  • (1) This clause applies to a metering equipment provider that proposes to install or modify a metering installation at a point of connection other than a point of connection to the grid.
  • (2) The metering equipment provider must consult with the distributor and the trader for the point of connection on the matters specified in subclause (2A), before—
    • (a) finalising the design of a metering installation for the point of connection; or
    • (b) modifying the design of a metering installation installed at the point of connection; or
    • (c) finalising or modifying the design of a metering installation when replacing a metering component or metering installation with a new metering component or new metering installation, even if the new metering component or metering installation has the same or similar design and functionality as the existing metering component or metering installation.
  • (2A) The metering component’s or matters referred to in subclause (2) are the metering installation’s
    • (a) required functionality; and
    • (b) terms of use; and
    • (c) required interface format; and
    • (d) integration of the ripple receiver and the meter; and
    • (e) functionality for controllable load.
  • (2B) In addition to subclause (2), any consultation carried out under subclause (2), and any agreement that may be reached in that consultation, does not affect the application of clause 19 of Schedule 10.7.
  • (2C) Despite subclause (2), the metering equipment provider does not need to consult with—
    • (a) the distributor if the metering equipment provider has already consulted with the distributor on the design of—
      • (i) a metering component or metering installation that has the same or similar design and functionality as the replacement metering component or metering installation; or
      • (ii) the new metering installation; or
    • (b) the trader if the metering equipment provider has already consulted with the trader on the design of—
      • (i) a metering component or metering installation that has the same or similar design and functionality as the replacement metering component or metering installation; or
      • (ii) the new metering installation.
  • (2D) To avoid doubt, subclause (2C) is intended to permit a metering equipment provider to re-use the design of a metering component or metering installation if—
    • (a) the metering equipment provider has already consulted the distributor and trader in accordance with subclause (2); and
    • (b) the metering equipment provider will re-use the design of the metering component or metering installation
      • (i) on the distributor’s network; and
      • (ii) at an ICP for which the trader is responsible.
  • (3) Each participant involved in the consultation referred to in subclause (2) must—
    • (a) use its best endeavours to reach agreement; and
    • (b) act reasonably and in good faith.
  • (4) If the participants referred to in subclause (2) cannot agree, within 20 business days of the distributor first being advised of the proposed new or modified metering installation, on the metering installation’s requirements set out in subclause (2A)(a) to (e)—
    • (a) an affected participant may refer the matter to the Authority under clause 10.50 by advising the Authority
      • (i) that agreement has not been reached; and
      • (ii) of the identity of all affected participants; and
      • (iii) the reasons (if and to the extent known) why agreement was not reached; and
    • (b) the Authority
      • (i) may, at its discretion, determine the metering installation requirements; and
      • (ii) must, if it determines the metering installation requirements,—
        • (A) do so in accordance with clause 10.50(4); and
        • (B) advise each affected participant of the determination it has made

Clause 10.34(1) and (2): substituted, on 1 February 2016, by clause 28(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2015.

Clause 10.34(2): amended, on 1 May 2016, by clause 6 of the Electricity Industry Participation Code Amendment (Minor Code Amendments) 2016.

Clause 10.34(2)(b): amended, on 1 February 2021, by clause 15(1)(a) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 10.34(2)(c): inserted, on 1 February 2021, by clause 15(1)(b) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 10.34(2A): inserted, on 1 February 2016, by clause 28(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2015.

Clause 10.34(2A): amended, on 1 February 2021, by clause 15(2) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 10.34(2B), (2C) and (2D): inserted, on 1 February 2021, by clause 15(3) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 10.34(4): amended, on 1 February 2016, by clause 28(3) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2015.

10.35

Physical location of metering installations

  • (1) A reconciliation participant responsible for ensuring there is a category 1 metering installation or category 2 metering installation must ensure that the metering installation is located as physically close to a point of connection as practical in the circumstances.
  • (2) A reconciliation participant responsible for ensuring there is a category 3 or higher metering installation must,—
    • (a) if practical in the circumstances, ensure that the metering installation is located at a point of connection; or
    • (b) if it is not practical in the circumstances to locate the metering installation at the point of connection, calculate the quantity of electricity conveyed through the point of connection using a loss compensation process approved by the certifying ATH.
  • (3) If a calculation is carried out under subclause (2)(b), the certifying ATH must record in the metering installation certification report
    • (a) the details of the calculation; and
    • (b) any assumption used; and
    • (c) any measurement used.
  • (4) This clause does not apply to an existing metering installation that is in place on 29 August 2013.

Clause 10.35(3): amended, on 29 August 2013, by clause 23(1) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 10.35(4): amended, on 29 August 2013, by clause 23(2) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

10.36

Reconciliation participant to have arrangement with metering equipment provider

A reconciliation participant must, before accepting responsibility to be the reconciliation participant for a point of connection, enter into an arrangement with a metering equipment provider

  • (a) for the reconciliation participant to provide the metering equipment provider with physical access to the metering installation for the point of connection and the premises at which it is situated; and
  • (b) arranging for the electrical disconnection of the point of connection, if required by the metering equipment provider to enable the metering equipment provider to comply with its obligations under this Part; and
  • (c) for the metering equipment provider to provide the reconciliation participant with access at the services access interface to the metering data from the metering installation for the point of connection, in accordance with an authorisation from—
    • (i) in the case of an ICP, the consumer; or
    • (ii) in the case of an NSP, the network owner.

Clause 10.36(b): amended, on 5 October 2017, by clause 175 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

Active and reactive energy metering

10.37

Active and reactive measuring and recording requirements

  • (1) A metering equipment provider must ensure that each half-hour metering installation that is a category 3 metering installation, or higher category of metering installation, certified after 29 August 2013, measures and separately records, in accordance with this Part,—
    • (a) if the measuring and recording requirement is for consumption only—
      • (i) import active energy; and
      • (ii) import reactive energy; and
      • (iii) export reactive energy; or
    • (b) if the measuring and recording requirement is for consumption and generation, or generation only—
      • (i) import active energy; and
      • (ii) export active energy; and
      • (iii) import reactive energy; and
      • (iv) export reactive energy.
  • (1A) A metering equipment provider must ensure that each half-hour metering installation that is a category 2 metering installation, certified after 29 August 2013, is capable of measuring and recording—
    • (a) import active energy; and
    • (b) export active energy; and
    • (c) import reactive energy; and
    • (d) export reactive energy.
  • (1B) A metering equipment provider must ensure that each half-hour metering installation that is a category 2 metering installation, certified after 29 August 2013, measures and separately records, in accordance with this Part,—
    • (a) if the measuring and recording requirement is for consumption only, import active energy; or
    • (b) if the measuring and recording requirement is for consumption and generation, or generation only—
      • (i) import active energy; and
      • (ii) export active energy.
  • (2) Despite subclauses (1)(a) and (1B)—
    • (a) each metering installation, for a point of connection to the grid, certified after 29 August 2013, must measure and separately record—
      • (i) import active energy; and
      • (ii) export active energy; and
      • (iii) import reactive energy; and
      • (iv) export reactive energy; and
    • (b) the accuracy of each local service metering installation for electricity used in and by a grid substation must be within the applicable accuracy tolerances set out in Table 1 of Schedule 10.1.

Clause 10.37: amended, on 29 August 2013, by clause 24 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 10.37(1): amended, on 1 February 2016, by clause 29(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2015.

Clause 10.37(1A) and (1B): inserted, on 1 February 2016, by clause 29(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2015.

Clause 10.37(2): amended, on 1 February 2016, by clause 29(3) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2015.

Certification of metering installations

10.38

Certification of metering installations

A metering equipment provider must—

  • (a) obtain and maintain certification in accordance with this Part—
    • (i) for each metering installation for which it is responsible; and
    • (ii) for each metering component in a metering installation for which it is responsible; and
  • (b) ensure that any tests required for certification under paragraph (a) are conducted in accordance with this Code including the obligations under Schedule 10.7 or 10.8 (whichever is applicable) by an ATH contracted by the metering equipment provider.

Metering infrastructure

10.39

Responsibility for metering infrastructure integration

  • (1) A metering equipment provider must ensure that—
    • (a) for each metering installation for which it is responsible, an appropriately designed metering infrastructure is in place; and
    • (b) in each metering installation for which it is responsible,—
      • (i) each metering component is compatible with, and will not cause any interference with the operation of, any other metering component in the metering installation; and
      • (ii) collectively, all metering components integrate to provide a functioning system; and
    • (c) each metering installation for which it is responsible is correctly and accurately integrated within the associated metering infrastructure.
  • (2) Subclause (1) does not apply to an electrically disconnected metering installation for an ICP.

Clause 10.39(2): amended, on 5 October 2017, by clause 176 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

Approved test houses and ATHs

10.40

General requirements for approval as ATH

  • (1) A person wishing to be approved as an ATH, or an ATH wishing to renew its approval, must apply to the Authority
    • (a) at least 2 months before the intended effective date of the approval or renewal; and
    • (b) in writing; and
    • (c) in the prescribed form; and
    • (d) in accordance with Schedule 10.3.
  • (2) A person making an application must satisfy the Authority (providing, where appropriate, suitable evidence) that the person—
    • (a) has the facilities and procedures to reliably meet, for the requested term of the approval, the minimum requirements of this Code for the class or classes of ATH for which it is seeking approval; and
    • (b) has had an audit under Part 16A; and
    • (c) is a fit and proper person for approval.
  • (3) Any approved test house operated solely by an ATH is, for all purposes of this Code and the Act, deemed to be approved in accordance with the procedures in the Code.

Clause 10.40(2)(b): amended, on 1 June 2017, by clause 9 of the Electricity Industry Participation Code Amendment (Requirements and Processes for Audits) 2016.

10.41

Requirements applying to ATHs

An ATH must, when carrying out activities under this Part,—

  • (a) only carry out activities for which it has been approved by the Authority; and
  • (b) exercise a degree of skill, diligence, prudence, foresight, and economic management, taking into account the technological complexity of the metering components and metering installations being tested—
    • (i) determined by reference to good industry practice; and
    • (ii) that would reasonably be expected from a skilled and experienced ATH engaged in the management and operation of an approved test house; and
  • (c) comply with all applicable safety, employment, environmental, and other enactments; and
  • (d) exercise any discretion given to it under this Part by—
    • (i) taking into account the relevant circumstances of the particular instance; and
    • (ii) acting professionally; and
  • (e) record the manner in which it carried out its activities and its reasons for carrying the activities out in that manner.

10.42

ATH’s functions and ongoing obligations

  • (1) An ATH must comply with this Code including Schedules 10.4, 10.7, and 10.8.
  • (2) An ATH must, if this Part requires an ATH to complete a function or activity before a metering installation is certified, complete the function or activity as part of the process undertaken to obtain certification for the metering installation.

Metering installations that are inaccurate, defective, or not fit for purpose

10.43

Metering installations that are inaccurate, defective, or not fit for purpose to be investigated

  • (1) For the purposes of this clause and clauses 10.44 to 10.48, a metering installation is—
    • (a) accurate, if it is within the applicable accuracy tolerances set out in Table 1 of Schedule 10.1:
    • (b) inaccurate, if it is outside the applicable accuracy tolerances set out in Table 1 of Schedule 10.1.
  • (2) A participant must comply with this clause and clauses 10.44 to 10.48 if—
    • (a) in the case of a metering equipment provider, it is advised under subclause (3)(a); or
    • (b) it becomes aware of an event or circumstance that leads it to believe a metering installation is or could be—
      • (i) inaccurate; or
      • (ii) defective; or
      • (iii) not fit for purpose.
  • (3) A participant referred to in subclause (2)(b), other than the metering equipment provider responsible for the metering installation, must—
    • (a) advise the metering equipment provider responsible for the metering installation that it has become aware of an event or circumstance that leads it to believe the metering installation is or could be—
      • (i) inaccurate; or
      • (ii) defective; or
      • (iii) not fit for purpose; and
    • (b) include, with the advice (if and to the extent they are known), all relevant details.
  • (4) A metering equipment provider must, if it is advised under subclause (3)(a), or becomes aware as referred to in subclause (2)(b), within the period set out in subclause (5),—
    • (a) investigate—
      • (i) if it is advised under subclause (3)(a), the event or circumstance that it is advised of; or
      • (ii) if it becomes aware as referred to in subclause (2)(b), the event or circumstance that leads it to believe the metering installation is or could be—
        • (A) inaccurate; or
        • (B) defective; or
        • (C) not fit for purpose; and
    • (b) complete, or arrange the completion of, a report that contains details of the metering equipment provider’s investigation, its conclusion, and the reasons for its conclusion; and
    • (c) provide the report to all affected participants.
  • (5) The time period for the purposes of subclause (4) is as soon as reasonably practicable, but no later than—
    • (a) 20 business days after becoming aware of the event or circumstance, for a category 1 metering installation:
    • (b) 10 business days after becoming aware of the event or circumstance, for a category 2 metering installation:
    • (c) 5 business days after becoming aware of the event or circumstance, for a category 3 or higher metering installation.

10.44

Metering installations that are inaccurate, defective, or not fit for purpose to be tested

  • (1) A metering equipment provider must, if a report provided under clause 10.43(4)(c) demonstrates that a metering installation for which it is responsible is inaccurate, defective, or not fit for purpose—
    • (a) arrange testing of the metering installation by an ATH; and
    • (b) arrange the provision of a statement of situation referred to in clause 10.46 by the ATH.
  • (2) If the report demonstrates that a metering installation is accurate, not defective, and fit for purpose, a participant who believes that the metering installation is inaccurate, defective, or not fit for purpose, may require testing of the metering installation by—
    • (a) advising the metering equipment provider responsible for the metering installation, within 5 business days of receiving the report, of—
      • (i) its reasons for requiring testing; and
      • (ii) the scope of the testing required; and
    • (b) using its best endeavours to agree with the metering equipment provider on an ATH who will test the metering installation and provide a statement of situation under subclause (1).
  • (3) A metering equipment provider who has been advised under subclause (2)(a) that a participant believes that a metering installation, for which the metering equipment provider is responsible, requires testing, must arrange for an ATH
    • (a) to test the metering installation; and
    • (b) to provide the metering equipment provider with a statement of situation under subclause (1)(b) within 5 business days of—
      • (i) becoming aware that a metering installation for which it is responsible may be inaccurate, defective, or not fit for purpose under subclause (1); or
      • (ii) reaching an agreement with the participant under subclause (2)(b).
  • (4) If the metering equipment provider and the participant requesting the test under subclause (2) cannot, within 5 business days of the metering equipment provider being advised under subclause (2)(a), agree on an ATH, either participant may advise the Authority, including the reasons, if and to the extent known, why agreement was not reached.
  • (5) The Authority must, within 5 business days of being advised under subclause (4), advise the metering equipment provider of the ATH that it must instruct to carry out the testing and to provide a statement of situation under subclause (1)(b).
  • (6) The metering equipment provider must instruct the ATH referred to in subclause (5) within 5 business days of being advised by the Authority.
  • (7) The metering equipment provider must ensure that the ATH, as soon as practicable after being contracted under subclause (1) or subclause (5), carries out the required testing and delivers the statement of situation to the metering equipment provider.
  • (8) Despite anything else in this Code, a participant is in breach of this Code from when the tests carried out by an ATH under this clause demonstrate that a metering installation is—
    • (a) inaccurate; or
    • (b) defective; or
    • (c) not fit for purpose.

Clause 10.44(4), (5) and (6): amended, on 5 October 2017, by clause 177 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

10.45

Investigation and testing costs

The ATH’s costs incurred by the metering equipment provider under clause 10.44 must be borne by—

  • (a) the metering equipment provider, if the investigation or test demonstrates that the metering installation is—
    • (i) defective; or
    • (ii) inaccurate; or
    • (iii) not fit for purpose; or
  • (b) the participant who required that the metering installation be investigated or tested, if the investigation or test demonstrates that the metering installation is—
    • (i) not defective; and
    • (ii) accurate; and
    • (iii) fit for purpose.

10.46

Statement of situation

  • (1) A statement of situation provided by an ATH under clause 10.44(1)(b) must include—
    • (a) details of the tests carried out; and
    • (b) results of the tests carried out; and
    • (c) full details of what was found; and
    • (d) conclusions of whether the metering installation is—
      • (i) accurate:
      • (ii) defective:
      • (iii) fit for purpose; and
    • (e) the reasons for the conclusions in paragraph (d); and
    • (f) an assessment of the risk to the completeness and accuracy of the raw meter data; and
    • (g) the details of any remedial action proposed or undertaken; and
    • (h) any correction factors to apply to raw meter data to ensure that the volume information is accurate; and
    • (i) the period over which the correction factor must be applied to the raw meter data.
  • (2) A metering equipment provider must, within 3 business days of receiving the statement of situation, provide copies of it—
    • (a) to the relevant affected participants for all metering installations; and
    • (b) to the Authority
      • (i) for all category 3 and above metering installations; and
      • (ii) if requested by the Authority, for each category 1 metering installation and each category 2 metering installation.

Clause 10.46(2): substituted, on 15 May 2014, by clause 13 of the Electricity Industry Participation (Minor Code Amendments) Code Amendment 2014.

Clause 10.46(2)(b): amended, on 5 October 2017, by clause 178 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

10.46A

Timeframe for correcting defects and inaccuracies in metering installation

  • (1) This clause applies to a metering equipment provider that becomes aware, or is advised under clause 10.43, that a metering installation for which it is responsible, is—
    • (a) inaccurate; or
    • (b) defective; or
    • (c) not fit for purpose.
  • (2) A metering equipment provider to which this clause applies—
    • (a) must undertake remedial action to make the metering installation
      • (i) accurate; and
      • (ii) not defective; and
      • (iii) fit for purpose; and
    • (b) must use its best endeavours to complete the remedial action under paragraph (a) no later than 10 business days after the date on which it is required to provide a report to all affected participants under clause 10.43(4)(c).

Clause 10.46A: inserted, on 1 February 2021, by clause 16 of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

10.47

ATH to keep records of modifications to correct defects and inaccuracies in metering installation

An ATH must, when taking action to remedy an inaccuracy or defect within a metering installation, ensure that records of any modifications that are carried out to the metering installation are kept for each metering component of the metering installation in the metering records and in a manner reasonable in the circumstances to ensure that further investigation can be carried out.

Clause 10.47 Heading: amended, on 1 February 2021, by clause 17 of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

10.48

Correction of defects and inaccuracies in raw meter data

  • (1) A participant may, within 40 business days of receiving a statement of situation under clause 10.46(2), advise the metering equipment provider of any questions, or requests for clarification, it has in relation to the corrections needed to the raw meter data from the metering installation.
  • (2) A metering equipment provider must, within 10 business days of being advised under subclause (1), respond in detail to the questions or requests for clarification.
  • (3) A metering equipment provider must, within 10 business days of being advised under subclause (1), advise the reconciliation participant responsible for providing submission information for the point of connection, of the correction factors referred to in clause 10.46(1)(h) and the period referred to clause 10.46(1)(i).
  • (4) The reconciliation participant must apply the correction factors advised under subclause (3), for the period advised under subclause (3), to the raw meter data to obtain more accurate information as required under clause 15.12.

NSP table

10.49

NSP table

  • (1) The Authority must publish an NSP table.
  • (2) The reconciliation manager must advise the Authority of any change to the information contained in the NSP table within 1 business day of becoming aware of such change.
  • (3) The Authority must update the NSP table within 2 business days of being advised by the reconciliation manager under subclause (2).

Clause 10.49(1): replaced, on 5 October 2017, by clause 179(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

Clause 10.49(2) and (3): amended, on 5 October 2017, by clause 179(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

Dispute resolution

10.50

Dispute resolution

  • (1) A participant must, in good faith, use its best endeavours to resolve any dispute with any other person about a matter dealt with in this Part.
  • (2) A participant may refer any dispute or failure to reach agreement within the required timeframe in this Part to the Authority for determination.
  • (3) If a complaint is not resolved under subclause (1), or by determination of the Authority under subclause (2), the Authority or a participant may refer the complaint to the Rulings Panel in accordance with subpart 4 of Part 2 of the Act and the regulations.
  • (4) When determining a dispute, or failure to reach agreement, under subclause (2), the Authority must do so in a way that—
    • (a) is consultative with the parties involved; and
    • (b) encourages the parties, where possible, to work together on matters that are agreed; and
    • (c) takes into account the costs to be borne by, and the benefits that would accrue to, the participants involved; and
    • (d) maximises the use of informal means to resolve the dispute or conclude an agreement.
  • (5) The existence of a dispute or failure to reach agreement does not excuse a participant from complying with this Code.
  • (6) A participant’s obligations in this clause are subject to the Act and the regulations.

Clause 10.50(3): amended, on 20 December 2021, by clause 28(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.

Clause 10.50(6): amended, on 20 December 2021, by clause 28(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.

Transitional provisions

10.51

Transitional provisions

  • (1) In this clause—
    • (a) Part 10 means Part 10 of the Code that was effective prior to 29 August 2013; and
    • (b) reference to a COP means a code of practice under Part 10.
  • (2) The intent of this clause is—
    • (a) as far as practicable, to preserve the effect of Part 10, prior to 29 August 2013; and
    • (b) to clarify that a breach of Part 10 will subsist as a breach of the Code, despite the coming into force of this Part; and
    • (c) to clarify that disputes and complaints about breaches under Part 10 must be resolved under this Part, and to provide the procedure to ensure that will happen; and
    • (d) to clarify that certain exemptions, authorisations, and code of practice 10.5 variations under Part 10 will remain in force in accordance with their terms, as if they had been made under this Part; and
    • (e) to clarify the effect of certain contractual arrangements after this Part comes into force; and
    • (f) to clarify the effect of a participant being in compliance with certain of the provisions in Part 10, after this Part comes into force.
  • (3) A certification, as at 28 August 2013, of—
    • (a) a metering installation
      • (i) as a category 1 metering installation that had interim certification under Part 10, continues under this Part until 1 April 2015; and
      • (ii) as a category 6 metering installation, continues as a category 5 metering installation and otherwise in accordance with the terms of the certification; and
      • (iii) as any other category, continues under this Part in accordance with the terms of the certification; and
    • (b) a metering component continues under this Part in accordance with the terms of the certification.
  • (4) An audit that was carried out under the Code by an auditor, that was completed, immediately prior to 29 August 2013, continues to have the effect and status of an audit under this Part.
  • (5) The following persons certified and approved by the Electricity Commission or the Authority, under the Code, immediately prior to 29 August 2013, remain, for all purposes of this Part, certified and approved by the Authority, in accordance with the terms and scope of the relevant certification and approval as if such certification and approval had been issued under this Part:
    • (a) an auditor; and
    • (b) an approved test house, which will be approved as an ATH under this Part.
  • (6) The following continue in effect despite anything else in, or the coming into force of, this Part, to the extent that they relate to or concern the same, or similar, obligations under this Part, and will apply to a participant’s obligations under or compliance with, the relevant obligation under this Part:
    • (a) an approval for an alternative quality management system previously issued under clauses 4(4) and 6(12) of COP 10.2:
    • (b) an approval for an alternative standard previously issued under clause 3(4) of COP 10.2 and clause 2 of COP 10.2 and 10.3:
    • (c) a variation under clause 3(15) or 4(7) to 4(9) of COP 10.3:
    • (d) a temporary certification under clause 9(17) of COP 10.3:
    • (e) an alternative standard that an approved test house has used in the certification of a metering installation under clause 2 of COP 10.3 and clause 2 of COP 10.4:
    • (f) a variation approved by the market administrator under COP 10.5:
    • (g) a statistical sampling process under clause 5(18) of COP 10.3:
    • (h) an exemption under section 11 of the Act.
  • (7) An ATH must, if it has certified a metering installation using an alternative standard referred to in subclause (6)(e), in accordance with Part 10, advise the Authority of that alternative standard within 3 business days of 29 August 2013.
  • (8) The following continue in effect, despite anything else in, or the coming into force of, this Part, to the extent that they relate to or concern the same, or similar, obligations under this Part, and apply to a participant’s obligations under or compliance with, the relevant obligation under this Part:
    • (a) calibration intervals referred to in clause 6(1) of COP 10.2; and
    • (b) the maximum intervals between inspections referred to in clause 9(2) of COP 10.3, provided that if the date by which the next inspection would, under this Part, be later, then such later date will apply.
  • (9) Despite anything else in, or the coming into force of, this Part—
    • (a) clause 10.4 and clauses 10.12 to 10.15 of Part 10 continue to apply insofar as they relate to all raw meter data interrogated and processed under Part 10, on which submission information is based that is still subject to the reconciliation process under Part 15, until the reconciliation process for the submission information has been concluded in accordance with Part 15; and
    • (b) clauses 10.7(b) and (c) of Part 10 continue to apply in relation to all raw meter data recorded before 29 August 2013; and
    • (c) an approved test house’s obligations under clauses 5(16) and 5(17) of COP 10.2 and clause 4(12) of COP 10.3 will continue in accordance with their terms in relation to all records created before 29 August 2013.
  • (10) If a participant is a party to an arrangement, assignment, or contract (including an agency agreement) previously entered into under clauses 10.2, 10.3, or 10.6 of Part 10 in relation to a participant’s responsibilities under Part 10 and a provision in that arrangement, assignment, or contract is inconsistent with this Part, the provision ceases to be effective from 29 August 2013, but this is without prejudice to any existing disputes under such arrangements, assignments, or contracts, that must be resolved between the relevant persons concerned in accordance with the arrangement, assignment, or contract as if it remained effective.
  • (11) Despite anything else in, or the coming into force of, this Part—
    • (a) any dispute concerning a metering installation, metering data, raw meter data, and all related matters that were in existence immediately before 29 August 2013,—
      • (i) remain in existence; and
      • (ii) may be resolved under clause 10.50; and
    • (b) any breaches or alleged breaches of Part 10, and investigations of rule breaches or alleged rule breaches under Part 10, are unaffected and must be concluded as if the relevant provisions alleged to have been breached, under Part 10, and the relevant Part 10 definitions remain in force; and
    • (c) any rule breaches or alleged rule breaches described in paragraph (b) will be dealt with by the Authority and the Rulings Panel under clause 10.50 and the Act.
  • (12) Despite anything else in, or the coming into force of, this Part, subclause (13) applies to a participant who was immediately prior to 29 August 2013 responsible under Part 10 for—
    • (a) measuring the quantity of electricity at any metering installation; or
    • (b) estimating the quantity of unmetered load.
  • (13) A participant described in subclause (12), who is responsible for volume information which has not, at 29 August 2013, been submitted to the reconciliation manager in accordance with Part 15 must complete the submission of the volume information to the reconciliation manager in accordance with Part 10, as if that Part remained effective.
  • (14) Despite anything else in, or the coming into force of, this Part, a participant who is responsible for a metering installation under Part 10, immediately prior to 29 August 2013 must remain in compliance with—
    • (a) clauses 10.7(b) and 10.7(c) of Part 10, in respect of raw meter data kept before 29 August 2013, and does not breach any of the corresponding obligations in this Part, provided that the participant keeps the raw meter data in compliance with clauses 10.7(b) and 10.7(c) of Part 10; and
    • (b) clause 10 of COP 10.3, in respect of records kept before 29 August 2013, and does not breach any of the corresponding obligations in this Part, provided that the participant keeps the records in compliance with rule 10 of COP 10.3.
  • (15) The following procedures commenced before, but not completed by, 29 August 2013 are not valid unless they are completed in compliance with this Part:
    • (a) metering installation tests; and
    • (b) audits of an approved test house under Part 10 (which must be completed as an audit of an ATH under this Part).
  • (16) The obligations of a metering equipment provider expressed in this Part as applying in relation to arranging certification of a metering installation or a metering component after 29 August 2013 do not apply to—
    • (a) a metering installation referred to in subclause (3)(a):
    • (b) a metering component referred to in subclause 3(b).

Clause 10.51: amended, on 29 August 2013, by clause 25 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 10.51(6)(f): amended, on 5 October 2017, by clause 180 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

Schedule 10.1

cls 10.37 and 10.43

Tables

Table 1: Metering installation characteristics and associated requirements

Defining Characteristics

Associated Requirements of active energy metering

Metering installation category

Primary voltage

(V)

Primary current 

(I)

Measuring transformers

Metering
installation certification type

Maximum meter class for installation category

Accuracy tolerances

Selected component metering installation minimum IEC class (more accurate components may be used)

Metering installation

certification and inspection

Maximum permitted error

Maximum site uncertainty

Meter 

Current Transformer

Maximum metering installation certification
validity period

Maximum inspection period 

1

V < 1kV

I ≤ 160A

None

NHH or HHR

Class 2.0

± 2.5%

0.6%

2

N/A

180 months

126 months

2

V < 1kV

I ≤ 500A

CT and where applicable, VT

NHH or HHR

Class 2.0

± 2.5%

0.6%

2

1

120 months

126 months

3

V < 1kV

500A < I ≤ 1200A

CT

HHR only


Class 1.0

± 1.25%

0.3%

1

0.5

120 months

63 months

V < 1kV

500A < I ≤ 1200A

VT & CT



Class 0.5

N/A

N/A

1kV ≤ V ≤ 11kV

I ≤ 100A

11kV < V ≤ 22kV

I ≤ 50A

4

V < 1kV

I > 1200A

CT

HHR only






Class 0.5

± 1.25%

0.3%

N/A

N/A

60 months

33 months

V < 1kV 

I > 1200A

VT & CT

1kV ≤ V ≤ 6.6kV

100A < I ≤ 400A

6.6kV < V ≤ 11kV

100A < I ≤ 200A

11kV < V ≤ 22kV

50A < I ≤ 100A

5

1kV ≤ V ≤ 6.6kV

I > 400A

VT & CT

HHR only



Class 0.2

± 0.75%

0.2%

N/A

N/A

36 months

19 months

6.6kV < V ≤ 11kV 

I>200A

V > 11kV

I > 100A

V > 22kV

Any current

 

Schedule 10.1, Table 1: replaced, on 1 February 2021, by clause 18 of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Table 2: [Revoked]

Schedule 10.1, Table 2: revoked, on 1 February 2021, by clause 19 of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Table 3: Selected component certification and comparative recertification minimum test requirements

 

Event

Design check

Prevailing load test

Data storage device check

Software security and communication equipment check

Control device check

Wiring check

Component certification check

Review of compensation factors

Raw meter data output test

Supply polarity check

Register advance test

Installation or component configuration check

Category 1 metering installations

Initial certification, or recertification with all meters replaced

M

   

M

MI

M

M

M

M

M

M

M

Recertification with no meters replaced 

M

M

 

M

MI

M

M

M

M

M

M

M

Recertification with one or more meters replaced with a certified meter(s), at least one existing meter remains, and metering installation expiry date is not changed

M

   

M

MI

M

M

M

M

M

M

M

Recertification with one or more meters replaced with a certified meter(s), at least one existing meter remains (which must have calibration that is valid for the new certification period), and metering installation expiry date is changed

M

M

 

M

MI

M

M

M

M

M

M

M

Categories 2 – 3

Initial certification, recertification, or meter change including internal data storage devices

M

M

MI

(for Cat 3 only)

M

MI

M

M

M

M

M

M

M

Measuring transformer change or ratio change 

M

M

     

M

M

M

M

M

M

M

Categories 1– 3

Metrology software change either onsite or remote 

M

 

M

M

   

M

M

M

 

M

M

External data storage device change 

M

 

M

M

 

M

M

M

M

 

M

M

Control device change 

M

 

MI

 

M

M

M

 

M

   

M

Additional equipment (eg wiring) 

M

M

     

M

   

M

M

M

M

Key: M = mandatory, MI = mandatory if installed.

Table 3: rows 6 and 8 amended, on 15 May 2014, by clause 14 of the Electricity Industry Participation (Minor Code Amendments) Code Amendment 2014.

Table 3: row 3 amended, on 19 December 2014, by clause 21 of the Electricity Industry Participation Code Amendment (Minor Code Amendments) (No 3) 2014.

Table 3: replaced, on 1 February 2021, by clause 20 of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Table 4: Fully calibrated certification minimum test requirements

Event

Design

Measuring transformer

Meter

Primary injection to meter

Prevailing load

Data storage device

Software security and communication equipment

Control device

Wiring check

Component certification

check

Review of compensation factors

Raw meter data output

Supply

polarity

Register advance

Installation or component

configuration

Metering installation

Initial certification

M

M

M

T

M

M

M

M

M

M

M

M

M

M

M

Recertification

M

 

M

 

M

M

M

M

M

M

M

M

M

M

M

Meter change including internal data storage device

M

 

M

 

M

M

M

 

M

 

M

M

M

M

M

Metrology change either onsite or remote

M

 

M

   

M

M

     

M

M

 

M

M

Component change or recertification

External data storage device change

M

       

M

M

 

M

 

M

M

 

M

M

Measuring transformer change or ratio change 

M

M

 

T

M

     

M

 

M

M

M

M

 

Control device change 

M

       

MI

 

M

M

   

M

   

M

Additional equipment (eg wiring)

M

   

T

M

     

M

   

M

M

M

 

Initial certification

M

M

M

T

M

M

M

M

M

M

M

M

M

M

M

Recertification

M

 

M

 

M

M

M

M

M

M

M

M

M

M

M

Key: M = mandatory, T = mandatory if test method and test equipment permit, MI = mandatory if the control device is integral with the meter.

Table 5: Standards for metering components

Meter and data storage device standards 

Standards 

Electricity metering equipment (AC) – Part 1: General requirements, tests and test conditions (classes 0.5, 1 and 2)

EN 50470-1

Electricity metering equipment (AC) – Part 2: Particular requirements – Electromechanical meters for active energy (classes 1 and 2)

EN 50470-2

Electricity metering equipment (AC) – Part 3: Particular requirements – Static meters for active energy (classes 0.5, 1 and 2)

EN 50470-3

Electricity metering equipment (AC) – Particular requirements – Part 11: Electromechanical meters for active energy (classes 0.5, 1 and 2)

IEC 62053-11

Electricity metering equipment (AC) – Particular requirements – Part 21: Static meters for active energy (classes 1 and 2)

IEC 62053-21

Electricity metering equipment (AC) – Particular requirements – Part 22: Static meters for active energy (classes 0.2 S and 0.5 S)

IEC 62053-22

Electricity metering equipment (AC) – Particular requirements – Part 23: Static meters for reactive energy (classes 2 and 3)

IEC 62053-23

Electricity metering equipment (AC) – Particular requirements – Part 61: Power consumption and voltage requirements

IEC 62053-61

Electricity metering equipment (AC) – General requirements, tests and test conditions – Part 11: Metering equipment

IEC 62052-11

Measuring transformer standards

 

Instrument transformers – Part 1: Current transformers

IEC 60044-1

Instrument transformers – Part 2: Inductive voltage transformers

IEC 60044-2

Instrument transformers – Part 3: Combined transformers

IEC 60044-3

Instrument transformers – Part 5: Capacitor voltage transformers

IEC 60044-5

Coupling capacitors and capacitor dividers

IEC 60358

Instrument transformers – Part 7: Electronic voltage transformers

IEC 60044-7

Instrument transformers – Part 8: Electronic current transformers

IEC 60044-8

Other standards

 

Electricity metering equipment (AC) – Tariff and load control – Part 11: Particular requirements for electronic ripple control receivers

IEC 62054-11

Electricity metering equipment (AC) – Tariff and load control – Part 21: Particular requirements for time switches

IEC 62054-21

 

Table 5: row 1 amended, on 15 May 2014, by clause 15 of the Electricity Industry Participation (Minor Code Amendments) Code Amendment 2014.

Table 6: Standards of accuracy and overall uncertainty for active and reactive meter calibration and testing

Value of Current %

Power Factor

Maximum Overall Uncertainty %

Percentage Error

Limits of Meter,

Including Uncertainty

Class of meter 2.0 and 2.0S

5 to 120

1

±0.4

±1.9

10 to 120

0.5 lagging

±0.6

±1.9

10 to 120

0.8 leading

±0.6

±1.9

Class of meter 1.0 and 1.0S

5 to 120

1

±0.2

±0.9

10 to 120

0.5 lagging

±0.25

±0.9

10 to 120

0.8 leading

±0.25

±0.9

Class of meter 0.5 and 0.5S

5 to 120

1

±0.1

±0.5

10 to 120

0.5 lagging

±0.12

±0.6

10 to 120

0.8 leading

±0.12

±0.6

Class of meter 0.2S

5 to 120

1

±0.06

±0.2

10 to 120

0.5 lagging

±0.09

±0.3

10 to 120

0.8 leading

±0.09

±0.3

Class of meter 3.0 reactive

20 to 120

Zero

±1.0

±3.0

20 to 120

0.8 leading

±1.5

±3.5

20 to 120

0.8 lagging

±1.5

±3.5

Class of meter 2.0 reactive

20 to 120

Zero

±0.5

±2.0

20 to 120

0.8 leading

±1.0

±2.5

20 to 120

0.8 lagging

±1.0

±2.5

Table 7: Voltage, current, and phase displacement parameters for polyphase meters

Polyphase meters

Class of meter

0.2 and 0.5

1.0

2.0

3.0

Each of the voltages between line and neutral or between any 2 lines will not differ from the average corresponding voltage by more than:


±0.1%


±1.0%


±1.0%


±1.0%

Each of the currents in the conductors will not differ from the average current by more than:

±1.0%

±2.0%

±2.0%

±2.0%

The phase displacements of each of these currents from the corresponding line-to-neutral voltage, irrespective of the power factor, will not differ from each other by more than:





Schedule 10.1, Table 7: amended, on 1 February 2016, by clause 30 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2015.

Table 8: Required minimum sample size for category 1 metering installation inspections required under clause 45(2)(c) of Schedule 10.7

Number of metering installations identified 

Minimum sample size

1

1

2-8

2

9-15

3

16-25

5

26-50

8

51-90

13

91-150

20

151-280

32

281-500

50

501-1200

80

1201-3200

125

3201-10,000

200

10,001-35,000

315

35,001-150,000

500

150,001+

800

Schedule 10.2

cl 10.17

[Revoked]

Schedule 10.2: revoked, on 1 June 2017, by clause 10 of the Electricity Industry Participation Code Amendment (Requirements and Processes for Audits) 2016.

Schedule 10.3

cl 10.40

ATHs – approval, expiry, cancellation, and renewal of approval

1

Applications for approval and renewal of approval

  • (1) A person wishing to be approved as an ATH, or an ATH wishing to renew its approval, must apply, in the prescribed form, to the Authority at least 2 months before the intended effective date of the approval or renewal.
  • (2) An applicant must—
    • (a) include in its application—
      • (i) the final audit report obtained under Part 16A, together with its responses to the report; and
      • (ii) a copy of any quality management certificates it holds; and
      • (iii) a copy of its most recent quality management audit report; and
      • (iv) the class of ATH for which it is seeking approval; and
      • (v) the functions under clauses 3(2) and 4(2) for which it is seeking approval; and
      • (vi) the calibration expiry date of each of its working standards and reference standards; and
    • (b) provide promptly any other information or documentation the Authority may reasonably request.
  • (3) The Authority must, within 2 months of receiving an application, advise the applicant of—
    • (a) the approval of the application, if the applicant satisfies the Authority that it has met the requirements set out in clause 10.40; or
    • (b) the declination of the application, providing reasons, if the Authority considers that—
      • (i) the information supplied by the applicant is incomplete or unsatisfactory; or
      • (ii) the applicant otherwise fails to demonstrate that it would be, and would remain for the period and functions for which the application is made, compliant with the requirements set out in clause 10.40.
  • (4) If an application is approved, the Authority must issue a certificate of approval specifying the—
    • (a) period of the term of approval, which must not exceed 12 months from the date of approval; and
    • (b) functions that the applicant has been approved to carry out; and
    • (c) [Revoked]
    • (d) date of approval.

Clause 1(2)(a)(i): amended, on 1 June 2017, by clause 11(1) of the Electricity Industry Participation Code Amendment (Requirements and Processes for Audits) 2016.

Clause 1(4)(a): amended, on 5 October 2017, by clause 181 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

Clause 1(4)(c): revoked, on 1 June 2017, by clause 11(2) of the Electricity Industry Participation Code Amendment (Requirements and Processes for Audits) 2016.

2

[Revoked]

Clause 2: revoked, on 1 June 2017, by clause 12 of the Electricity Industry Participation Code Amendment (Requirements and Processes for Audits) 2016.

3

Approval of class A ATHs

  • (1) An applicant applying for approval, or renewal of approval, as a class A ATH must, as part of its application, confirm that—
    • (a) it holds and complies with AS/NZS ISO 17025 accreditation, for at least the requested term of the approval; and
    • (b) the scope of its AS/NZS ISO 17025 accreditation covers the activities that it undertakes, or proposes to undertake; and
    • (c) it complies, and will be likely to continue to comply during the requested term of the approval, with any requirements of its ISO accreditation; and
    • (d) if it proposes to carry out field work—
      • (i) it is certified to the relevant AS/NZS ISO 9001:2008 or AS/NZS ISO 9001:2016 and will remain certified during the requested term of the approval; and
      • (ii) the scope of its AS/NZS ISO 17025 accreditation has been extended to cover the carrying out of the field work.
  • (2) The Authority may approve an applicant to be, or renew an applicant’s approval as, a class A ATH to carry out 1 or more of the following functions:
    • (a) calibration of—
      • (i) working standards:
      • (ii) metering components (other than a calibration referred to in paragraph (c)):
      • (iii) metering installations:
    • (b) issuing calibration reports:
    • (c) calibration of metering components onsite:
    • (d) installation and modification of metering installations:
    • (e) installation and modification of metering components:
    • (f) certification of all categories of metering installations under this Code, and issuing of certification reports:
    • (g) testing of metering installations under clause 10.44 and production of statements of situation under clause 10.46:
    • (h) inspection of metering installations.
  • (3) A class A ATH may only carry out 1 or more of the functions listed in subclause (2), subject to—
    • (a) the current scope of its approval under subclause (2); and
    • (b) any limitations that may be specified in the class A ATH’s AS/NZS ISO 17025 accreditation or the relevant AS/NZS ISO 9001:2008 or AS/NZS ISO 9001:2016 certification.
  • (4) The Authority may decline an application for approval as a class A ATH even if the applicant—
    • (a) has obtained the necessary ISO accreditation or certification; or
    • (b) has obtained or satisfied any other pre-requisite to approval.

Clause 3(1)(b): amended, on 29 August 2013, by clause 26 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 3(1)(d)(i) and 3(3)(b) amended, on 1 June 2017, by clause 13 of the Electricity Industry Participation Code Amendment (Requirements and Processes for Audits) 2016.

4

Approval of class B ATHs

  • (1) An applicant applying for approval, or renewal of approval, as a class B ATH must, as part of its application to the Authority, confirm that—
    • (a) it holds and complies with AS/NZS ISO 9001:2016 certification for at least the term of the requested approval; and
    • (b) the scope of its AS/NZS ISO 9001:2016 certification covers the activities that it undertakes, or proposes to undertake; and
    • (c) it will develop and at all times during the term of the requested approval maintain a conflict of interest policy in compliance with AS/NZS ISO 17025.
  • (1A) Despite subclause (1), an applicant may apply to the Authority for approval as a class B ATH without confirming that it holds and complies with AS/NZS ISO 9001:2016 certification for at least the term of the requested approval, provided the applicant confirms as part of its application that—
    • (a) it holds and complies with AS/NZS ISO 9001:2016 certification at the time of the application and that certification expires during the approval period; and
    • (b) it has in place appropriate plans to ensure that it renews its AS/NZS ISO 9001:2016 certification for the term of the requested approval, so that its AS/NZS ISO 9001:2016 certification remains in place continuously throughout the approval period.
  • (2) The Authority may approve an applicant to be, or renew an applicant’s approval as, a class B ATH to carry out 1 or more of the following functions:
    • (a) calibration of class 0.5 meters, class 1 meters and class 2 meters, and class 0.5 current transformers and class 1.0 current transformers, provided that the calibrations are carried out under their approved quality certification and in accordance with this Part, and included within the ATH audit for approval:
    • (b) installation and modification of metering installations:
    • (c) installation and modification of metering components:
    • (d) calibration of metering components onsite:
    • (e) certification, using the selected component certification method, of—
      • (i) category 1 metering installations:
      • (ii) category 2 metering installations:
      • (iii) category 3 metering installations with a primary voltage of less than 1kV:
    • (f) certification, using the fully calibrated certification method, of—
      • (i) category 1 metering installations:
      • (ii) category 2 metering installations:
      • (iii) category 3 metering installations with a primary voltage of less than 1kV:
    • (g) certification, using the comparative recertification method, of category 2 metering installations:
    • (h) issuing of certification reports in respect of certifications of metering installations under paragraphs (e) to (g):
    • (i) inspection of—
      • (i) category 1 metering installations:
      • (ii) category 2 metering installations:
      • (iii) category 3 metering installations with a primary voltage of less than 1kV.
  • (3) A class B ATH may only carry out 1 or more of the functions listed in subclause (2), subject to—
    • (a) the current scope of its approval under subclause (2); and
    • (b) any limitations that may be specified in the relevant AS/NZS ISO 9001:2008 or AS/NZS ISO 9001:2016 certification.
  • (4) The Authority may decline an application for approval as a class B ATH even if the applicant—
    • (a) has obtained the necessary ISO certification; or
    • (b) has obtained or satisfied any other pre-requisite to approval.

Clause 4(1)(a) and (b) amended, on 1 June 2017, by clause 14 of the Electricity Industry Participation Code Amendment (Requirements and Processes for Audits) 2016.

Clause 4(1)(b): amended, on 29 August 2013, by clause 27 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 4(1)(a), (b) and (c): amended, on 1 February 2021, by clause 21(1)(a) and (b) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 4(1A): inserted, on 1 February 2021, by clause 21(2) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 4(3)(b) amended, on 1 June 2017, by clause 14 of the Electricity Industry Participation Code Amendment (Requirements and Processes for Audits) 2016.

4A

Incorporation of AS/NZS ISO 9001:2008 and AS/NZS ISO 9001:2016 by reference

  • (1) The New Zealand Standards AS/NZS ISO 9001:2008 and AS/NZS ISO 9001:2016 are incorporated by reference in this Code.
  • (2) [Revoked]
  • (3) [Revoked]

Clause 4A: inserted, on 1 June 2017, by clause 15 of the Electricity Industry Participation Code Amendment (Requirements and Processes for Audits) 2016.

Clause 4A(1): amended, on 1 August 2023, by clause 40(1) of the Electricity Industry Participation Code Amendment (System Operation Documents) 2023.

Clauses 4A(2) and 4A(3): revoked, on 1 August 2023, by clause 40(2) and 40(3) of the Electricity Industry Participation Code Amendment (System Operation Documents) 2023.

5

Expiry and cancellation of approval

  • (1) If the Authority believes that an ATH is or was in breach of this Part the Authority may cancel the approval of the ATH with immediate effect by advising the ATH.
  • (2) An ATH must not, at any time after the expiry or cancellation of its approval, display or use its certificate of approval.

6

Changes that affect approval

  • (1) If an ATH intends to make a material change to any of its facilities, processes, or procedures, or the scope of the ATH’s ISO accreditation is reduced during the term of its approval, the ATH must, at least 5 business days before the change is to take place or reduction in scope is effected,—
    • (a) advise the Authority of all relevant details of the change or reduction in scope; and
    • (b) in the case of a material change, submit to the Authority an audit report confirming that, after the change has come into effect, the ATH will continue to meet the requirements under clause 10.40(2)(a).
  • (2) An ATH’s approval is automatically cancelled from the date of the change or reduction in scope under subclause (1), if the ATH fails to advise the Authority under subclause (1)(a).
  • (3) The Authority may, if it is advised by an ATH under subclause (1), either—
    • (a) cancel an ATH’s approval from the date that the Authority advises the ATH that the Authority is not satisfied that the ATH will continue to meet the requirements under clause 10.40(2)(a) after the change or reduction in scope has come into effect; or
    • (b) revise the scope of the ATH’s approval.

7

Notice of cancellation, expiry, or revision of scope of ATH approval

  • (1) The Authority must give written notice to all metering equipment providers if—
    • (a) an ATH’s approval expires and the Authority does not renew it:
    • (b) the Authority cancels an ATH’s approval under clause 5:
    • (c) an ATH’s approval is cancelled under clause 6(2) or 6(3)(a):
    • (d) the scope of an ATH’s approval has been revised under clause 6(3)(b).
  • (2) The Authority must include with the notice under subclause (1) the date on which the approval expired or was cancelled, or the scope of the approval was revised.
  • (3) A metering equipment provider given notice under subclause (1) must treat all metering installations certified by the ATH during the period during which it was not validly approved, or was performing activities outside its scope of approval, as being defective from the date of which the Authority gave notice under subclause (2) and follow the procedures set out in clauses 10.43 to 10.48.
  • (4) Despite subclause (3), the Authority may give a metering equipment provider written notice that the metering equipment provider must treat a metering installation certified by the ATH as being defective and follow the procedures set out in clauses 10.43 to 10.48.

Clause 7 Heading: amended, on 1 November 2018, by clause 29 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.

Clause 7: amended, on 5 October 2017, by clause 182 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

8

Register of ATHs

  • (1) The Authority must, keep, maintain, and publish a register of approved ATHs.
  • (2) The Authority must remove an ATH’s details from the register if the ATH’s approval—
    • (a) expires and the Authority does not renew it; or
    • (b) is cancelled.

Schedule 10.4

cl 10.42

ATH ongoing functions and obligations

1

Accommodation and environment

An ATH must, for each approved test house that it operates,—

  • (a) maintain a list of personnel who are authorised to access and use its laboratory and storage facilities; and
  • (b) restrict access to its laboratory and storage facilities to—
    • (i) the personnel specified under paragraph (a); and
    • (ii) the Authority; and
    • (iii) an auditor conducting an audit; and
    • (iv) any other person who is, at all times, directly supervised by a member of personnel specified under paragraph (a); and
  • (c) restrict access to its metering records to—
    • (i) the relevant metering equipment provider:
    • (ii) the Authority:
    • (iii) an auditor conducting an audit:
    • (iv) the relevant metering component owner; and
  • (d) ensure that the environment in which its activities are undertaken does not, or could not reasonably be expected to, invalidate test results or adversely affect the required accuracy of measurement; and
  • (e) monitor and record the environmental conditions within its approved test house’s laboratory and storage facilities; and
  • (f) comply with the specific requirements of the applicable standard listed in Table 5 of Schedule 10.1 for the calibrations or tests being carried out.

Clause 1(c)(iv): amended, on 29 August 2013, by clause 28 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

2

Equipment

  • (1) An ATH must, at all times, ensure that—
    • (a) it has access to all items of equipment required for the performance of the calibrations and tests it is approved to undertake under this Part; and
    • (b) each item of equipment it uses is maintained in accordance with the manufacturer’s recommendations and this Code (but if there is any inconsistency or contradiction between the manufacturer’s recommendations and this Code, this Code takes precedence); and
    • (c) it maintains records about each item of its equipment, including—
      • (i) details of—
        • (A) maintenance history; and
        • (B) the ATH’s maintenance programme; and
      • (ii) calibration reports, including before and after adjustment results; and
      • (iii) in-service checks; and
      • (iv) a history of any damage, malfunction, modification, or repair.
  • (2) A class B ATH must have and maintain procedures for the purchase of test equipment and associated consumables.

3

Reference standards and working standards

  • (1) An ATH must not use a reference standard or working standard for any activity regulated under this Part unless—
    • (a) in the case of—
      • (i) a reference standard, the reference standard has been calibrated by an approved calibration laboratory; or
      • (ii) a working standard, the working standard has been calibrated by an approved calibration laboratory or a class A ATH; and
    • (b) the current calibration report for the reference standard or working standard confirms that it—
      • (i) performs within the manufacturer’s accuracy specifications; and
      • (ii) has been calibrated under subclause (2) at an interval not exceeding the calibration intervals set out in the following table.

Table 1: Calibration intervals

Standard

Initial calibration 
interval (months 
beginning from the date of the first calibration)

Maximum 
calibration 
interval (months 
beginning from 
the date of the 
current calibration 
report)

Reference standard or working standard (other than a working standard used for on-site calibration) Measuring transformers 36 60
Comparator bridges 36 60
Meters 12 24
Power factor, voltage and current meters 12 24
Working standard used for on-site calibration All 2 12
  • (2) An ATH must ensure that a reference standard or working standard is calibrated
    • (a) for the first time, within the applicable initial calibration interval set out in Table 1 of subclause (1); and
    • (b) for each subsequent calibration, within the applicable maximum calibration interval set out in Table 1 of subclause (1).
  • (3) A class A ATH must ensure that—
    • (a) in all cases of calibration of its reference standards, the uncertainties given in the reference standard calibration report are sufficiently small so that the overall uncertainty in the measurements used to test a metering installation does not exceed one third of the maximum permitted error set out in Table 1 of Schedule 10.1 for the category of metering installation that the reference standard will be used to calibrate; and
    • (b) it does not use a working standard on a system operating at a voltage of 33kV or above between active conductors, unless the working standard has been calibrated by an approved calibration laboratory; and
    • (c) it does not use a reference standard, other than a standard measuring transformer, unless it is maintained at the appropriate reference conditions set out in the reference standard’s current calibration report.
  • (4) If appropriate reference conditions under subclause (3)(c) cannot be achieved, the class A ATH must calculate and apply adjustments in accordance with the processes and procedures under subclause (5) so that the reference standard achieves the errors and uncertainties set out in the reference standard’s current calibration report.
  • (5) An ATH must develop and maintain processes and procedures for calculating and applying adjustments to a reference standard’s errors and uncertainties to compensate for deviations from the reference conditions contained in the reference standard’s current calibration report.
  • (6) An ATH must retain a copy of the current calibration report for each of its reference standards and working standards.

4

Metering component testing systems

An ATH may use a complete calibrated metering component testing system (also known as a test bench) as an alternative to a separately calibrated working standard only if—

  • (a) the ATH calibrates the complete calibrated metering component testing system under clause 3 as if it was a working standard; and
  • (b) before completing the calibration report, the ATH carries out a testing system accuracy test, using approved reference standards.

5

Calibration errors

  • (1) For the purposes of this clause, a reference standard or working standard has a calibration error if it is performing outside of the manufacturer’s accuracy specifications.
  • (2) An ATH must not use a reference standard or working standard for calibration, if it believes, or should reasonably be expected in the circumstances to believe, that the reference standard or working standard has a calibration error.
  • (3) An ATH must, as soon as reasonably practicable, but no more than 3 months after becoming aware of a calibration error—
    • (a) investigate the error; and
    • (b) ensure the cause of the error is recorded in a calibration report; and
    • (c) if the investigation indicates that the reference standard or working standard performs outside the manufacturer’s accuracy specifications, advise each ATH that has used any equipment that was calibrated using the reference standard or working standard since the previous calibration, of the error.
  • (4) An ATH must, if a reference standard or a working standard has a calibration error,—
    • (a) treat each metering installation that it has calibrated using the reference standard or working standard as outside the applicable accuracy tolerances set out in Table 1 of Schedule 10.1; and
    • (b) comply with clause 10.43.
  • (5) For the purposes of this clause, a working standard includes a complete calibrated metering component testing system referred to in clause 4.

6

Measurement traceability

An ATH must document, maintain, and comply with, a system that ensures, whenever it undertakes a calibration test or measurement,—

  • (a) it keeps sufficient records to enable the ATH to replicate the test or measurement in every respect should the need arise; and
  • (b) the results of the measurements are traceable.

Requirements for calibration of metering components

7

Calibration methods

  • (1) An ATH must, before it certifies a metering installation or metering component, ensure that 1 of the following persons has calibrated the metering components under this Part:
    • (a) an approved calibration laboratory; or
    • (b) an ATH with the appropriate approval under Schedule 10.3.
  • (2) An ATH must, before it certifies a metering component, ensure that the metering component is calibrated or adjusted under—
    • (a) the appropriate physical and electrical reference conditions detailed in the standard listed in Table 5 of Schedule 10.1; or
    • (b) conditions which permit the ATH to calculate the results and their uncertainty at the reference conditions detailed in the standard listed in Table 5 of Schedule 10.1.
  • (3) A class B ATH must, when calibrating a metering component,—
    • (a) follow all relevant requirements of NZ/AS ISO 17025 for calibration; and
    • (b) only use the relevant methodologies that have been audited in the class B ATH’s most recent audit for approval.
  • (4) If an ATH calibrates a metering component, it must ensure that the individual test points that it uses are—
    • (a) no less than the minimum set out in the standards listed in Table 5 of Schedule 10.1; or
    • (b) sufficient and appropriate in the circumstances to ensure that the calibration allows calculation of the metering installation error as set out in clause 22 of Schedule 10.7.
  • (5) An ATH must, when calibrating a metering component,—
    • (a) if necessary, adjust and document the error compensation; and
    • (b) ensure that any adjustment carried out under paragraph (a) is appropriate to achieve an error as close as practicable to zero; and
    • (c) ensure that the uncertainty of measurement during the calibration of the metering component does not exceed one third of the maximum permitted error in the relevant standard listed in Table 5 of Schedule 10.1; and
    • (d) if the metering component is intended for a metering installation which is to be certified using the selected component certification method, ensure that the ATH records the errors of a current transformer from 5% to 120% of rated primary current.
  • (6) An ATH must ensure that—
    • (a) it has documented instructions on the use and operation of all relevant equipment it uses for calibration; and
    • (b) it has documented calibration procedures that it must make available to, and ensure are followed by, its staff carrying out the calibration; and
    • (c) its calibration procedures are aligned with the standards listed in Table 5 of Schedule 10.1.
  • (7) An ATH
    • (a) may select a test point other than those specified in the relevant standard listed in Table 5 of Schedule 10.1, or at a lower burden than specified in the standard; but
    • (b) must, if it does this, document its reasons for the selection of these test points in the calibration report.

8

Compensation factors

An ATH must, if it is approved to certify metering installations, have a documented process for determining compensation factors.

9

Seals

An ATH must have a documented system for applying seals to a metering installation, that—

  • (a) meets the requirements of clause 47 of Schedule 10.7; and
  • (b) is appropriate in the circumstances to ensure—
    • (i) the ATH’s ability to monitor the metering installation’s continued integrity; and
    • (ii) the relevant metering equipment provider is alerted as soon as practicable to any unauthorised access to the metering installation.

10

Services access interface

An ATH must, when preparing a metering installation certification report, determine, and record in the certification report,—

  • (a) all services access interfaces; and
  • (b) the conditions under which each services access interface may be used.

Clause 10: replaced, on 1 February 2021, by clause 22 of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

11

Certification and calibration reports

  • (1) An ATH must, for each metering installation that it certifies, produce a certification report in accordance with Schedule 10.7.
  • (2) An ATH must, for each metering component
    • (a) that it calibrates, produce a calibration report in accordance with Schedule 10.8; and
    • (b) that it certifies, produce a certification report in accordance with Schedule 10.8.

12

ATH record keeping and documentation

  • (1) An ATH must ensure it documents and maintains a record system for all records, certificates, and reports for any activity regulated under this Part.
  • (2) An ATH must ensure that—
    • (a) all its records, certificates, and reports are stored securely; and
    • (b) each of its test records for a metering installation is identified by a unique identifier; and
    • (c) all of its records, certificates, and reports are sufficiently detailed to enable verification of all aspects of all tests it carries out, including the following:
      • (i) test conditions; and
      • (ii) specific test equipment used; and
      • (iii) personnel carrying out the tests.

13

Retention of ATH records relating to metering components

  • (1) An ATH must, for each activity regulated under this Part in relation to a metering component that it calibrates or certifies, retain the following records relating to that metering component for at least 48 months after the certification expiry date of the metering component,—
    • (a) all of the ATH’s records, certificates, and reports; and
    • (b) all certification reports produced by the ATH; and
    • (c) all calibration reports produced by the ATH.
  • (2) If an ATH intends to cease being an ATH, the ATH must transfer the records described in subclause (1) to the metering equipment provider either—
    • (a) recorded in the registry as being responsible for the metering installation where the metering component is installed; or
    • (b) identified in the metering records provided to the reconciliation manager under clause 10.26(7)(c) or 10.30(2)(c).

Clause 13: replaced, on 1 March 2024, by clause 38 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2024.

13A

Retention of ATH records relating to metering installations

  • (1) An ATH must, for each activity regulated under this Part in relation to a metering installation that the ATH certifies, retain the following records relating to that metering installation for at least 48 months after the certification expiry date of the metering installation:
    • (a) all of the ATH’s records, certificates, and reports:
    • (b) all certification reports produced by the ATH.
  • (2) If an ATH intends to cease being an ATH, the ATH must transfer the records described in subclause (1) to the metering equipment provider either—
    • (a) recorded in the registry as being responsible for the metering installation; or
    • (b) identified in the metering records provided to the reconciliation manager under clause 10.26(7)(c) or 10.30(2)(c).

Clause 13A: inserted, on 1 March 2024, by clause 39 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2024.

14

Making available of ATH records

An ATH must, within 5 business days of creating a record, certificate, or report for a metering installation that it certifies,—

  • (a) send, in electronic form or such other form as may be agreed between the parties, a copy of the record, certificate, or report to the metering equipment provider responsible for the metering installation; and
  • (b) ensure that the metering equipment provider receives the record, certificate, or report.

15

ATH organisation and management

  • (1) An ATH must ensure that—
    • (a) it has managerial staff who, unless otherwise permitted in the relevant approval, all have the authority and resources needed to discharge their duties; and
    • (b) the responsibilities, authority, and functional relationships of all its personnel are fully and accurately specified and recorded in the ATH’s records.
  • (2) An ATH must appoint—
    • (a) a technical manager (however named) with overall responsibility for technical operations, who must have appropriate engineering qualifications and experience in the operation of an approved test house; and
    • (b) a quality manager (however named), with responsibility for the quality management certification and the implementation of the quality management system.
  • (3) An ATH must ensure that all staff who perform or supervise work or activities regulated under this Part are technically competent, experienced, qualified, and trained for the functions they perform.

16

Quality management system

An ATH must establish, document, implement, maintain, and comply with a quality management system which records its processes and procedures to ensure compliance with this Part.

17

Field work

A class A ATH must, if it arranges for another person to carry out field work, ensure that person is certified to the relevant AS/NZS ISO 9001:2008 or AS/NZS ISO 9001:2016 at all times while the person carries out the work.

Clause 17 amended, on 1 June 2017, by clause 16 of the Electricity Industry Participation Code Amendment (Requirements and Processes for Audits) 2016.

Schedule 10.5

cl 10.20

[Revoked]

Schedule 10.5: revoked, on 1 June 2017, by clause 17 of the Electricity Industry Participation Code Amendment (Requirements and Processes for Audits) 2016.

Schedule 10.6

cl 10.20

Metering equipment provider ongoing obligations and functions

1

Metering equipment provider must provide access to raw meter data

  • (1) A metering equipment provider must, within 10 business days of receiving a request from a trader with whom it has an arrangement to access raw meter data from a metering installation for which the metering equipment provider is responsible, give remote or onsite access at the services access interface to the trader to collect, obtain, and use raw meter data from the metering installation.
  • (2) A metering equipment provider may, if it receives a request from a person with whom it has an arrangement, other than a trader under subclause (1), to access raw meter data from a metering installation for which the metering equipment provider is responsible, give remote or onsite access at the services access interface to the person to collect, obtain, and use raw meter data from the metering installation.
  • (3) A metering equipment provider must only give access to a trader under subclause (1), or a person under subclause (2), if the trader or person has entered into a contract to collect, obtain, and use the raw meter data, with the consumer whose electricity is measured or estimated, or whose load is controlled at the metering installation.
  • (4) A metering equipment provider must, within 10 business days of receiving a request from 1 of the following parties, give the party access to raw meter data from a metering installation for which it is responsible:
    • (a) a relevant reconciliation participant with whom it has an arrangement, other than a trader:
    • (b) the Authority:
    • (c) an ATH:
    • (d) an auditor.
  • (5) A party listed in subclause (4) may only request access to raw meter data for the purposes of exercising the party’s rights and performing the party’s obligations under this Code or any relevant regulations in relation to 1 or more of the following:
    • (a) the party’s audit functions:
    • (b) the party’s administration functions:
    • (c) the party’s testing functions:
    • (d) the provision of submission information to the reconciliation manager.
  • (6) The metering equipment provider must provide a trader under subclause (1) or a party under subclause (4) with—
    • (a) the raw meter data; or
    • (b) any necessary facilities, codes, keys, or other means to enable the trader or party to access the raw meter data by the most practicable means.
  • (7) The metering equipment provider must, when complying with subclause (6), or when providing access to a person under subclause (2), use appropriate procedures to ensure that—
    • (a) the raw meter data is received only by—
      • (i) the trader, person, or party; or
      • (ii) a contractor to a trader, person, or party; and
    • (b) the security of the raw meter data and the metering installation is maintained; and
    • (c) access to raw meter data under subclauses (1) to (6) is limited to only the specific raw meter data
      • (i) authorised by a contract described in subclause (3), in the case of a trader under subclause (1) or a person under subclause (2); or
      • (ii) required for the purposes of exercising the party’s rights and performing the party’s obligations under this Code, any relevant regulations, or the Act in relation to the party’s audit, administration, and testing functions, in the case of a party referred to in subclause (4).
  • (8) Nothing in this Part affects proprietary interests in metering data.

Clause 1(5) and (7)(c)(ii): amended, on 5 October 2017, by clause 183 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

Clause 1(5) and (7)(c)(ii): amended, on 20 December 2021, by clause 29 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.

2

Restrictions on use of raw meter data

  • (1) A metering equipment provider must not give a trader under clause 1(1), a person under clause 1(2), or a party under clause 1(3), access to raw meter data from a metering installation for which it is responsible, if to do so would, or would reasonably be expected to,—
    • (a) breach any regulatory or legal requirement; or
    • (b) prejudice the maintenance and monitoring of this Code, including the prevention, investigation, and detection of Code breaches and the right to a fair hearing before the Authority or the Rulings Panel; or
    • (c) result in the metering equipment provider breaching an obligation of confidentiality; or
    • (d) interfere with the privacy of a natural person; or
    • (e) create an improper gain or improper advantage for any participant or person; or
    • (f) commercially disadvantage the metering equipment provider or any other participant or person, in a material manner; or
    • (g) prejudice the future supply of raw meter data that is required by a market operation service provider to perform an obligation under this Code.
  • (2) A metering equipment provider must not limit or restrict a person’s or party’s right to access information from a metering installation for which the metering equipment provider is responsible, if the right of access is provided for in this Part.

3

Metering equipment provider must provide access to metering installation

  • (1) A metering equipment provider must, within 10 business days of receiving a request from 1 of the following parties, arrange physical access to each metering component in a metering installation for which it is responsible:
    • (a) a relevant reconciliation participant with whom it has an arrangement, other than a trader:
    • (b) the Authority:
    • (c) an ATH:
    • (d) an auditor:
    • (e) a gaining metering equipment provider.
  • (2) A party listed in subclause (1) may only request physical access to a metering component in the metering installation for the purposes of exercising the party’s rights and performing the party’s obligations under this Code or any relevant regulations in relation to 1 or more of the following:
    • (a) the party’s audit functions:
    • (b) the party’s administration functions:
    • (c) the party’s testing functions:
    • (d) the provision of metering components.
  • (3) The metering equipment provider must arrange for a party under subclause (1) to be provided with any necessary facilities, codes, keys, or other means to enable the party to obtain physical access to all metering components in the metering installation by the most practicable means.
  • (4) In complying with subclause (3), the metering equipment provider must use appropriate procedures to ensure that—
    • (a) the security of the metering installation is maintained; and
    • (b) physical access to the metering installation under subclause (1) is limited to only the physical access required for the purposes of exercising the party’s rights and performing the party’s obligations under this Code or any relevant regulations in relation to the party’s audit, administration, and testing functions.
  • (5) If a party referred to in subclause (1) requires urgent physical access to a metering installation, it must advise the relevant metering equipment provider, giving all relevant particulars of the physical access required and the reason for the urgency, and the metering equipment provider must use its best endeavours to arrange physical access in accordance with the requested urgency.

Clause 3(2) and (4)(b): amended, on 5 October 2017, by clause 184 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

Clause 3(2) and (4)(b): amended, on 20 December 2021, by clause 30 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.

4

Metering equipment provider record keeping and documentation

  • (1) A metering equipment provider must—
    • (a) for each metering installation for which it is responsible, keep accurate and complete records as specified in Table 1 of Schedule 11.4; and
    • (b) for each metering installation for which it is responsible other than an interim certified metering installation, keep accurate and complete records of—
      • (i) the certification expiry date of each metering component in the metering installation; and
      • (ii) all equipment used in relation to the metering installation, including serial numbers and details of the equipment's manufacturer; and
      • (iii) the manufacturer’s, or if different the most recent, test certificate for each metering component in the metering installation; and
      • (iv) the metering installation category for the metering installation; and
      • (v) all certification reports and calibration reports showing dates tested, tests carried out, and test results for all metering components in the metering installation; and
      • (vi) the contractor who installed each metering component in the metering installation; and
      • (vii) the certification sticker, or equivalent details, for each metering component that is certified under Schedule 10.8 in the metering installation; and
      • (viii) seal identification information under clause 47 of Schedule 10.7 relating to the metering installation; and
      • (ix) any applicable compensation factors; and
      • (x) the owner of each metering component within the metering installation; and
      • (xi) any applications installed within each metering component within the metering installation; and
      • (xii) the signed inspection report under clause 44 of Schedule 10.7, confirming that the metering installation continues to comply with the requirements of this Part.
  • (2) A metering equipment provider must, within 10 business days of receiving a request from a participant for a signed inspection report prepared under clause 44 of Schedule 10.7, make a copy of the report available to the participant.
  • (3) A metering equipment provider must retain metering records relating to a metering component in a metering installation for which it is or was responsible, for at least 48 months after the metering component is removed from the metering installation, even if—
    • (a) the metering installation is subsequently decommissioned; or
    • (b) the metering equipment provider ceases to be responsible for the metering installation.
  • (4) A metering equipment provider must retain metering records relating to a metering installation for which it is or was responsible, unless—
    • (a) the metering installation is decommissioned; or
    • (b) the metering equipment provider ceases to be responsible for the metering installation; or
    • (c) the metering installation has been recertified in accordance with clause 11 of Schedule 10.7 or clause 13 of Schedule 10.7.
  • (5) If subclause (4)(a), 4(b) or 4(c) applies, the metering equipment provider must retain the metering records for at least 48 months after the event described in those subclauses.

Clause 4(3): substituted, on 1 February 2016, by clause 31 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2015.

Clause 4(3): replaced, on 1 March 2024, by clause 40(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2024.

Clause 4(4) and (5): inserted, on 1 March 2024, by clause 40(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2024.

4A

Transfer of metering records

  • (1) A metering equipment provider that intends to cease being a metering equipment provider (MEP A) must transfer its metering records to the metering equipment provider (MEP B) that is taking responsibility for every metering component or metering installation that MEP A is responsible for.
  • (2) If a metering equipment provider (MEP B in subclause (1)) receives metering records under subclause (1), it must retain those metering records in accordance with clause 4.

Clause 4A: inserted, on 1 March 2024, by clause 41 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2024.

4B

Metering equipment provider retention of ATH records

If a metering equipment provider receives an ATH record under clause 13(2) of Schedule 10.4 or clause 13A(2) of Schedule 10.4, the metering equipment provider must retain that record for at least 48 months after the date of expiry of the certification of the metering installation or metering component to which the record relates.

Clause 4B: inserted, on 1 March 2024, by clause 41 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2024.

5

Metering equipment provider to provide access to metering records

  • (1) A gaining metering equipment provider may request that a losing metering equipment provider provide it with access to metering records required for the gaining metering equipment provider to exercise its rights and perform its obligations under this Code or any relevant regulations in relation to its respective auditing, administration, and testing functions.
  • (2) The losing metering equipment provider must, within 10 business days of receiving a request under subclause (1), provide the gaining metering equipment provider with—
    • (a) the metering records; or
    • (b) any necessary facilities, codes, keys, or other means to enable the gaining metering equipment provider to obtain access to the metering records by the most practicable means.
  • (3) In complying with subclause (2), the losing metering equipment provider must use appropriate procedures to ensure that—
    • (a) the metering records are received only by the gaining metering equipment provider or its contractor; and
    • (b) the security of the metering records is maintained; and
    • (c) it only provides access to the specific metering records required for the purposes of the gaining metering equipment provider exercising its rights and performing its obligations under this Code or any relevant regulations in relation to its auditing, administration, and testing functions.

Clause 5(1) and (3)(c): amended, on 5 October 2017, by clause 185 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

Clause 5(1) and (3)(c): amended, on 20 December 2021, by clause 31 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.

6

Provision of metering records when ATH recertifying metering installation

  • (1) This clause applies if—
    • (a) a metering equipment provider contracts with an ATH to recertify a metering installation for which the metering equipment provider is responsible; and
    • (b) the ATH did not perform the previous certification of the metering installation.
  • (2) If this clause applies, the metering equipment provider must, no later than 10 business days after the effective date of the contract, provide the ATH with a copy of all relevant metering records.

7

Metering equipment provider must use participant identifier

  • (1) A metering equipment provider must—
    • (a) ensure that it has a unique participant identifier for its activities as metering equipment provider under this Code; and
    • (b) use its participant identifier, if required under this Code, to correctly identify its information.
  • (2) A metering equipment provider must apply to the Authority in the prescribed form for a participant identifier at least 5 business days before the metering equipment provider requires the participant identifier.
  • (3) The Authority may change a metering equipment provider’s participant identifier.
  • (4) If the Authority changes a metering equipment provider’s participant identifier
    • (a) it must advise the metering equipment provider of the date on which the change takes effect at least 3 months before the date; and
    • (b) the new participant identifier becomes effective from the date advised under paragraph (a).

8

Electronic interrogation of metering installation

  • (1) This clause applies when raw meter data can only be obtained from a metering equipment provider’s back office.
  • (2) A metering equipment provider must—
    • (a) ensure that the interrogation cycle for each metering installation that it electronically interrogates does not exceed the maximum interrogation cycle in the registry; and
    • (b) interrogate a metering installation for which it is responsible at least once in each maximum interrogation cycle in the registry; and
    • (c) when electronically interrogating a metering installation, ensure that the interrogation and processing system electronically monitors and corrects its internal clocks against a time source with a verifiable standard, at a frequency sufficient, and no longer than 1 week, to ensure the internal clock is accurate, when carrying out an interrogation, to within ±5 seconds of—
      • (i) New Zealand standard time; or
      • (ii) New Zealand daylight time.
  • (3) A metering equipment provider must, for each metering installation for which it is responsible, record in the processing system log, the time, the date, and the extent of any change in the internal clock setting in the metering installation.
  • (4) A metering equipment provider must ensure that a data storage device in a metering installation for which it is responsible for interrogating does not exceed the maximum time error set out in Table 1 of subclause (5).
  • (5) A metering equipment provider must, when interrogating a metering installation,—
    • (a) compare the time on the internal clock of the data storage device with the time on the interrogation and processing system clock; and
    • (b) calculate the time error for the data storage device; and
    • (c) if the time error calculated under paragraph (b) is equal to or less than the applicable time error set out in Table 1, correct the clock of the data storage device; and
    • (d) if the time error calculated under paragraph (b) is greater than the applicable time error set out in Table 1,—
      • (i) correct the clock of the data storage device; and
      • (ii) compare the time of the clock with the time of the interrogation and processing system clock; and
      • (iii) advise the affected reconciliation participant for the point of connection, within 5 business days of correcting the clock, of any affected raw meter data; and
      • (iv) comply with the requirements of clause 10.43; and
    • (e) download the event log; and
    • (f) check the event log for any evidence of an event that may affect the integrity or operation of the metering installation such as malfunctioning or tampering.

Table 1: Maximum permitted time errors

Metering installation 

category

Half-hour metering

installations

(seconds)

Non half-hour metering 

installations

(seconds)

1 ±30 ±60
2 ±10 ±60
3 ±10 NA
4 ±10 NA
5 ±5 NA

 

  • (5A) A metering equipment provider must, if it finds an event that may affect the integrity or operation of a metering installation,—
    • (a) investigate and remediate the event; and
    • (b) advise the relevant reconciliation participant that it is investigating and remediating the event; and
    • (c) advise the relevant reconciliation participant of any corrections to the raw meter data required; and
    • (d) advise the relevant reconciliation participant of any event that does not affect the integrity or operation of the metering installation but which may affect the accuracy of the raw meter data.
  • (6) The metering equipment provider must, when interrogating a metering installation, ensure that all raw meter data downloaded as part of the interrogation, and used for submitting information for the purposes of Part 15, is archived—
    • (a) for no less than 48 months after the interrogation date; and
    • (b) in a form that cannot be modified without an audit trail being created; and
    • (c) in a form that is secure and prevents access by any unauthorised person; and
    • (d) in a form that is accessible to authorised personnel.
  • (7) A metering equipment provider must, when interrogating a metering installation,—
    • (a) ensure that for all metering information, an interrogation log is generated by the interrogation software to record details of each interrogation; and
    • (b) review the event log either manually or by an automated software function which flags exceptions and—
      • (i) take appropriate action where problems are apparent; and
      • (ii) pass relevant event log entries to the reconciliation participant for the metering installation; and
    • (c) ensure that the interrogation log forms part of the interrogation audit trail and contains the following as a minimum:
      • (i) the date of interrogation; and
      • (ii) the time of commencement of interrogation; and
      • (iii) the operator of the interrogation system identification (where available); and
      • (iv) the unique identifier of the data storage device being interrogated; and
      • (v) any clock errors outside the range specified in Table 1 of subclause (5) and the extent of any change in the internal clock setting; and
      • (vi) the method of interrogation; and
      • (vii) the identifier of the reading device used for interrogation (if applicable).
  • (8) Subclause (9) applies when—
    • (a) a metering equipment provider interrogates a half-hour metering installation which is a category 1 metering installation or a category 2 metering installation; and
    • (b) the certifying ATH confirmed, as a part of the metering installation’s most recent certification, that the metering equipment provider’s back office processes include, for each interrogation cycle, a comparison of—
      • (i) the increment of the accumulating meter registers; and
      • (ii) the sum of the half-hour metering raw meter data for the same period.
  • (9) When this subclause applies, the metering equipment provider must ensure that each electronic interrogation of the metering installation that retrieves half hour raw meter data compares the sum of that data against the increment of the metering installation’s accumulating meter registers for the same period.
  • (10) A metering equipment provider must not, when interrogating a metering installation, apply the compensation factor recorded in the registry for that metering installation to any raw meter data downloaded as part of the interrogation.
  • (11) If an electronic interrogation of a metering installation by a metering equipment provider does not download all of the raw meter data as part of the interrogation, the metering equipment provider must—
    • (a) investigate the reasons for the failure, restore communications, and download all of the raw meter data as soon as possible but no later than the time specified in subclause (12); or
    • (b) in accordance with clause 3(c) of Schedule 11.4, update the registry metering records to show that the metering component is no longer an advanced metering infrastructure device.
  • (12) If a metering equipment provider decides to take the actions specified in subclause (11)(a), the metering equipment provider must complete those actions by the earlier of—
    • (a) the number of full days that equate to no more than 25% of the maximum interrogation cycle for the metering installation from the date of the last successful interrogation; and
    • (b) 30 days from the date of the last successful interrogation.
  • (13) If the metering equipment provider does not complete investigating, restoring communications, and downloading all of the raw meter data in accordance with subclause (11)(a) within the time specified in subclause (12) or determines at any time during the time period specified in subclause (12) that it will not be able to complete those tasks within that time frame, the metering equipment provider must update the registry metering records in accordance with clause 3(d) of Schedule 11.4 to show that the metering component is no longer an advanced metering infrastructure device.

Clause 8(3): amended, on 1 February 2021, by clause 23(1) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 8(5)(f): replaced, on 1 February 2021, by clause 23(2) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 8(5A): inserted, on 1 February 2021, by clause 23(3) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 8(6)(b): amended, on 1 November 2018, by clause 30(a) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.

Clause 8(7)(c): amended, on 1 November 2018, by clause 30(b) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.

Clause 8(7)(c)(v): amended, on 1 February 2021, by clause 23(4) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 8(8)(b): replaced, on 1 February 2021, by clause 23(5) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 8(9): amended, on 1 February 2021, by clause 23(6) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 8(10), (11), (12) and (13): inserted, on 1 February 2021, by clause 23(7) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

9

Contracting with ATH

A metering equipment provider must, when contracting with an ATH in relation to the required activities for the certification of a metering installation for which it is responsible, ensure that an ATH contracted to perform work under this Part has the appropriate scope of approval for such work.

Schedule 10.7

cls 10.11, 10.20, 10.26, 10.38 and 10.42

Metering installation requirements

Metering installation general requirements

1

Maintenance and repair of metering installations

  • (1) A metering equipment provider must comply with subclause (2)—
    • (a) for each metering installation for which it is responsible; and
    • (b) for each metering component in a metering installation for which it is responsible.
  • (2) A metering equipment provider must ensure that—
    • (a) it carries out regular maintenance, including battery monitoring and replacement, in accordance with the applicable requirements in the metering records; and
    • (b) it carries out all necessary repairs; and
    • (c) if it is not possible to repair a metering installation or metering component so that it complies with the applicable requirements in this Part, it is—
      • (i) replaced with a metering installation or metering component that complies with the applicable requirements in this Part; or
      • (ii) in the case of a metering installation, decommissioned; and
    • (d) it documents in the metering records all maintenance, repairs, or replacements it carries out at the time it carries out the maintenance, repairs, or replacement.

Metering installation design reports

2

Design reports for metering installations

  • (1) A metering equipment provider must obtain a design report under this clause for—
    • (a) a proposed new metering installation for which it will be responsible, before it installs the metering installation; and
    • (b) a modification to an existing metering installation for which it is responsible before the modification commences.
  • (2) The metering equipment provider must ensure that a design report is prepared by a person with an appropriate level of skill, expertise, experience, and qualification.
  • (3) The metering equipment provider must ensure that a design report includes—
    • (a) a schematic drawing of the metering installation for use by an ATH; and
    • (b) details of the configuration scheme that programmable metering components are to include; and
    • (c) confirmation that the configuration scheme has been approved by an approved test laboratory; and
    • (d) for each services access interface, the maximum interrogation cycle specified in clause 36(4); and
    • (e) any compensation factor arrangements; and
    • (f) the method of certification required under this Part to be used for the metering installation; and
    • (g) the name and signature of the person who prepared the design report and the date on which it was signed.
  • (4) The metering equipment provider must provide the design report to the certifying ATH before the ATH installs or modifies—
    • (a) the metering installation; or
    • (b) a metering component in the metering installation.

Clause (2)(3)(d): amended, on 1 February 2021, by clause 24 of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

3

ATH design report obligations

  • (1) A certifying ATH must, before it certifies a new or modified metering installation, check and approve, in writing, the design report provided under clause 2 (including the configuration scheme and the schematic drawing), to ensure that the proposed new or modified metering installation
    • (a) will function correctly; and
    • (b) will provide the required accuracy and raw meter data; and
    • (c) complies with this Part.
  • (2) The certifying ATH must, within 10 business days of the date on which it certifies the metering installation
    • (a) update the design report with any changes to the metering installation design; and
    • (b) provide a copy of the updated design report to the metering equipment provider responsible for the metering installation.

4

Metering equipment provider obligations

  • (1) A metering equipment provider must, for each metering installation for which it is responsible,—
    • (a) ensure that the sum of the measured error and uncertainty does not exceed the maximum permitted error set out in Table 1 of Schedule 10.1 for the category of the metering installation; and
    • (b) ensure that the design of the metering installation, including its data storage device and interrogation system, will ensure that the sum of the measured error and the smallest possible increment of the energy value of the raw meter data obtained from the metering installation does not exceed the maximum permitted error set out in Table 1 of Schedule 10.1 for the category of the metering installation; and
    • (c) comply with the requirements applying to the metering equipment provider in the design report provided under clause 2; and
    • (d) ensure that the metering installation complies with—
      • (i) the design report provided under clause 2; and
      • (ii) this Part.
  • (2) A metering equipment provider must ensure that, for each metering installation for which it is responsible for an ICP that is not also an NSP,—
    • (a) the metering installation configuration does not use subtraction to determine submission information used for the purposes of Part 15; and
    • (b) which is a category 3 or higher metering installation, is a half-hour metering installation.
  • (3) A metering equipment provider must ensure that, for each metering installation for which it is responsible for an NSP that is not a point of connection to the grid,—
    • (a) the metering installation configuration does not use subtraction to determine submission information used for the purposes of Part 15; and
    • (b) it is a half-hour metering installation.
  • (4) A metering equipment provider must, for each metering installation for which it is responsible, ensure that it is appropriate having regard to the physical and electrical characteristics of the point of connection.

Determination of metering installation categories

5

Determination of metering installation category

An ATH must, before it certifies a metering installation, determine the category of the metering installation in accordance with the following:

  • (a) subject to clause 6, if the metering installation incorporates a current transformer, its category must be determined according to the primary current rating of the current transformer and the connected voltage set out in Table 1 of Schedule 10.1:
  • (b) if the metering installation does not incorporate a current transformer and the quantity of electricity conveyed is measured by a meter, it must be category 1.

Clause 5(a): amended, on 23 February 2015, by clause 75 of the Electricity Industry Participation Code Amendment (Distributed Generation) 2014.

Clause 5(a): amended, on 5 October 2017, by clause 186 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

6

Determining metering installation incorporating current transformer to be lower category

  • (1) When determining the category of a metering installation under clause 5(a), an ATH may under subclause (2) determine the category of a metering installation to be lower than would otherwise be the case under clause 5(a) only in 1 of the following circumstances:
    • (a) if a protection device, including a fuse or a circuit breaker, is installed that limits the maximum current of the metering installation:
    • (b) if the metering equipment provider, acting reasonably on the basis of historical metering data, believes that the maximum current to be conveyed through the point of connection will, at all times during the intended certification period, be lower than the current setting of the protection device for the category for which the metering installation
      • (i) is certified; or
      • (ii) is required to be certified by this Code:
    • (c) if the metering installation uses less than 0.5 GWh in any 12 month period:
    • (d) if the metering equipment provider, acting reasonably on the basis of historical metering data, believes that the metering installation (including, for example, a metering installation for an emergency fire pump or flood pump) will use less than 0.5 GWh in any 12 month period.
  • (2) An ATH may determine the category of a metering installation to be lower than would otherwise be the case under clause 5(a) of this Schedule, provided that,—
    • (a) if the circumstance in subclause (1)(a) applies, when certifying the metering installation, determine the category of the metering installation by reference to the maximum current setting of the protection device and, when doing so, the ATH must—
      • (i) confirm the suitability and operational condition of the protection device; and
      • (ii) record, in the metering records, the rating and setting of the protection device; and
      • (iii) seal the protection device under clause 47; and
      • (iv) apply, if practicable, a warning tag to the seal under clause 47(6):
    • (b) if the circumstance in subclause (1)(b) applies, the ATH must, when certifying the metering installation, determine the metering installation category according to the metering installation’s expected maximum current but only—
      • (i) at the request of the metering equipment provider; and
      • (ii) if the ATH considers it appropriate in the circumstances:
    • (c) if the circumstance in subclause (1)(c) or subclause (1)(d) applies and the primary voltage is less than 1 kV, when certifying the metering installation, the ATH must determine the metering installation as category 2:
    • (d) if the circumstance in subclause (1)(c) or subclause (1)(d) applies and the primary voltage is greater than or equal to 1 kV, when certifying the metering installation, the ATH must determine the metering installation as category 3.
  • (2A) If when certifying a metering installation an ATH determines the category of a metering installation under—
    • (a) subclause (2)(b), then the metering equipment provider responsible for the metering installation must, each month, obtain a report from the participant interrogating the metering installation which details the maximum current conveyed through the metering installation for the prior month:
    • (b) subclause (2)(c), then the metering equipment provider responsible for the metering installation must, each month during the certification period, obtain a report from the participant interrogating the metering installation which details the total kWh consumption of the metering installation for the prior 12 months.
  • (2B) For the purposes of subclause (2A)(a), the metering equipment provider must determine the maximum current from raw meter data from the metering installation either:
    • (a) by calculation from the kVA by trading period if available; or
    • (b) from a maximum current indicator if fitted in the metering installation.
  • (2C) If a metering equipment provider does not receive the report under subclause (2A)(a) in any month, or the report demonstrates that the maximum current conveyed through the point of connection at any time during the previous month exceeded the maximum permitted current for the metering installation category as certified, certification for the metering installation to which the report relates is automatically cancelled from––
    • (a) the date on which the metering equipment provider should have received the report; or
    • (b) the date on which the metering equipment provider received the report if earlier.
  • (2D) If a metering equipment provider does not receive the report under subclause (2A)(b) in any month, or the report identifies that the electricity conveyed through the point of connection exceeded 0.5 GWh during the previous 12 month period, the certification for the metering installation to which the report relates is automatically cancelled from––
    • (a) the date on which the metering equipment provider should have received the report; or
    • (b) the date on which the metering equipment provider received the report if earlier.
  • (3) The ATH must, before it determines a metering installation to be a lower category under this clause, visit the site of the metering installation to ensure that the installation is suitable for the metering installation to be determined to be a lower category.
  • (4) If an ATH determines a metering installation to be a lower category under this clause the metering installation certification report must include all information required to demonstrate, as at the certification date, compliance with this clause.

Clause 6 Heading: amended, on 1 February 2021, by clause 25(1) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 6(1)(b): amended, on 29 August 2013, by clause 30(1) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 6(2)(b)(i): amended, on 29 August 2013, by clause 30(2) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 6(2)(c): amended, on 29 August 2013, by clause 30(3) and (4) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 6(2)(c)(iii): amended, on 29 August 2013, by clause 30(5) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 6(1) and (2): replaced, on 1 February 2021, by clause 25(2) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 6(2A), (2B), (2C) and (2D): inserted, on 1 February 2021, by clause 25(2) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Certification of metering installation

7

Method of certification

  • (1) An ATH must, when certifying a metering installation, only use—
    • (a) the selected component certification method under clause 11, if the metering installation is a category 1 metering installation, a category 2 metering installation or a category 3 metering installation; or
    • (b) the fully calibrated certification method under clause 13.
  • (2) Despite subclause (1), an ATH may recertify
    • (a) a category 1 metering installation using statistical sampling under clause 16; or
    • (b) a category 2 metering installation using the approved comparative recertification method under clause 12.
  • (3) If an ATH uses statistical sampling under subclause (2)(a), it must use the applicable method described in subclause (1)(a) and (1)(b) to certify each metering installation in the sample.

8

Metering installation certification requirements

  • (1) An ATH must not certify a metering installation unless the metering installation complies with this Part.
  • (2) An ATH must, when certifying a metering installation,—
    • (a) prepare a certification report for the metering installation; and
    • (b) specify in the certification report whether the metering installation is —
      • (i) half hour; or
      • (ii) non half hour; or
      • (iii) half hour and non half hour; and
    • (c) determine the services access interfaces for the metering installation under clause 10 of Schedule 10.4 and record in the metering installation certification report
      • (i) each services access interface; and
      • (ii) the conditions under which each services access interface may be used; and
    • (d) ensure that each metering component in the metering installation functions correctly.
  • (3) An ATH may only certify a metering installation as category 3 or higher if the metering installation incorporates a half hour meter or half hour data storage device to quantify the electricity conveyed.
  • (4) An ATH must, when preparing a metering installation certification report, record the category of the metering installation.

Clause 8(2)(b)(ii) and (iii): amended, on 1 February 2021, by clause 26(a) and (b) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 8(2)(b)(iii): inserted, on 1 February 2021, by clause 26(c) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 8(2)(c): replaced, on 1 February 2021, by clause 26(d) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 8(3): amended, on 29 August 2013, by clause 31 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

8A

ATH amends certification reports

  • (1) Subject to subclause (2), an ATH may amend a certification report for a metering installation prepared under this Schedule, or a certification report for a metering component prepared under Schedule 10.8, if—
    • (a) the ATH prepared the certification report; and
    • (b) the ATH
      • (i) receives, or becomes aware of, new information relevant to the certification; or
      • (ii) becomes aware of a change to the metering installation or metering component, other than a change that affects the accuracy of the metering installation or metering component; and
    • (c) the new information or change would have caused the ATH to reach a different conclusion in its certification report.
  • (2) An amendment under subclause (1) must not—
    • (a) change the category of the metering installation:
    • (b) extend the expiry date in the certification report:
    • (c) change a calibration report in the certification report.
  • (3) If an ATH amends a certification report under subclause (1)—
    • (a) the ATH must advise the relevant metering equipment provider of the changes to the certification report; and
    • (b) the metering equipment provider must, upon being advised under paragraph (a), update the registry in accordance with Part 11.
  • (4) Despite anything else in this Part, if an ATH amends a certification report under this clause, the certification of the metering installation or metering component remains valid to the extent of the amendment.

Clause 8A: inserted, on 12 January 2018, by clause 4 of the Electricity Industry Participation Code Amendment (Amendments to Certification Reports) 2017 and expired on 12 October 2018.

Clause 8A: inserted, on 13 October 2018, by clause 4 of the Electricity Industry Participation Code Amendment (Amendments to Certification Reports) 2018.

9

Certification tests

  • (1) An ATH, when carrying out a test set out in Table 3 or Table 4 of Schedule 10.1,—
    • (a) to carry out a prevailing load test on a metering installation or metering component, must do so by using a working standard connected to the metering installation:
    • (b) to carry out an installation or component configuration test on a metering installation or metering component, must ensure that the actual configuration scheme is the same as the scheme for the metering installation or metering component recorded in the design report:
    • (c) to carry out a raw meter data output test for a category 1 metering installation or category 2 metering installation, must do so by—
      • (i) applying a load on each phase that is—
        • (A) greater than 5% of the meter's maximum rated current for a category 1 metering installation; or
        • (B) 10 amps on each phase for a category 2 metering installation; and
      • (ii) using either the working standard referred to in subclause (1)(a) or an ammeter in good working order with an accuracy range of +/- 5% to measure the load applied to the metering installation and—
        • (A) recording the resulting increment of the meter register value over a measured period of time; or
        • (B) recording the resulting accumulation of pulses from the load over a measured period of time; and
      • (iii) ensuring that the change in the meter register that occurs under subclause (ii)(A) or subclause (ii)(B) is at least "1" in the least significant digit, or one mark if the least significant digit does not have numerical markings; and
      • (iv) if the meter is a Ferraris disc meter, undertaking two raw meter data output tests in which the second test must have a load applied to the meter that is at least double the load applied to the meter in the test carried out in accordance with subparagraph (c)(i) and measuring:
        • (A) the increment of the sum of the meter registers; or
        • (B) the accumulation of pulses resulting from the increase in load:
    • (d) to carry out a raw meter data output test for a half-hour metering installation which is a category 1 metering installation or for a half-hour metering installation which is a category 2 metering installation, must either—
      • (i) compare the output from a working standard to the raw meter data from the metering installation for a minimum of 1 trading period; or
      • (ii) if the raw meter data is to be used for the purposes of Part 15, confirm that the metering equipment provider’s back office processes include a comparison of:
        • (A) the increment of the accumulating meter registers; and
        • (B) the sum of the half-hour metering raw meter data for the same period:
    • (e) to carry out a raw meter data output test for a category 3 or higher half-hour metering installation, must compare the output of a working standard to the raw meter data from the metering installation for a minimum of 1 trading period:
    • (f) to carry out a raw meter data output test for a non half-hour metering installation which is a category 2 metering installation, must do so by comparing the output of a working standard to the increment of the sum of the meter registers.
  • (1A) If an ATH performs a raw meter data output test under subclause (1)(c) or subclause (1)(d), for a metering installation that will be certified for remote meter reading, the ATH must—
    • (a) obtain the raw meter data from the back office system where the raw meter data is held; or
    • (b) ensure that the metering equipment provider responsible for the metering installation has a process to validate a meter reading taken at the time of the metering installation certification with a meter reading from the metering equipment provider's back office system.
  • (2) If an ATH performs a test under subclause (1) that requires a comparison between 2 quantities, the ATH must not certify the metering installation unless the metering installation passes the test.
  • (3) For the purposes of subclause (2), a metering installation passes if the test demonstrates that the difference between the 2 quantities is within the applicable accuracy tolerances set out in Table 1 of Schedule 10.1.

Clause 9(1): amended, on 1 February 2021, by clause 27(a) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 9(1): amended, on 29 August 2013, by clause 32(1) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 9(1)(c): replaced, on 1 February 2021, by clause 27(b) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 9(1)(c)(i) and (ii): inserted, on 29 August 2013, by clause 32(2) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 9(1)(d)(ii): replaced, on 1 February 2021, by clause 27(c) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 9(1A): inserted, on 29 August 2013, by clause 32(3) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

10

Test results

  • (1) An ATH must, before it certifies a metering installation or any of a metering installation’s metering components, review the relevant test results for each of the metering installation’s metering components to ensure that—
    • (a) the metering component passed all the tests; and
    • (b) the metering installation meets the requirements for certification.
  • (2) If the ATH considers that the test results show that the requirements in this Part for certification of the metering installation are not met, it must—
    • (a) within 5 business days of reviewing the tests, advise the relevant metering equipment provider providing detailed reasons; and
    • (b) not certify the metering installation.

11

Selected component certification of metering installation

  • (1) This clause applies only when an ATH uses the selected component certification method.
  • (2) An ATH may use the selected component certification method to certify a metering installation only for the categories of metering installation for which the stated requirements are set out in Table 1 of Schedule 10.1.
  • (3) An ATH must only use the selected component certification method to certify a metering installation
    • (a) by carrying out the tests set out in Table 3 of Schedule 10.1; and
    • (b) if an ATH or an approved test laboratory or an approved calibration laboratory has calibrated each of the following metering components in the metering installation in accordance with clause 1(1)(a)(ii) or 1(1)(b) of Schedule 10.8:
      • (i) meter:
      • (ii) measuring transformer; and
    • (c) if each data storage device in the metering installation has been certified in accordance with clause 5 of Schedule 10.8.
  • (4) An ATH must, before it uses the selected component certification method,—
    • (a) check the design report of the metering installation to—
      • (i) confirm the metering installation functions in accordance with the design report; and
      • (ii) ensure the metering installation complies with this Part; and
    • (b) ensure that each metering component in the metering installation is used only in a permitted combination as set out in Table 1 of Schedule 10.1; and
    • (c) check and confirm that the metering installation is correctly wired in accordance with all applicable requirements and enactments; and
    • (d) ensure that each metering component in the metering installation is fit for purpose.
  • (5) An ATH must, when it certifies a metering installation under this clause, ensure that the metering installation certification report includes confirmation that the ATH has—
    • (a) checked the design report of the metering installation to—
      • (i) confirm the metering installation functions in accordance with the design report; and
      • (ii) ensure the metering installation complies with this Part; and
    • (b) ensured that each metering component in the metering installation has been calibrated and certified as required in this Part; and
    • (c) ensured that the metering installation has passed the relevant tests and checks set out in Table 3 of Schedule 10.1; and
    • (d) checked and confirmed that the metering installation is correctly wired in accordance with all applicable requirements and enactments; and
    • (e) carried out any tests and checks required to confirm the integrity of the metering installation and recorded these and their results in the metering installation certification report.
  • (6) An ATH must, when it certifies a metering installation under this clause, include in the metering installation certification report
    • (a) any compensation factors that must be applied; and
    • (b) how the compensation factors must be applied under clause 2 of Schedule 15.3.

Clause 11(3)(b): substituted, on 29 August 2013, by clause 33(1) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 11(3)(b): amended, on 15 May 2014, by clause 18 of the Electricity Industry Participation (Minor Code Amendments) Code Amendment 2014.

Clause 11(3)(c): inserted, on 29 August 2013, by clause 33(1) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 11(5)(e): amended, on 29 August 2013, by clause 33(2) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

12

Comparative recertification

  • (1) This clause only applies when an ATH uses the comparative recertification method.
  • (1A) The comparative recertification method may only be used to recertify a category 2 metering installation.
  • (2) An ATH may only use the comparative recertification method to recertify a category 2 metering installation in accordance with this Part if—
    • (a) the certification of the current transformers in the metering installation expires before the meter certification expiry date; and
    • (b) each of the following metering components in the metering installation is certified at the date of recertification in accordance with Schedule 10.8:
      • (i) data storage device:
      • (ii) meter.
  • (2A) For the avoidance of doubt, an ATH may use the comparative recertification method to recertify a category 2 metering installation in accordance with this Part if the certification of the current transformers in the metering installation has expired.
  • (3) An ATH must, when recertifying a category 2 metering installation under this clause, ensure that—
    • (a) the metering installation has passed the tests set out in Table 3 of Schedule 10.1, using a working standard connected to the metering installation; and
    • (b) the current measurement sensor connected around the cables or bus-bars adjacent to the metering installation is sufficiently accurate so that the sum of the measured metering installation accuracy, the uncertainty of the metering installation, and the uncertainty of the current measurement sensor does not exceed the maximum permitted error set out in Table 1 of Schedule 10.1 for the category of the metering installation; and
    • (c) the overall metering installation accuracy meets the requirements of Table 1 of Schedule 10.1.
  • (4) An ATH must, before it uses the comparative recertification method—
    • (a) check the design report of the metering installation to—
      • (i) confirm the metering installation functions in accordance with the design report; and
      • (ii) ensure the metering installation complies with this Part; and
    • (b) check and confirm that the metering installation is correctly wired in accordance with all applicable requirements and enactments; and
    • (c) carry out any tests and checks required to confirm the integrity of the metering installation and record these and their results in the metering installation certification report.
  • (5) An ATH must, for each metering installation it certifies under this clause,—
    • (a) prepare a certification report; and
    • (b) ensure that each metering component in the metering installation is fit for purpose.

Clause 12(1A): inserted, on 1 February 2021, by clause 28(a) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 12(2)(b): amended, on 1 February 2021, by clause 28(b) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 12(2A): inserted, on 1 February 2021, by clause 28(c) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

13

Fully calibrated metering installation certification

  • (1) This clause only applies when an ATH uses the fully calibrated certification method.
  • (2) An ATH may only use the fully calibrated certification method to certify a category 1 metering installation, or higher category of metering installation.
  • (3) An ATH must use the fully calibrated certification method to certify a metering installation
    • (a) by carrying out the tests set out in Table 4 of Schedule 10.1; and
    • (b) only if each of the following metering components in the metering installation has been certified in accordance with Schedule 10.8:
      • (i) data storage device:
      • (ii) meter:
      • (iii) measuring transformer.
  • (4) An ATH must ensure that each metering component in a metering installation which is certified under this clause has a current certification report that—
    • (a) complies with the requirements of this Part; and
    • (b) if the metering component is a calibrated metering component, includes a calibration report that—
      • (i) confirms that the metering component complies with the requirements of its accuracy class set out in Table 1 of Schedule 10.1; and
      • (ii) includes the certification date of the metering component.
  • (5) An ATH must, when preparing a metering installation certification report under this clause, include confirmation that the ATH has—
    • (a) checked the design report of the metering installation to—
      • (i) confirm the metering installation functions in accordance with the design report; and
      • (ii) ensure the metering installation complies with this Part; and
    • (b) ensured that each metering component in the metering installation has been calibrated and certified as required in this Part; and
    • (c) ensured that the relevant tests and checks set out in Table 4 of Schedule 10.1 have been passed; and
    • (d) checked and confirmed that the metering installation is correctly wired in accordance with all applicable requirements and enactments; and
    • (e) carried out any tests and checks required to confirm the integrity of the metering installation.
  • (6) An ATH must, when it certifies a metering installation under this clause, include in the metering installation certification report
    • (a) any compensation factors that must be applied; and
    • (b) how the compensation factors must be applied under clause 2 of Schedule 15.3.
  • (7) An ATH must, before it certifies a metering installation under this clause, ensure that the ATH uses the manufacturer’s meter class accuracy, and not the meter’s actual tested accuracy, to determine whether the metering installation is within the relevant maximum permitted error set out in Table 1 of Schedule 10.1.

14

Insufficient load for metering installation certification tests

  • (1) This clause only applies if there is insufficient electricity conveyed through a point of connection to allow an ATH to complete a prevailing load test for a metering installation that is being certified as a half-hour metering installation.
  • (2) When this clause applies, the ATH must, when certifying the metering installation, ensure that—
    • (a) it performs an additional integrity check of the metering installation wiring, and records the results of this check in the certification report; and
    • (b) it records in the certification report that the metering installation is certified under this clause.
  • (3) A metering equipment provider must, for each metering installation for which it is responsible, and that is certified under this clause, obtain and monitor raw meter data from the metering installation at least once each month during the period of certification to determine if load during the month is sufficient for a prevailing load test to be completed.
  • (4) Despite subclause (1), the metering equipment provider must, if raw meter data obtained under subclause (3) demonstrates, at any time, that there is sufficient electricity conveyed through the point of connection for a prevailing load test to be completed, ensure that the certifying ATH makes a subsequent visit to the metering installation as soon as practicable, but no later than 20 business days after the metering equipment provider has obtained the raw meter data, to carry out and complete the tests set out in Table 4 of Schedule 10.1.
  • (5) The certifying ATH must, if the tests referred to in subclause (4) demonstrate that the metering installation performs within the relevant maximum permitted error set out in Table 1 of Schedule 10.1,—
    • (a) update the metering installation certification report, within 5 business days of completing the tests, to include the results of the tests carried out; and
    • (b) leave the original metering installation certification expiry date unchanged.
  • (6) If the tests referred to in subclause (4) demonstrate that the metering installation does not perform within the relevant maximum permitted error set out in Table 1 of Schedule 10.1—
    • (a) the metering installation certification is automatically cancelled from the date of the tests; and
    • (b) the certifying ATH must advise the metering equipment provider of the cancellation within 1 business day of carrying out the tests; and
    • (c) the metering equipment provider must follow the procedure set out in clauses 10.43 to 10.48.

Clause 14(1): amended, on 29 August 2013, by clause 34 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 14(3): amended, on 5 October 2017, by clause 187 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

15

Recertification programme

  • (1) A metering equipment provider must have a recertification programme for all metering installations for which it is responsible to ensure that each metering installation is recertified prior to the expiry date of its then current certification if the metering installation is not decommissioned.
  • (2) Subclause (1) does not apply to an electrically disconnected metering installation for an ICP.

Clause 15(2): amended, on 5 October 2017, by clause 188 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

Statistical sampling recertification

16

Recertification of group of category 1 metering installations by statistical sampling

  • (1) A metering equipment provider may arrange for an ATH to recertify a group of category 1 metering installations for which the metering equipment provider is responsible using a statistical sampling process set out in subclause (2).
  • (2) To recertify a group of category 1 metering installations, an ATH must—
    • (a) select a sample from the group, using a statistical sampling process—
      • (i) prescribed in AS/NZS 1284.13:2002; or
      • (ii) that is approved and published by the Authority; and
    • (aa) use the pass/fail criteria in AS/NZS 1284.13:2002 to evaluate whether the group meets the recertification requirements of this Part; and
    • (ab) if the group meets the recertification requirements of this Part use the appropriate maximum validity period set out in Table 5 of AS/NZS 1284.13:2002 as the certification validity period for each metering installation in the group, except that if a class 1 static (electronic) meter sample is within the accuracy tolerance of ± 1.5%, the appropriate maximum validity period for that group is 7 years; and
    • (b) subject to subclause (2A), recertify each metering component in the metering installation in the sample using—
      • (i) the fully calibrated certification method; or
      • (ii) the selected component certification method; and
    • (c) advise the metering equipment provider as soon as reasonably practicable, if the group—
      • (i) meets the recertification requirements of this Part; or
      • (ii) fails to meet the recertification requirements of this Part.
  • (2A) Where a metering component in a metering installation in the sample referred to in subclause (2)(b) has been, or will be, displaced, an ATH (the “first ATH”) may arrange for the displacing ATH to:
    • (a) recertify the metering component in the metering installation using—
      • (i) the fully calibrated certification method; or
      • (ii) the selected component certification method;
    • (b) record sufficient details about the metering installation to allow the first ATH to assess the metering installation as part of the sample and provide those details to the first ATH; and
    • (c) deliver the removed metering component to the first ATH without damage.
  • (3) An ATH must, when selecting a sample from the group under subclause (2)(a),—
    • (a) document the process it follows and any assumptions it makes; and
    • (b) keep records in accordance with clause 13 of Schedule 10.4, of—
      • (i) each step in the process; and
      • (ii) each metering installation in the sample; and
      • (iii) each metering installation in the group that is recertified using this process.
  • (4) The recertification of a metering installation in the group—
    • (a) commences from the date of the advice referred to in subclause (2)(c)(i) if the sample meets the recertification requirements of this Part:
    • (b) is automatically cancelled from the date of the advice referred to in subclause (2)(c)(ii) if the sample fails to meet the recertification requirements of this Part.
  • (5) The metering equipment provider must, upon being advised under subclause (2)(c), update the registry in accordance with Part 11.
  • (6) Despite clause 41(1), an ATH who recertifies a group of metering installations using a statistical sampling process is not required to apply a certification sticker to a metering installation in the group that was not part of the sample.

Clause 16(2)(a)(i): amended, on 29 August 2013, by clause 35(1) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 16(2)(aa): inserted, on 29 August 2013, by clause 35(3) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 16(2)(ab): inserted, on 1 February 2021, by clause 29 of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 16(2)(b): substituted, on 29 August 2013, by clause 35(4) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 16(2)(b): amended, on 1 April 2025, by clause 8(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2025.

Clause 16(2)(c): amended, on 29 August 2013, by clause 35(5) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 16(2)(a)(i), (aa) and (ab): amended, on 1 March 2024, by clause 42(1) and (2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2024.

Clause 16(2A): inserted, on 1 April 2025, by clause 8(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2025.

Certification validity periods

17

Determination of expiry dates for certification of metering components and metering installations

  • (1) An ATH must, when certifying a metering installation,—
    • (a) determine, in accordance with this clause, the date on which the metering installation’s certification will expire; and
    • (b) record the expiry date in the metering installation certification report.
  • (2) The expiry date for a metering installation’s certification is the earliest of—
    • (a) the date falling after the date of its commissioning by the number of months equivalent to the maximum metering installation certification validity period for the relevant category of metering installation, as set out in Table 1 of Schedule 10.1; and
    • (b) the earliest certification expiry date of a metering component in the metering installation; and
    • (c) a date determined by the ATH taking into account—
      • (i) the condition of each metering component in the metering installation; and
      • (ii) all relevant circumstances relating to the metering installation.
  • (3) Despite subclause (2), the expiry date for each metering installation in a group of metering installations recertified under clause 16, that does not form a part of the sample, is the earliest expiry date of the metering installations in the sample.

18

Interim certified metering installations

  • A metering equipment provider must ensure that each interim certified metering installation on 28 August 2013 is certified under this Part by no later than 1 April 2015.

Clause 18: amended, on 29 August 2013, by clause 36 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

19

Modification of metering installations

  • (1) If a metering installation is modified, the certification of the metering installation is automatically cancelled with effect from—
    • (a) the date the modification began; or
    • (b) if the metering equipment provider responsible for the metering installation does not know the date in subclause (a), the date on which the metering equipment provider became aware of, or would reasonably have been expected to have become aware of, the modification.
  • (2) For the purposes of this Part, a modification of a metering installation includes, any 1 or more of the following:
    • (a) any change to the software, ROM, or firmware in the metering installation that may affect the operation of the metrology layer unless the change is made under subclause (3):
    • (b) replacement, installation, removal, repair, or modification, of a metering component in the metering installation, other than the temporary connection of testing or monitoring equipment by using a test facility:
    • (ba) replacing a metering installation with a new metering installation:
    • (c) any change to the burdening of a measuring transformer in the metering installation, unless changed under clause 31(6):
    • (d) reconfiguration of any wiring (but not straight replacement of wiring in a category 1 metering installation):
    • (e) relocation of a metering component in the metering installation or the metering installation enclosure:
    • (f) any interference with the metering installation that affects the accuracy of the metering installation.
  • (2A) For the purposes of subclause (1), and despite subclause (2), a modification of a metering installation does not include the replacement of a modem in the metering installation by the ATH that is responsible for certifying the metering installation.
  • (2B) To avoid doubt, replacing a metering component or a metering installation is a modification of a metering installation under subclause (2) including when––
    • (a) the replacement metering component or metering installation has the same or similar design and functionality as the existing metering component or metering installation; or
    • (b) the metering equipment provider did not need to consult with a distributor or trader because clause 10.34(2C) applied.
  • (3) Despite subclauses (1) and (2)(a), the certification of a metering installation is not cancelled if—
    • (a) an approved test laboratory has tested and confirmed under clause 39 that the integrity of the measurement and logging of a data storage device in the metering installation would be unaffected by the change; and
    • (b) the change does not, or would not be considered by the ATH who most recently certified the metering installation to, affect—
      • (i) the accuracy of the raw meter data obtained from the metering installation; or
      • (ii) the accuracy of the metrology layer of the metering installation; or
      • (iii) a compensation factor programmed into any metering component in the metering installation; and
    • (c) the ATH who most recently certified the metering installation approves, in advance, the process of changing the software, ROM, or firmware in the metering installation; and
    • (d) the change is carried out in accordance with a documented methodology that has been audited under this Part; and
    • (e) the metering equipment provider responsible for the metering installation records in the metering records the details of the change, including the time and date; and
    • (f) any change of the metering installation’s parameters does not affect the metrology layer; and
    • (g) [Revoked]
    • (h) clause 8A(1) applies.
  • (3A) Despite subclauses (1) and (2)(b), the certification of a metering installation is not cancelled if—
    • (aa) a control device that does not switch meter registers has malfunctioned and been replaced with a certified control device; and
    • (a) the replacement control device has the same characteristics as the control device it replaces and—
      • (i) is certified in accordance with this Part; and
      • (ii) will not adversely affect the operation of any other metering components or connections to those metering components; and
      • (iii) is likely to receive control signals, as required by clause 34; and
      • (iv) is correctly connected and programmed; and
    • (b) the metering equipment provider responsible for the metering installation has in place—
      • (i) an appropriate agreement with the approved test house that is responsible for the certification of the metering installation, to record the replacement in its metering installation certification records; and
      • (ii) appropriate procedures for ensuring that replacements are carried out only by persons authorised by the metering equipment provider; and
    • (c) the metering equipment provider updates—
      • (i) the metering records with the details of the replacement, including the date; and
      • (ii) the registry metering records.
  • (3B) In setting a procedure under subclause (3A)(b)(ii), a metering equipment provider must ensure that, within 10 business days of the replacement occurring, the person carrying out the replacement provides the notice and metering records for the replaced control device and the replacement control device to—
    • (a) the metering equipment provider; and
    • (b) the approved test house that is responsible for the certification of the metering installation.
  • (3C) Despite subclauses (1) and (2)(b), the certification of a metering installation is not cancelled, if clause 48(1A) to (1H) applies.
  • (4) Despite subclause (2)(e), the certification of a metering installation continues if—
    • (a) there is a minor repositioning of 1 of the following in a category 1 metering installation which does not involve disconnection of wiring:
      • (i) the meter in the existing metering installation enclosure; or
      • (ii) the existing metering installation enclosure; or
    • (b) the relocation does not cause, directly or indirectly, the metering installation to be—
      • (i) outside the applicable accuracy tolerances set out in Table 1 of Schedule 10.1; or
      • (ii) defective; or
      • (iii) not fit for purpose.
  • (5) [Revoked].
  • (6) [Revoked]
  • (7) [Revoked].

Clause 19(2): amended, on 1 February 2021, by clause 30(a) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 19(2)(b): amended, on 1 February 2021, by clause 30(b) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 19(2)(ba): inserted, on 1 February 2021, by clause 30(c) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 19(2A): inserted, on 29 August 2013, by clause 37(1) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 19(2B): inserted, on 1 February 2021, by clause 30(d) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 19(3)(f): amended, on 29 August 2013, by clause 37(2) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 19(3)(f): amended, on 1 February 2016, by clause 32(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2015.

Clause 19(3)(f): amended, on 13 October 2018, by clause 5(1) of the Electricity Industry Participation Code Amendment (Amendments to Certification Reports) 2018.

Clause 19(3)(g): revoked, on 1 February 2016, by clause 32(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2015.

Clause 19(3)(g): inserted, on 29 August 2013, by clause 37(3) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 19(3)(h): inserted, on 13 October 2018, by clause 5(2) of the Electricity Industry Participation Code Amendment (Amendments to Certification Reports) 2018.

Clause 19(3A): amended, on 1 February 2016, by clause 32(3)(a) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2015.

Clause 19(3A)(aa): inserted, on 1 February 2016, by clause 32(3)(b) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2015.

Clause 19(3A) and 19(3B): inserted, on 29 August 2013, by clause 37(3) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 19(3B): amended, on 1 November 2018, by clause 31(a), (b) and (c) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.

Clause 19(3C): inserted, on 1 February 2021, by clause 30(e) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 19(5), (6) & (7): revoked, on 20 December 2021, by clause 32 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.

20

Cancellation of certification of metering installations

  • (1) The certification of a metering installation is automatically cancelled on the date on which any 1 of the following events takes place:
    • (a) the metering installation is modified otherwise than under clause 19(3), 19(3A), or 19(3C):
    • (b) the metering installation is classed as outside the applicable accuracy tolerances set out in Table 1 of Schedule 10.1, defective, or not fit for purpose under—
      • (i) this Part; or
      • (ii) any audit:
    • (c) an ATH advises the metering equipment provider responsible for the metering installation of—
      • (i) a reference standard or working standard used to certify the metering installation not being compliant with this Part when it was used to certify the metering installation; or
      • (ii) the failure of a group of meters in the statistical sampling recertification process for the metering installation; or
      • (iii) the failure of a certification test for the metering installation:
    • (d) the manufacturer of a metering component in the metering installation determines that the metering component does not comply with the standards to which the metering component was tested:
    • (e) an inspection of the metering installation, that is required under this Part, is not carried out in accordance with the relevant clauses of this Part:
    • (f) if under clause 6(2) the metering installation has been determined to be a lower category, and:
      • (i) the metering equipment provider has not received, in any month, the report referred to in clause 6(2A)(a); or
      • (ii) the report referred to in clause 6(2A)(a) demonstrates that the maximum current conveyed through the metering installation, at any time during the previous month, exceeded the maximum permitted current for the metering installation category as certified; or
      • (iii) the metering equipment provider has not received, in any month, the report referred to in clause 6(2A)(b); or
      • (iv) the report referred to in clause 6(2A)(b) identifies that the electricity conveyed through the point of connection exceeded 0.5 GWh during the previous 12 month period:
    • (g) the metering installation
      • (i) is certified under clause 14 and sufficient load is available for full certification testing; and
      • (ii) has not been retested under clause 14(4):
    • (h) a control device in the metering installation certification is, and remains for a period of at least 10 business days, bridged out under clause 35(1):
    • (i) the metering equipment provider responsible for the metering installation is advised by an ATH under clause 48(6)(b) that a seal has been removed or broken and the accuracy and continued integrity of the metering installation has been affected.
    • (j) the metering installation is a half-hour metering installation and was certified after 29 August 2013, the service access interface is the metering equipment provider’s back office, and the metering equipment provider
      • (i) fails to comply with clause 8(2)(b) of Schedule 10.6; or
      • (ii) fails to comply with clause 8(9) of Schedule 10.6; or
      • (iii) performs the comparison in clause 8(9) of Schedule 10.6 but—
        • (A) the difference between the sum of the half hour metering raw meter data and the increment of the metering installation’s accumulating meter registers is greater than 1kWh; and
        • (B) the metering equipment provider has failed to remediate the issue causing the difference and provide the correct data within three business days.
  • (2) A metering equipment provider must, within 10 business days of becoming aware that 1 of the events in subclause (1) has occurred in relation to a metering installation for which it is responsible––
    • (a) update the metering installation’s certification expiry date in the registry; and
    • (b) if any one of the events in subclause (1)(j) has occurred, update the metering installation’s AMI flag to “N” in the registry.
  • (3) The obligations in subclause (2) do not apply if the metering installation is recertified within the 10 business days specified in subclause (2).

Clause 20(1): amended, on 1 February 2016, by clause 33(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2015.

Clause 20(1)(a): amended, on 1 February 2016, by clause 33(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2015.

Clause 20(1)(a): amended, on 1 February 2021, by clause 31(1)(a) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 20(1)(f): inserted, on 1 February 2021, by clause 31(1)(b) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 20(1)(j): inserted, on 1 February 2021, by clause 31(2) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 20(2): replaced, on 1 February 2021, by clause 31(3) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 20(3): inserted, on 1 February 2021, by clause 31(3) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Accuracy and error calculation

21

Metering installation accuracy

  • An ATH must not certify a metering installation if the metering installation exceeds the maximum permitted error for the relevant metering installation category set out in Table 1 of Schedule 10.1, after the application of any external compensation factors.

22

Error Calculation

  • (1) An ATH must, before it certifies a metering installation under clauses 12 or 13, calculate the error of the metering installation in accordance with the following:
    • (a) the ATH must calculate the percentage error of the metering installation using appropriate mathematical methods, taking account of—
      • (i) all sources of measurement error; and
      • (ii) the estimated total quantity of electricity to be conveyed through the metering installation over the next 12 months; and
    • (b) the error calculation must include uncertainty in measurement; and
    • (c) for the purposes of paragraph (b), the ATH must calculate uncertainty at a 95% level of confidence and in compliance with JCGM 100:2008.
  • (2) The ATH must not certify the metering installation if—
    • (a) the uncertainty for the metering installation is greater than the relevant maximum site uncertainty set out in Table 1 of Schedule 10.1; and
    • (b) the sum of the measured error and the uncertainty of the metering installation is greater than the relevant maximum permitted error set out in Table 1 of Schedule 10.1.
  • (3) The ATH must record the calculation under subclause (1)(a) in the metering installation certification report.

23

Time keeping requirements

  • A metering equipment provider must, if a time keeping device that is not remotely monitored and corrected controls the switching of a meter register in a metering installation for which it is responsible, ensure that the time keeping device—
    • (a) has a time keeping error of not greater than an average of 2 seconds per day over a period of 12 months; and
    • (b) is monitored and corrected at least once every 12 months.

24

Compensation factors

  • (1) An ATH must, before it certifies a metering installation that requires a compensation factor
    • (a) advise the metering equipment provider responsible for the metering installation of the compensation factor; and
    • (b) ensure that the compensation factor, whether internally or externally applied, is only applied as follows:
      • (i) for ratio compensation, on a category 1 metering installation, or higher category of metering installation; or
      • (ii) for error compensation, on a metering installation that quantifies electricity conveyed through a point of connection to the grid; or
      • (iii) for loss compensation, only on a category 3 or higher metering installation.
  • (2) An ATH must, when it prepares a certification report for a metering installation that requires a compensation factor, record the methodology, assumptions, measurements, calculation, and details of—
    • (a) each compensation factor that is included within the internal configuration of the metering installation; and
    • (b) each compensation factor that must be applied to the raw meter data.
  • (3) A metering equipment provider must, for a metering installation in relation to which an external compensation factor must be applied,—
    • (a) if the metering installation is for a point of connection that is an NSP, advise the reconciliation participant responsible for the metering installation of the compensation factor within 10 business days of the date on which the metering installation is certified; or
    • (b) in all other cases, update the compensation factor recorded in the registry in accordance with Table 1 of Schedule 11.4.

Clause 24(1): amended, on 1 February 2021, by clause 32(a)(i) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 24(1)(b): amended, on 1 February 2021, by clause 31(a)(ii) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 24(3): amended, on 1 February 2021, by clause 31(b)(i) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 24(3)(b): amended, on 5 October 2017, by clause 189 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

Clause 24(3)(b): amended, on 1 February 2021, by clause 31(b)(ii) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Installation of metering components in metering installations

25

Installation of metering components

  • (1) An ATH must, before it certifies a metering installation, ensure that installation of—
    • (a) measuring transformers, and associated burden if required, test facilities, potential fuses, and switchboard wiring, was carried out by—
      • (i) a suitably qualified person (for example by a switchboard manufacturer); or
      • (ii) an ATH; and
    • (b) each metering component in the metering installation, other than a metering component referred to in paragraph (a), is carried out by an ATH.
  • (2) An ATH must, before it certifies a metering installation, ensure that each metering component in the metering installation has been installed in accordance with the design report under clause 2.

26

Requirements for metering installation incorporating meter

  • (1) A metering equipment provider must ensure that each meter in a metering installation for which it is responsible is certified in accordance with this Part.
  • (2) An ATH must, unless clause 43(2) applies, before it certifies a metering installation incorporating a meter, if the meter had previously been used in another metering installation, ensure that the meter has been recalibrated since it was removed from the previous metering installation, by—
    • (a) an approved calibration laboratory; or
    • (b) an ATH.
  • (3) The ATH must, before it certifies a metering installation incorporating a meter, document in the metering records
    • (a) any regular maintenance required for the meter in accordance with the manufacturer’s recommendations; and
    • (b) any maintenance that has been carried out on the meter (for example battery monitoring and replacement).
  • (4) An ATH must, before it certifies a metering installation incorporating a meter, record in the metering installation certification report, the maximum interrogation cycle for the metering installation.
  • (5) The maximum interrogation cycle for a metering installation referred to in subclause (4) is the period of memory availability given the meter configuration.
  • (6) Subclause (4) does not apply to a metering installation incorporating both a meter and a data storage device (see clause 36 of Schedule 10.7).

Clause 26(2): amended, on 1 February 2016, by clause 34(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2015.

Clause 26(6): substituted, on 1 February 2016, by clause 34(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2015.

27

Meter certification expiry date

  • (1) An ATH must, before it certifies a metering installation incorporating a meter, determine the meter certification expiry date for each meter in the metering installation in accordance with this clause.
  • (2) The meter certification expiry date must be the earliest end date of the following periods, calculated from the date of commissioning of the metering installation:
    • (a) the maximum metering installation certification validity period set out in Table 1 of Schedule 10.1 for the relevant category of metering installation; or
    • (b) [Revoked]
    • (c) the certification period specified in the meter certification report.
  • (3) Despite subclause (2), the meter certification expiry date for a meter that has been certified and subsequently installed in, but then removed from, a category 1 metering installation, remains the meter certification expiry date determined for that meter when it was installed in the category 1 metering installation.
  • (4) Despite subclauses (2) and (3), if meter is not installed in a metering installation within 24 months of the date of the meter’s certification report, the meter must be recertified before it is installed.
  • (5) The ATH must record the certification expiry date for each meter in a metering installation in—
    • (a) the metering installation certification report; and
    • (b) the meter certification report.

Clause 27(2)(b): revoked, on 1 February 2021, by clause 33(a) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 27(3): amended, on 29 August 2013, by clause 38 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 27(4): amended, on 1 February 2021, by clause 33(b) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

28

Requirements for metering installation incorporating measuring transformer

  • (1) A metering equipment provider must ensure that each measuring transformer in a metering installation for which it is responsible is certified in accordance with this Part.
  • (2) An ATH must, before it certifies a metering installation which includes a measuring transformer that had previously been used in another metering installation, ensure that the measuring transformer has been recalibrated, since it was removed from the previous metering installation, by—
    • (a) an approved calibration laboratory; or
    • (b) an ATH.
  • (3) The ATH must, before it certifies a metering installation incorporating a measuring transformer, document in the metering records
    • (a) any regular maintenance required for the measuring transformer in accordance with the manufacturer’s recommendations; and
    • (b) any maintenance that has been carried out on the measuring transformer.
  • (4) An ATH must, before it certifies a metering installation incorporating a measuring transformer,—
    • (a) ensure that—
      • (i) the measuring transformer is connected to a meter through a test facility that has provision for isolation; and
      • (ia) the test facility and the provision for isolation are installed as physically close to the meter as practicable in the circumstances; and
      • (ii) the test facility has a transparent cover that is not obscured; and
    • (b) using the fully calibrated certification method or the comparative recertification method, ensure that the ATH calculates the maximum permitted error in accordance with clause 22; and
    • (c) carry out primary injection tests on the measuring transformer if it considers it is appropriate in the circumstances; and
    • (d) ensure that the measuring transformer is—
      • (i) mounted securely; and
      • (ii) if practicable, in an enclosure that is sealed in accordance with clause 47 against unauthorised access; and
    • (e) ensure that any voltage supply from a voltage transformer to a meter, or other equipment in the metering installation, is protected by appropriately rated fuses or circuit breakers dedicated to the supply; and
    • (f) ensure that all fuses and circuit breakers are sealed or located in sealed enclosures under clause 47; and
    • (g) ensure that, if an enclosure also contains fuses or circuit breakers supplying other circuits, those supplying metering circuits are individually sealed; and
    • (h) ensure that if the measuring transformer’s secondary circuit in the metering installation is earthed, it is earthed at no more than 1 point; and
    • (i) ensure that the total in-service burden (magnitude and phase angle, where appropriate) on the measuring transformer complies with clause 31.
      • (i) [Revoked]
      • (ii) [Revoked].
  • (5) Despite subclause (4)(d)(ii), if access to the enclosure is required by a person other than an employee or subcontractor of an ATH, the ATH may use alternative sealing arrangements (for example, terminal studs drilled so that sealing wire can be passed through the holes to secure the connections, or the use of sealing paint applied to terminal screws).

Clause 28(4)(a): substituted, on 29 August 2013, by clause 39 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 28(4)(b): replaced, on 1 February 2021, by clause 34(a) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 28(4)(i): amended, on 1 February 2021, by clause 34(b)(i) and (ii) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 28(4)(i)(i) and (ii): revoked, on 1 February 2021, by clause 34(b)(iii) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

29

Measuring transformer certification expiry date

  • (1) An ATH must, before it certifies a metering installation incorporating a measuring transformer, determine the measuring transformer certification expiry date for each measuring transformer in the metering installation in accordance with this clause.
  • (2) The measuring transformer certification expiry date must be no later than the last day of the measuring transformer certification validity period specified in the measuring transformer certification report, after the date of commissioning.
  • (3) The ATH must record the measuring transformer certification expiry date for each measuring transformer in a metering installation in—
    • (a) the certification report for the metering installation; and
    • (b) the certification report for the measuring transformer.

30

Other equipment using measuring transformer

  • (1) A metering equipment provider must not permit a measuring transformer, in a metering installation for which it is responsible, to be connected to equipment used at any time for a purpose other than metering, unless it is not practical for the equipment to have a separate measuring transformer.
  • (2) An ATH must, before it certifies a metering installation incorporating a measuring transformer used by—
    • (a) another metering installation, ensure, where voltage transformers are connected to more than 1 meter, that—
      • (i) the meters are included in the metering installation being certified; and
      • (ii) appropriate fuses or circuit breakers are provided to protect the metering circuit from short circuits or overloads affecting the other meter:
    • (b) equipment referred to in subclause (1), ensure that—
      • (i) the accuracy of the metering installation remains within the maximum permitted error for the relevant metering installation category set out in Table 1 of Schedule 10.1; and
      • (ii) the metering installation certification report confirms that the accuracy of the metering installation remains within the maximum permitted error for the relevant metering installation set out in Table 1 of Schedule 10.1; and
      • (iii) any wiring between the equipment and any part of the metering installation has no intermediate joints; and
      • (iv) the equipment referred to in subclause (1) is labelled appropriately, including with any restrictions regarding being electrically disconnected; and
      • (v) the connection details of the equipment referred to in subclause (1) are recorded in the metering installation design report; and
      • (vi) appropriate fuses or circuit breakers are provided to protect the voltage transformer and metering circuit from short circuits or overloads affecting the other equipment; and
      • (vii) the wiring referred to in subparagraph (iii) is certified as part of the metering installation.
  • (3) [Revoked]

Clause 30(2)(b)(iv): amended, on 5 October 2017, by clause 190 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

Clause 30(2)(b)(vi): amended, on 29 August 2013, by clause 40(1) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 30(2)(b)(vii): inserted, on 29 August 2013, by clause 40(2) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 30(3): revoked, on 29 August 2013, by clause 40(3) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

31

Measuring transformer burden and compensation requirements

  • (1) An ATH may certify a metering installation for a point of connection to the grid that includes error compensation factors as an alternative to the use of burden resistors, only if the ATH is satisfied the error compensation factors will provide a more accurate result than the use of burden resistors.
  • (2) A metering equipment provider must ensure that a change to, or addition of, a measuring transformer burden or compensation factor related to a measuring transformer, in a metering installation for which it is responsible, is only carried out by:
    • (a) the ATH who most recently certified the metering installation; or
    • (b) if the metering installation is for a point of connection to the grid, a suitably qualified person approved by both—
      • (i) the metering equipment provider responsible for the metering installation; and
      • (ii) the ATH who most recently certified the metering installation.
  • (3) An ATH must, before it may add or change any burden or compensation factor detailed in the design report referred to in clause 2,—
    • (a) obtain the approval of the metering equipment provider responsible for the metering installation, which may be withheld in the metering equipment provider’s absolute discretion; and
    • (b) if it obtains the approval referred to in paragraph (a), record in the metering records the reason for the proposed addition or change.
  • (4) A metering equipment provider must, before it may approve the addition of, or change to, the burden or compensation factor of a measuring transformer in a metering installation for which it is responsible, consult with the ATH who carried out the most recent certification of the metering installation.
  • (5) If the metering equipment provider approves the addition of, or change to, the burden or compensation factor under subclause (4), it must ensure that the metering installation, other than a metering installation for a point of connection to the grid, is recertified by an ATH for the addition of or change to the burden or compensation factor before the addition or change becomes effective.
  • (6) Despite subclause (3)(a), an ATH may change the burden on a voltage transformer, without obtaining the approval of the metering equipment provider, if the ATH confirms in the certification report that the difference between the new burden and the burden at the time of the most recent metering installation certification is—
    • (a) less than or equal to one thirtieth of the rating, in VA, of the voltage transformer if the voltage transformer is rated at less than 30 VA; or
    • (b) no greater than 1 VA, if the voltage transformer is rated at equal to or greater than 30 VA.
  • (7) An ATH must, before it certifies a metering installation incorporating a measuring transformer,—
    • (a) ensure that the in-service burden (magnitude and phase angle, where appropriate) on the measuring transformer does not exceed the upper limit of the range specified for the measuring transformer if specified in the design report for the metering installation; and
    • (b) ensure that the in-service burden on the measuring transformer is within the range specified in the certification report for the measuring transformer by installing burdening resistors to increase the in-service burden if necessary; or
    • (c) confirm that—
      • (i) if the primary voltage of the measuring transformer is greater than 1kV, a class A ATH has confirmed by calibration that the accuracy of the measuring transformer will not be adversely affected by the in-service burden being less than the lowest burden test point specified in the standard; or
      • (ii) the measuring transformer's manufacturer has confirmed that the accuracy of the measuring transformer will not be adversely affected by the in-service burden being less than the lowest burden test point specified in the standard.

Clause 31(7): replaced, on 1 February 2021, by clause 35 of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 31(7): substituted, on 29 August 2013, by clause 41 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 31(7)(b): amended, on 15 May 2014, by clause 19 of the Electricity Industry Participation (Minor Code Amendments) Code Amendment 2014.

Clause 31(7)(b): substituted, on 19 December 2014, by clause 22 of the Electricity Industry Participation Code Amendment (Minor Code Amendments) (No 3) 2014.

32

Alternative certification requirements for metering installation incorporating measuring transformer

  • (1) An ATH may, if it cannot comply with the requirements of clause 2 of Schedule 10.8 due solely to its inability to obtain physical access to test an installed measuring transformer in a metering installation, certify the metering installation for a period not exceeding 24 months, if—
    • (a) the measuring transformer has not previously been certified under this clause; and
    • (b) the ATH is satisfied, having made due enquiry, that the metering installation will comply with the applicable accuracy requirements as set out in Table 1 of Schedule 10.1; and
    • (c) the ATH has advised the metering equipment provider responsible for the metering installation that this clause applies; and
    • (d) in the case of an ICP that is not an NSP, the metering equipment provider has updated the metering installation's certification in the registry.
  • (2) The metering equipment provider must, if a metering installation for which it is responsible has been certified under subclause (1),—
    • (a) by no later than 10 business days after the date of certification of the metering installation, advise the Authority in the prescribed form of—
      • (i) all relevant details of the metering installation; and
      • (ii) the reason or reasons why the ATH could not obtain physical access to the measuring transformer; and
      • (iii) the reason or reasons why the accuracy of the metering installation cannot be outside of the applicable accuracy requirements set out in Table 1 of Schedule 10.1; and
      • (iv) the metering installation certification expiry date; and
    • (b) respond, within 5 business days, to any requests from the Authority for additional information; and
    • (c) ensure that all of the details are recorded in the metering installation certification report.
  • (3) If an ATH certifies a metering installation under subclause (1), the metering equipment provider responsible for the metering installation must take all steps to ensure that the metering installation is certified, before the metering installation certification expiry date referred to in subclause (2)(a)(iv), in accordance with all other applicable requirements of this Part.
  • (4) If the Authority subsequently determines that the ATH could have obtained physical access to test an installed measuring transformer in the metering installation, the metering installation is deemed to be defective and the metering equipment provider responsible for the metering installation must comply with clauses 10.43 to 10.48.

Clause 32(1)(d): amended, on 1 February 2021, by clause 36 of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 32(1)(d), (2) and (4): amended, on 5 October 2017, by clause 191 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

33

Requirements for metering installation incorporating control device

  • (1A) A reconciliation participant that is responsible for a point of connection must advise the metering equipment provider responsible for the metering installation at the point of connection if a control device in the metering installation is to be used by the reconciliation participant for any purpose under Part 15 to do either of the following:
    • (a) control a load:
    • (b) switch meter registers.
  • (1) A reconciliation participant must ensure that a control device is certified under this Part by an ATH before the reconciliation participant uses any raw meter data that depends on the operation of the control device, for any purpose under Part 15.
  • (2) An ATH must, before it certifies a metering installation incorporating a control device that must be certified under subclause (1),—
    • (a) determine the control device certification expiry date for each control device contained in the metering installation as being the same as the metering installation certification expiry date; and
    • (b) record the expiry date, for each control device, in the metering installation certification report; and
    • (c) if the metering installation contains a control device that had previously been used in another metering installation, ensure that the control device has been certified in accordance with Schedule 10.8 after it was removed from the other metering installation; and
    • (d) ensure that the metering installation certification report includes confirmation that—
      • (i) the control device complies with any applicable standards listed in Table 5 of Schedule 10.1; and
      • (ii) the control device is fit for purpose; and
    • (e) check that the control device is—
      • (i) likely to receive control signals, as required under clause 34; and
      • (ii) correctly connected; and
      • (iii) correctly programmed.

Clause 33(1A): inserted, on 29 August 2013, by clause 42(1) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 33(1): substituted, on 29 August 2013, by clause 42(2) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

34

Control device reliability requirements

  • (1) An ATH must, before it certifies a metering installation incorporating a control device that is required to be certified under clause 33, determine, in consultation with the relevant distributor if appropriate, if the likelihood of the control device not receiving control signals would affect the accuracy or completeness of the information for the purposes of Part 15.
  • (2) A control signal provider, if it is a participant, must respond in a timely manner to any requests from the ATH referred to in subclause (1).
  • (3) The ATH must, if it determines under subclause (1) that the likelihood of the control device not receiving control signals would affect the accuracy or completeness of the information for the purposes of Part 15, advise the metering equipment provider responsible for the metering installation of its determination, including all relevant details, within 3 business days of making its determination.
  • (4) If subclause (3) applies—
    • (a) the ATH may certify the metering installation excluding the control device; and
    • (b) the ATH must not certify the control device.
  • (5) The metering equipment provider must, as soon as reasonably practicable, and at least within 3 business days after being advised under subclause (3), advise the following parties of the ATH's determination, including all relevant details:
    • (a) the reconciliation participant for the point of connection for the metering installation; and
    • (b) the control signal provider.

Clause 34(4)(a): substituted, on 29 August 2013, by clause 43 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

35

Control device bridged out

  • (1) A participant must, within 10 business days of bridging out a control device, or becoming aware of a control device being bridged out, advise the following persons:
    • (a) the reconciliation participant for the point of connection for the metering installation; and
    • (b) the metering equipment provider responsible for the metering installation incorporating the control device.
  • (2) A metering installation incorporating a control device referred to in subclause (1) is defective for the purposes of clause 10.43 if it is used for the purposes of providing information for the purposes of Part 15.

36

Requirements for metering installation incorporating data storage device

  • (1) A metering equipment provider must ensure that each data storage device incorporated in a metering installation for which it is responsible, is certified in accordance with this Part.
  • (2) An ATH must, before it certifies a metering installation incorporating a data storage device that had previously been used in another metering installation, ensure that the data storage device has been recalibrated since it was removed from the previous metering installation, by—
    • (a) an approved calibration laboratory; or
    • (b) an approved test laboratory; or
    • (c) an ATH.
  • (3) An ATH must, before it certifies a metering installation incorporating a data storage device (including a metering installation incorporating both a meter and a data storage device), record in the metering installation certification report, the maximum interrogation cycle for the data storage device.
  • (4) The maximum interrogation cycle for each services access interface for a metering installation incorporating a data storage device is the shortest of the following periods:
    • (a) the period of inherent data loss protection for the metering installation; and
    • (b) the period of memory availability given the data storage device configuration; and
    • (c) the longest period in which the accumulated drift of a data storage device clock is expected to remain in compliance with the maximum time error set out in Table 1 of clause 2 of Schedule 15.2 for the category of the metering installation.

Clause 36(3): amended, on 29 August 2013, by clause 44 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 36(3): amended, on 1 February 2016, by clause 35 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2015.

Clause 36(4): amended, on 1 February 2021, by clause 37 of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

37

Data storage device certification expiry date

  • (1) An ATH must, before it certifies a metering installation incorporating a data storage device
    • (a) determine, in accordance with this clause, the data storage device certification expiry date for each data storage device contained in the metering installation; and
    • (b) record the expiry date in the metering installation certification report.
  • (2) The data storage device certification expiry date must—
    • (a) for a data storage device that is integral to a meter, be no later than the meter certification expiry date; or
    • (b) for a data storage device that is not integral to a meter, be no later than the earlier of—
      • (i) the last day of the data storage device certification validity period specified in the data storage device certification report, after the commissioning date; and
      • (ii) the meter certification expiry date.
  • (3) The ATH must record the data storage device certification expiry date for a data storage device in a metering installation in—
    • (a) the certification report for the metering installation; and
    • (b) the certification report for the data storage device.

Clause 37(2)(b)(i): amended, on 1 April 2025, by clause 9 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2025.

38

Requirements for certification of metering installation incorporating data storage device

  • (1) An ATH must, before it certifies a metering installation, ensure that each data storage device in the metering installation
    • (a) is installed so that onsite interrogation is possible without the need to interfere with seals; and
    • (b) has a dedicated power supply unless the data storage device is integrated with another metering component.
  • (2) An ATH must, before it certifies a metering installation,—
    • (a) ensure that each data storage device in the metering installation
      • (i) is compatible with each other metering component of the metering installation; and
      • (ii) is suitable for the electrical and environmental site conditions in which it is installed; and
      • (iii) has been certified under Schedule 10.8; and
      • (iv) has appropriate electrical separation between all of its outputs and inputs, and all of its outputs and inputs are rated for purpose; and (v) has no outputs that will interfere with the operation of the metering installation; and
      • (vi) records periods of data identifiable or deducible by both date and time on interrogation; and
    • (b) check and confirm in the metering installation certification report that each data storage device in the metering installation
      • (i) has memory capacity and functionality that is suitable for the proposed functions of the data storage device specified in the design report for the metering installation; and
      • (ii) has availability of memory for a period that is suitable for the proposed functions as set out in the design report for the metering installation, and for a minimum continuous period of 15 days.
  • (3) An ATH must, before it certifies a metering installation incorporating a data storage device, document in the metering records
    • (a) any regular maintenance required for the data storage device in accordance with the manufacturer's recommendations; and
    • (b) any maintenance that has been carried out on the data storage device (for example battery monitoring and replacement).

Heading: amended, on 1 February 2016, by clause 36 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2015.

Clause 38(2)(a)(iv): replaced, on 5 October 2017, by clause 192 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

39

Changes to data storage device software, ROM, or firmware

  • (1) A metering equipment provider must, if it proposes to change the software, ROM, or firmware of a data storage device installed in a metering installation for which it is responsible, ensure that, before the change is carried out, an approved test laboratory
    • (a) tests and confirms that the integrity of the measurement and logging of the data storage device would be unaffected by the proposed change; and
    • (b) documents the methodology and conditions necessary to implement the proposed change; and
    • (c) advises the ATH that certified the metering installation of any change that would, or would be likely to, affect the accuracy of the data storage device.
  • (2) A metering equipment provider must, when implementing a proposed change described in subclause (1),—
    • (a) carry out the change in accordance with the documented methodology and conditions referred to in subclause (1)(b); and
    • (b) keep a list of data storage devices to which the change was made; and
    • (c) update the metering records for each metering installation referred to in subclause (1) with details of the change and the methodology referred to in subclause (1)(b).

40

Communication equipment requirements

  • A metering equipment provider must ensure that the use of its communication equipment complies with the compatibility and connection requirements of any communication network operator to whose communication network the metering equipment provider has communication equipment connected.

41

Certification stickers

  • (1) An ATH must, except as provided for in clause 16(6) and subclause (4), if it has certified a metering installation under this Part, confirm the certification by attaching a metering installation certification sticker as physically close as practicable to (including, if practicable, on) the meter while maintaining reasonable visibility of the certification sticker and the meter.
  • (2) An ATH attaching a metering installation certification sticker must ensure that it shows—
    • (a) the name of the ATH who certified the metering installation; and
    • (b) the most recent certification date of the metering installation; and
    • (c) the metering installation category for which the metering installation has been certified; and
    • (d) the ICP identifier for the metering installation; and
    • (e) the certification number for the metering installation; and
    • (f) any other information that the Authority may, from time to time, specify by giving reasonable notice.
  • (3) An ATH must, when certifying a metering installation that includes a metering component that does not have a certification sticker attached—
    • (a) obtain the metering component certification sticker required under clause 8 of Schedule 10.8; and
    • (b) attach it next to the metering installation certification sticker.
  • (4) Despite subclauses (1) and (3)(b), the ATH must, if attaching a metering installation certification sticker as required under subclause (1) is not practicable,—
    • (a) devise and use an alternative means of documenting, providing, and maintaining information in a manner at least equivalent in its effect to that required under subclause (1); and
    • (b) keep any metering component certification sticker with the information referred to in paragraph (a).
  • (5) If an ATH certifies a metering component of a metering installation on the same day that the ATH certifies the metering installation, the ATH may combine the metering installation certification sticker under subclause (1) with the metering component certification sticker under clause 8(1) of Schedule 10.8.
  • (6) If an ATH combines a metering installation certification sticker with the metering component certification sticker under subclause (5), the ATH must––
    • (a) ensure that the combined sticker shows all the information required by subclause (2) and clause 8(2) of Schedule 10.8; and
    • (b) meet the requirements of subclauses (1), (3) and (4), as if the combined sticker were a metering installation certification sticker.
  • (7) The combined sticker under subclause (5) is immediately invalid if—
    • (a) the metering installation certification expiry date changes; or
    • (b) a metering component to which the combined certification sticker relates is removed from the metering installation.
  • (8) For the avoidance of doubt, the certification of any metering component that is not removed from the metering installation does not become invalid under subclause (7).
  • (9) An ATH must, when attaching a metering installation certification sticker under subclause (1), remove or obscure any invalid or expired certification stickers.

Clause 41(2)(f): amended, on 1 November 2018, by clause 32 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.

Clause 41(5) to (9): inserted, on 1 February 2021, by clause 38 of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

42

Enclosures

  • An ATH must, before it certifies a metering installation, ensure that, if a metering component in the metering installation is housed in a separate enclosure from the meter enclosure, the enclosure is—
    • (a) appropriate to the environment in which it is located; and
    • (b) has a warning label attached stating that the enclosure houses a metering component.

Certification of metering components

43

Metering components must be certified

  • (1) An ATH must, before it certifies a metering installation, ensure that each metering component that is required to be certified under this Part and which is in the metering installation
    • (a) is certified by an ATH in accordance with this Part; and
    • (b) since certification, has been appropriately stored and not used.
  • (2) Despite subclause (1) and clause 26(2), an ATH may certify a category 1 metering installation that contains a meter which has been removed from another category 1 metering installation (the "previous metering installation") if the ATH
    • (a) is satisfied that external factors have not affected the accuracy of the meter; and
    • (b) has confirmed that it has been no more than 12 months since the meter was installed in the previous metering installation; and
    • (c) has confirmed that the meter was calibrated or recalibrated before being installed in the previous metering installation and after being removed from any other metering installation in which the meter was previously installed.

Clause 43(1): amended, on 1 February 2016, by clause 37(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2015.

Clause 43(2): substituted, on 1 February 2016, by clause 37(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2015.

Inspection requirements

44

General inspection requirements

  • (1) An ATH must, when carrying out an inspection of a metering installation,—
    • (a) check and confirm that the data storage device in the metering installation operates in accordance with the requirements of this Part; and
    • (b) check and confirm that the expected remaining lifetime of each battery in the metering installation will be reasonably likely to meet or exceed the metering installation certification expiry date; and
    • (c) ensure that no modifications under clause 19 have been made to the metering installation without the change having been documented and certification requirements satisfied; and
    • (d) visually inspect all seals, enclosures, metering components, and wiring of the metering installation for evidence of damage, deterioration, or tampering; and
    • (e) ensure that the metering installation and its metering components carry appropriate certification stickers in accordance with clause 41; and
    • (f) in the case of a category 1 metering installation incorporating a data storage device, check and confirm there is no difference between the volume of electricity recorded by the master accumulation register of a data storage device, and the sum of the meter registers.
  • (2) An ATH must, for each inspection of a metering installation that it carries out, prepare an inspection report that details—
    • (a) the checks that were carried out; and
    • (b) the results of the checks; and
    • (c) the metering installation certification expiry date; and
    • (d) the serial numbers of each metering component in the metering installation; and
    • (e) any instances of non-compliance with this Part, and the actions taken to remedy such a breach; and
    • (f) the name and signature of the person who carried out the inspection and the date on which it was signed.
  • (3) The ATH must, within 10 business days of carrying out the inspection, provide the inspection report to the metering equipment provider who is responsible for the metering installation.
  • (4) If an ATH has not performed an inspection of a metering installation within the specified timeframe under clauses 45(1) or 46(1), the certification of the metering installation is automatically cancelled on the date by which the metering installation was required to have been inspected.
  • (5) A metering equipment provider must, within 20 business days of receiving the inspection report,—
    • (a) undertake a comparison of—
      • (i) the information recorded under subclauses (2)(c) and (d); and
      • (ii) the information in its own records; and
    • (b) investigate and correct any discrepancies found under paragraph (a); and
    • (c) update the registry with the relevant changes.

Clause 44(4): amended, on 20 December 2021, by clause 33 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.

Clause 44(5)(c): amended, on 5 October 2017, by clause 193 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.

45

Category 1 metering installation inspection requirements

  • (1) A metering equipment provider must ensure that—
    • (a) an ATH has completed an inspection of each category 1 metering installation for which the metering equipment provider is responsible within the period set out in Table 1 of Schedule 10.1, starting from the date of the metering installation’s most recent certification or inspection; or
    • (b) if the metering equipment provider is responsible for any category 1 metering installations that were certified more than 84 months ago, the metering equipment provider inspects a sample of all category 1 metering installations.
  • (1A) When inspecting a sample of category 1 metering installations under subclause (1)(b), the metering equipment provider must—
    • (a) complete the inspections each 12 month calendar year between 1 January and 31 December; and
    • (b) perform the first inspection in the same calendar year the oldest metering installation reaches 84 months since certification.
  • (2) A metering equipment provider must, for the purposes of subclause (1)(b), select a sample by—
    • (a) producing a list of all ICP identifiers of each category 1 metering installation for which it is responsible; and
    • (b) removing from the list of ICP identifiers, any ICP identifier for a metering installation that has been certified or inspected in the 84 months prior to 31 December in the year in which the list was produced; and
    • (c) identifying the applicable required minimum sample size set out in Table 8 of Schedule 10.1, based on the number of metering installations identified in the list of ICP identifiers in produced in accordance with paragraphs (a) and (b); and
    • (d) randomly selecting a sample, of the size required under paragraph (c), from the list produced in accordance with paragraphs (a) and (b).
  • (3) A metering equipment provider must, before it carries out inspections under subclause (1)(b),—
    • (a) submit a documented process for randomly selecting a sample to the Authority at least 2 months before the first date on which it proposes to carry out the inspections; and
    • (b) provide promptly any other information or documentation the Authority may reasonably request.
  • (4) The Authority must, within 2 months of receiving the documented process under subclause (3), advise the metering equipment provider that the documented process—
    • (a) has been approved; or
    • (b) has not been approved, providing reasons.
  • (5) A metering equipment provider must not inspect a sample under this clause unless the Authority has approved the documented process.
  • (6) A metering equipment provider must, for each inspection of a category 1 metering installation conducted under subclause (1)(b), keep records that detail—
    • (a) any defects identified that have affected the accuracy or integrity of the raw meter data recorded by the metering installation; and
    • (b) any discrepancies identified under clause 44(5)(b); and
    • (c) relevant characteristics, sufficient to enable reporting that identifies any correlations or relationships between inaccuracy and characteristics (for example the meter make, model, and network area, for each metering installation); and
    • (d) the procedure used, and the lists generated, to select a sample under subclause (2).
  • (7) A metering equipment provider must, if it believes that a metering installation that an ATH has inspected under this clause is or could be outside the applicable accuracy tolerances set out in Table 1 of Schedule 10.1, defective, or not fit for purpose,—
    • (a) comply with clause 10.43;
    • (b) arrange for an ATH to recertify the metering installation under this Schedule, if the metering installation is found to be—
      • (i) outside the applicable accuracy tolerances set out in Table 1 of Schedule 10.1; or
      • (ii) defective; or
      • (iii) not fit for purpose.
  • (8) A metering equipment provider must, by 1 April in each year, provide to the Authority a report in the prescribed form that states whether the metering equipment provider has, for the previous 1 January to 31 December period, arranged for an ATH to inspect each category 1 metering installation for which it is responsible—
    • (a) under subclause (1)(a), in which case the report must also include, for the period—
      • (i) a list showing the ICP identifier for each ICP which has a metering installation that was due for inspection, the dates by which the metering installation was due for inspection, and the date on which it was inspected; and
      • (ii) a summary of the instances of non-compliance of each category 1 metering installation inspected; and
      • (iii) the detailed records required under subclauses (6)(a) and (6)(b); or
    • (b) under subclause (1)(b), in which case the report must also include, for the period—
      • (i) the number of metering installations identified under subclause (2)(a) to (2)(c); and
      • (ii) a summary of the instances of non-compliance of each category 1 metering installation inspected; and
      • (iii) the detailed records required under subclauses (6)(a) and (6)(b).
  • (9) The Authority may, if it considers that the report provided under subclause (8) indicates that there is a statistically significant number of metering installations in the sample which are outside the applicable accuracy tolerances set out in Table 1 of Schedule 10.1, defective, or not fit for purpose, despite subclause (1)(b), advise the metering equipment provider that it must select another sample in accordance with subclause (2) and comply with the applicable requirements of this clause in respect of the sample.
  • (10) The metering equipment provider must select the additional sample under subclause (9), carry out the required inspections and report to the Authority under subclause (8), within 40 business days of being advised by the Authority under subclause (9).

Clause 45(1)(a) and (b): replaced, on 1 February 2021, by clause 39(1) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 45(1A): inserted, on 1 February 2021, by clause 39(2) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 45(2)(a): amended, on 1 February 2021, by clause 39(3)(a) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 45(2)(b): amended, on 1 February 2016, by clause 38(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2015.

Clause 45(2)(b): replaced, on 1 February 2021, by clause 39(3)(b) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 45(2)(c): amended, on 1 February 2016, by clause 38(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2015.

Clause 45(2)(d): amended, on 1 February 2016, by clause 38(3) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2015.

Clause 45(10): amended, on 29 August 2013, by clause 45 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

46

Category 2 metering installation or higher category of metering installation inspection requirements

  • (1) A metering equipment provider must ensure that each category 2 metering installation, or higher category of metering installation, for which it is responsible is inspected by an ATH at least once within the applicable period set out in Table 1 of Schedule 10.1 starting from the date of the metering installation’s most recent certification.
  • (2) An ATH must, when conducting an inspection of a category 2 metering installation, or higher category of metering installation, and in addition to complying with clause 44, conduct the following checks:
    • (a) a visual inspection of each metering component in the metering installation for damage, tampering, or defect; and
    • (b) if the current transformer can be safely accessed, check the position of the current transformer tap to ensure it is still appropriate for the expected maximum current for the metering installation; and
    • (c) check for the presence of appropriate voltages at the metering installation; and
    • (d) check the voltage circuit alarms and fault indicators.

Sealing

47

Sealing requirements

  • (1) For the purposes of this clause and clause 48, a reference to something being sealed includes being contained in a sealed enclosure.
  • (2) An ATH must, before it certifies a metering installation, ensure that each metering component in the metering installation that could reasonably be expected to affect the accuracy or reliability of the metering installation, is sealed.
  • (3) An ATH must, before leaving a metering installation unattended, ensure that each part and connection of a data storage device that is contained in, or attached to, the metering installation is sealed.
  • (4) Subclause (3) does not apply to a port for on-site reading that is not capable of carrying out any other function.
  • (5) An ATH must, before it certifies a metering installation, ensure that the main switch cover is sealed if the main switch—
    • (a) is on the supply side of the metering installation; and
    • (b) has provision for sealing.
  • (6) An ATH must, when applying a seal to a metering component in an enclosure, attach a label in a prominent position inside the enclosure, warning—
    • (a) of the presence of a sealed metering component in the enclosure; and
    • (b) that care must be taken not to disturb the connections to the metering component.
  • (7) An ATH must use a sealing system that enables the following information to be determined:
    • (a) the ATH who affixed the seal; and
    • (b) the person (or the sealing tool) who applied the seal; and
    • (c) when the seal was applied.

48

Removal or breakage of seals

  • (1) A participant who removes or breaks a seal without authorisation of the metering equipment provider responsible for the metering installation, other than in accordance with subclauses (1A) to (1F), must, within 10 business days of removing or breaking the seal,—
    • (a) advise the metering equipment provider of—
      • (i) the removal or breakage; and
      • (ii) the reason for the removal or breakage; and
    • (b) reimburse the metering equipment provider for the cost of reinstating the seal and recertification if required by the metering equipment provider.
  • (1A) A distributor may interfere with a metering installation without authorisation of the metering equipment provider responsible for the metering installation to reset a load control switch contained within a load control device or bridge or unbridge a load control switch if—
    • (a) the load control switch does not control a time block meter channel; and
    • (b) the distributor provides the load control signal to the load control device.
  • (1B) A distributor that removes or breaks a seal in accordance with subclause (1A) must—
    • (a) ensure that the personnel it uses to remove or break the seal are qualified or trained to a level sufficient to ensure they can safely remove or break the seal, bridge and unbridge the load control switch, and replace the seal in accordance with this Code; and
    • (b) replace the seal with its own seal and have a process for tracing the new seal to the personnel that removed or broke the seal for the distributor; and
    • (c) advise the trader and metering equipment provider responsible for the ICP at which the metering installation is located if the load control switch has been bridged or unbridged.
  • (1C) A trader that is advised under subclause (1B)(c) must, if the profile code has changed, advise the registry manager of the updated profile code for the ICP in accordance with clause 10 of Schedule 11.1.
  • (1D) A trader may remove or break a seal without authorisation of the metering equipment provider responsible for the metering installation to reset a load control switch or bridge or unbridge a load control switch if the load control switch does not control a time block meter channel.
  • (1E) A trader may remove or break a seal in a metering installation without authorisation of the metering equipment provider responsible for the metering installation
    • (a) to electrically connect the load or generation measured by the meter if the load or generation has been electrically disconnected at the meter; or
    • (b) to electrically disconnect the load or generation measured by the meter if the trader has exhausted all other appropriate methods of electrical disconnection; or
    • (c) to bridge the meter.
  • (1F) A trader that removes or breaks a seal in accordance with subclause (1D) or (1E) must—
    • (a) ensure that the personnel it uses to remove or break the seal are qualified or trained to a level sufficient to ensure they can safely remove or break the seal, perform the permitted work described in subclause (1D) or (1E), and replace the seal, in accordance with this Code; and
    • (b) replace the seal with its own seal and have a process for tracing the new seal to the personnel that removed or broke the seal for the trader; and
    • (c) if the profile code has changed, advise the registry manager of the updated profile code for the ICP in accordance with clause 10 of Schedule 11.1; and
    • (d) advise the metering equipment provider that is responsible for the metering installation in which the seal is located that the seal has been broken and what permitted work has been performed.
  • (1G) A metering equipment provider that has been advised under subclause (1B)(c) or (1F)(d) must advise the registry manager of the updated meter register content code for the relevant meter channel if required.
  • (2) A participant who is required under subclause (1)(b) to reimburse the cost of reinstating and recertifying a seal, must do so within 10 business days of the metering equipment provider advising the participant of the cost.
  • (3) A participant who becomes aware that another person has removed or broken a seal, must, within 3 business days of becoming aware, advise the metering equipment provider who is responsible for the metering installation.
  • (4) A metering equipment provider must, if it is advised under subclauses (1) or (3)—
    • (a) use all reasonable endeavours to ascertain—
      • (i) who removed or broke the seal; and
      • (ii) the reason for the removal or breakage; and
    • (b) arrange for an ATH to carry out, as soon as practicable, an inspection of the removal or breakage, and to determine any work required to remedy the removal or breakage.
  • (5) A metering equipment provider must make the arrangements required under subclause (4)(b) within—
    • (a) 3 business days of being advised under subclauses (1) or (3), if the metering installation is category 3 or higher; or
    • (b) 10 business days of being advised under subclauses (1) or (3), if the metering installation is a category 2 metering installation; or
    • (c) 20 business days of being advised under subclauses (1) or (3), if the metering installation is a category 1 metering installation.
  • (6) An ATH must, when investigating an unauthorised removal or breakage under subclause (4)(b), assess the accuracy and continued integrity of the metering installation and—
    • (a) if, in its opinion, the accuracy and continued integrity is unaffected, replace the removed or broken seals; or
    • (b) if, in its opinion, the accuracy and continued integrity is affected, replace the removed or broken seal and advise the metering equipment provider under clause 10.43.
  • (7) If subclause (6)(b) applies, the certification of the metering installation is automatically cancelled from the date on which a participant became aware, or should have become aware, of the removed or broken seal.
  • (8) If a person removes or breaks a seal without authorisation of the metering equipment provider responsible for the metering installation in which the seal is located or not in accordance with subclauses (1A) to (1F), the metering equipment provider or the ATH responsible for certifying the metering component are not liable for any breach of this Code that results from the person’s actions, provided the metering equipment provider or ATH can prove the seal had not been removed or broken when the metering equipment provider or ATH last performed work at the metering installation.

Clause 48(1): amended, on 1 February 2021, by clause 40(1) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clauses 48(1A) to (1G): inserted, on 1 February 2021, by clause 40(2) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 48(8): inserted, on 1 February 2021, by clause 40(3) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Schedule 10.8

cl 10.20, 10.38 and 10.42

Metering component requirements

Meters

1

Meter certification requirements

  • (1) An ATH must, before it certifies a meter, ensure that—
    • (a) an approved test laboratory has—
      • (i) conducted type-testing that the ATH considers appropriate for the model and version of meter; and
      • (ii) produced a type-test certificate that—
        • (A) confirms the meter’s technical characteristics; and
        • (B) confirms the range of environmental conditions within which the meter has been proven accurate and reliable; and
        • (C) confirms that the meter performs the functions for which it was designed; and
        • (D) confirms that the meter complies with the requirements of this Part; and
        • (E) records the tests undertaken by the approved test laboratory and the reasons why the ATH considers that they are appropriate; and
    • (b) the meter has a current calibration report issued by an approved calibration laboratory or an ATH approved to carry out calibration under Schedule 10.3; and
    • (c) the meter calibration report
      • (i) confirms that the meter complies with the standards listed in Table 5 of Schedule 10.1; and
      • (ii) records any tests the ATH has performed to confirm compliance under subparagraph (i) and the results of those tests; and
      • (iii) confirms that the meter has passed the tests; and
      • (iv) records any recommendations on error compensation; and
      • (v) includes any manufacturer’s calibration test reports; and
    • (d) it produces a meter certification report that includes—
      • (i) the date on which it certified the meter; and
      • (ii) the certification validity period or expiry date for the meter for each category of metering installation that the meter may be used in; and
      • (iia) if the certification validity period referred to in subparagraph (ii) is less than the maximum certification validity period permitted under Table 1 of Schedule 10.1, the reasons for the shorter certification validity period; and
      • (iii) the maintenance requirements for the meter; and
      • (iv) the meter calibration report; and
      • (v) whether the certification was based on batch test certificates; and
      • (vi) if the certification was based on batch test certificates, confirmation that the manufacturer’s batch testing facility is, in the ATH’s opinion, of an acceptable standard; and
    • (e) the percentage values of current set out in Table 6 or Table 7 of Schedule 10.1, as applicable, are relative to the meter’s base or rated current (1b or 1n) as appropriate, and this current is selected at a level appropriate for the metering installation in which the meter is to be installed.
  • (2) The certification validity period referred to in subclause (1)(d)(ii) must not be greater than the maximum certification validity period set out in Table 1 of Schedule 10.1 for the relevant categories of metering installations in which the meter may be used.

Clause 1(1)(b): amended, on 19 December 2014, by clause 23(1) of the Electricity Industry Participation Code Amendment (Minor Code Amendments) (No 3) 2014.

Clause 1(1)(c)(ii): amended, on 19 December 2014, by clause 23(2) of the Electricity Industry Participation Code Amendment (Minor Code Amendments) (No 3) 2014.

Clause 1(1)(d)(ii): amended, on 1 April 2025, by clause 10 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2025.

Clause 1(d)(iia): inserted, on 1 February 2021, by clause 41(a) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 1(2): amended, on 1 February 2021, by clause 41(b) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Measuring transformers

2

Measuring transformer certification requirements

  • (1) An ATH must, before it certifies a measuring transformer,—
    • (a) ensure, by testing, that a current calibration report sets out the measuring transformer’s errors at a range of primary values at their rated burdens; and
    • (b) that is a multi-tap current transformer, carry out the calibration tests and only certify the transformer for the ratios that have been calibrated if the test is passed; and
    • (c) [Revoked]
    • (d) determine the measuring transformer certification validity period or expiry date under clause 3(c)(ii); and
    • (e) determine the range, including highest and lowest values, that the in-service burden must be within to ensure the measuring transformer remains accurate, by using one or more of the following:
      • (i) the measuring transformer’s nameplate rating:
      • (ii) the calibration report for the measuring transformer:
      • (iii) the manufacturer’s documentation for the measuring transformer:
      • (iv) the standard set out in Table 5 of Schedule 10.1 the measuring transformer was manufactured to.
  • (2) An ATH must, before it certifies an epoxy insulated current transformer, ensure that the certification tests allow for, and the metering installation certification report shows, the current transformer’s age, temperature, and batch.

Clause 2(1)(c): amended, on 29 August 2013, by clause 46 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 2(1)(c): substituted, on 19 December 2014, by clause 24 of the Electricity Industry Participation Code Amendment (Minor Code Amendments) (No 3) 2014.

Clause 2(1)(c): revoked, on 1 February 2021, by clause 42(a) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 2(1)(d): amended, on 1 February 2021, by clause 42(b) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Clause 2(1)(d): amended, on 1 April 2025, by clause 11 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2025.

Clause 2(1)(e): inserted, on 1 February 2021, by clause 42(c) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

3

Measuring transformer certification report

  • An ATH must, before it certifies a measuring transformer, ensure that—
    • (a) the measuring transformer has a current calibration report issued by an approved calibration laboratory or an ATH approved to carry out calibration under Schedule 10.3; and
    • (b) the measuring transformer calibration report
      • (i) confirms that the measuring transformer complies with the standards listed in Table 5 of Schedule 10.1; and
      • (ii) records any tests the ATH has performed to confirm compliance under subparagraph (i) and the results of those tests; and
      • (iii) confirms that the measuring transformer has passed the tests; and
      • (iv) records any recommendations made by the ATH on error compensation; and
      • (v) includes any manufacturer’s calibration test reports; and
    • (c) it produces a measuring transformer certification report that includes—
      • (i) the date on which it certified the measuring transformer; and
      • (ii) the certification validity period or expiry date for the measuring transformer which must be no more than 120 months from the date on which it was certified; and
      • (iii) the measuring transformer calibration report; and
      • (iv) whether the certification was based on batch test certificates; and
      • (v) if the certification was based on batch test certificates, confirmation that the manufacturer’s batch testing facility is, in the ATH’s opinion, of an acceptable standard; and
      • (vi) the range, including highest and lowest values, that the in-service burden must be within; and
    • (d) it confirms that it has inspected the manufacturer’s test certificates, and carried out any additional tests it considers necessary, to satisfy itself that the measuring transformer meets the accuracy requirements of this Part.

Clause 3(a): amended, on 19 December 2014, by clause 25(1) of the Electricity Industry Participation Code Amendment (Minor Code Amendments) (No 3) 2014.

Clause 3(b)(ii): amended, on 19 December 2014, by clause 25(2) of the Electricity Industry Participation Code Amendment (Minor Code Amendments) (No 3) 2014.

Clause 3(c)(ii): amended, on 1 April 2025, by clause 12 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2025.

Clause 3(c)(vi): inserted, on 1 February 2021, by clause 43 of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Control devices

4

Control device certification report

  • (1) An ATH must, before it certifies a new control device, produce a certification report that—
    • (a) confirms that the control device complies with the applicable standards listed in Table 5 of Schedule 10.1; and
    • (b) includes the details and results of any test that the ATH has carried out to confirm compliance under paragraph (a); and
    • (c) confirms that the control device has passed such tests.
  • (2) An ATH must, before it certifies an existing installed control device, produce a certification report that—
    • (a) confirms that the control device is fit for purpose; and
    • (b) confirms the control device certification validity period or expiry date that the ATH considers appropriate, which must be no more than 180 months from the date on which it was certified.

Clause 4: substituted, on 29 August 2013, by clause 47 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).

Clause 4(1)(b): amended, on 15 May 2014, by clause 20 of the Electricity Industry Participation (Minor Code Amendments) Code Amendment 2014.

Clause 4(2)(b): amended, on 1 April 2025, by clause 13 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2025.

Data storage devices

5

Data storage device certification requirements

  • (1) An ATH must, before it certifies a data storage device used for storing information that is used for the purposes of Part 15, ensure that—
    • (a) an approved test laboratory has—
      • (i) conducted type-testing that the ATH considers appropriate for the model and version of data storage device; and
      • (ii) produced a type-test certificate that—
        • (A) confirms the data storage device’s technical characteristics; and
        • (B) confirms the range of environmental conditions within which the data storage device has been proven accurate and reliable; and
        • (C) confirms that the data storage device performs the functions for which it was designed; and
        • (D) confirms that the data storage device complies with this Part; and
        • (E) records the tests undertaken by the approved test laboratory to confirm compliance under sub-subparagraph (D) and the reasons why the ATH considers that they are appropriate; and
    • (b) it produces a certification report that—
      • (i) confirms the data storage device complies with the applicable standards listed in Table 5 of Schedule 10.1; and
      • (ii) records the tests the ATH has performed to confirm compliance with subparagraph (i) and the results of those tests; and
      • (iii) confirms that the data storage device has passed the tests; and
      • (iv) includes the date on which it certified the data storage device; and
      • (v) includes the certification validity period or expiry date for the data storage device for each category of metering installation in which the data storage device may be used; and
      • (vi) records the maintenance requirements for the data storage device; and
      • (vii) confirms that each period of data is identifiable or deducible by both date and time on interrogation; and
      • (viii) confirms that the time and date of the following event conditions are recorded in an event log:
        • (A) a loss of the power supply to the data storage device; and
        • (B) critical internal alarms such as memory integrity checking, battery low, battery failed, and tampering; and
        • (C) phase failure to the meter, if the data storage device is integral to the meter; and
        • (D) any software configuration changes; and
        • (E) results of time setting comparisons and corrections; and
        • (F) the transition from, and to, New Zealand daylight time, if the data storage device operates in New Zealand daylight time; and
      • (ix) confirms that the data storage device has the available memory capacity required by the type-test; and
      • (x) confirms that the data storage device has the functionality—
        • (A) to validate instructions from an interrogation system; and
        • (B) for time comparisons and corrections, in response to a valid instruction; and
      • (xi) confirms that all information logged is referenced to New Zealand Standard Time or New Zealand daylight time; and
      • (xii) confirms that the data storage device has data loss protection providing a continued clock and memory operation for a continuous period of at least 15 days when the power supply to the data storage device is lost.
  • (2) The data storage device certification validity period referred to in subclause (1)(b)(v) must be—
    • (a) no more than 180 months, if the data storage device is a discrete metering component; or
    • (b) the same as the meter certification validity period, if the data storage device is integral to the meter.
  • (3) Despite subclause (1)(b)(ix), the memory capacity of the data storage device must not be less than 15 days.
  • (4) For the purposes of subclause (1), a new version of the data storage device includes any change to the specification, hardware, or metrology software of the data storage device.

Clause 5(1)(b)(v): amended, on 1 April 2025, by clause 14 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2025.

Wiring

6

Wiring

  • (1) An ATH must, before it certifies a metering installation, ensure that all wiring in the metering installation is—
    • (a) suitable for the environment in which the metering installation is located; and
    • (b) fit for purpose; and
    • (c) securely fastened; and
    • (d) compliant with all applicable requirements and enactments.
  • (2) An ATH must, before it certifies a metering installation, ensure that the wiring between metering components in the metering installation
    • (a) is run as directly as practicable; and
    • (b) is appropriately sized and protected; and
    • (c) does not, to the extent practicable, include intermediate joints for any measuring transformer circuits; and
    • (d) subject to subclause (4), includes conductors that are clearly and permanently identified, by the use of any 1 or more of the following:
      • (i) colour coding:
      • (ii) marker ferrules:
      • (iii) conductor numbering.
  • (3) For the purposes of subclause (2)(c), if it is not practicable to exclude intermediate joints for any measuring transformer circuits, the ATH must ensure that the intermediate joints are—
    • (a) sealed or in a sealed enclosure; and
    • (b) located in a secure position; and
    • (c) recorded in the metering installation certification report.
  • (4) The ATH must, if the wiring is in a metering installation and does not comply with subclause (2)(d)—
    • (a) ensure, by testing, that the wiring has been correctly installed; and
    • (b) record the nature of the test or the tests, and the results of the test or tests, in the metering installation certification report.

Fuses and circuit breakers

7

Fuses and circuit breakers

  • An ATH must, before it certifies a metering installation, ensure that all fuses and circuit breakers that are part of the metering installation are—
    • (a) appropriately rated for the electrical duty and discrimination required; and
    • (b) clearly labelled and—
      • (i) sealed; or
      • (ii) located in sealed enclosures.

Certification stickers

8

Metering component certification stickers

  • (1) An ATH must, when certifying a metering component under this Part, confirm the certification by attaching a metering component certification sticker to the metering component or, if not practicable, provide the sticker with the metering component.
  • (2) An ATH referred to in subclause (1) must ensure that a metering component certification sticker shows—
    • (a) the name of the metering component owner (if available); and
    • (b) if the metering component is a meter or a measuring transformer, the name of the ATH or the approved calibration laboratory who calibrated the metering component; and
    • (c) the name of the ATH who certified the metering component; and
    • (d) the date on which the metering component was certified; and
    • (e) the initials or other unique identifier of the person who carried out the certification of the metering component.
  • (3) An ATH must ensure that a certification sticker is—
    • (a) made of weather-proof material; and
    • (b) permanently attached; and
    • (c) filled out using permanent markings.
  • (4) If an ATH certifies the metering component on the same day it certifies the metering installation that the metering component is installed in, the ATH may combine the metering component certification sticker under subclause (1) and the metering installation certification sticker under clause 41 of Schedule 10.7 and attach it to the metering installation in accordance with clause 41 of Schedule 10.7.

Clause 8(4): inserted, on 1 February 2021, by clause 44 of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.

Onsite calibration and certification

9

Onsite calibration and certification

  • (1) A certifying ATH may only calibrate a metering component onsite—
    • (a) in the metering component’s normal working environment; and
    • (b) by—
      • (i) measuring the influence of all onsite variables and including their estimated effects in the uncertainty calculation; and
      • (ii) ensuring that—
        • (A) the effects of any departures from the reference conditions specified in the relevant standards listed in Table 5 of Schedule 10.1 can accurately and reliably be calculated; and
        • (B) the metering installation, in which the metering component is incorporated, is within the applicable accuracy tolerances set out in Table 1 of Schedule 10.1 after taking into account all known influences including temperature and temperature co-efficient measurements.
  • (2) If an ATH calibrates a metering component onsite using manual methods, computers, or automated equipment for the capture, processing, manipulation, recording, reporting, storage, or retrieval of calibration data, it must ensure that its computer software
    • (a) is documented in the ATH’s procedures; and
    • (b) can manipulate the variables that affect the performance of the metering component in a manner that will produce results that would correctly indicate the level of compliance of the metering component with this Code.
  • (3) An ATH who certifies a metering component onsite must include in the metering component certification report confirmation that—
    • (a) it has calculated the uncertainty of measurement taking into account all environmental factors for both the metering component being calibrated and the working standards; and
    • (b) the calculation of the uncertainty referred to in paragraph (a) comprises all uncertainties in the chain of calibration; and
    • (c) the ATH has used a calibration procedure to calibrate the metering component that—
      • (i) was included in the ATH’s most recent audit; and
      • (ii) is appropriate for onsite calibration; and
      • (iii) includes the methodologies, calculations, and assumptions used by the ATH in determining the uncertainty; and
    • (d) the ATH believes the methodologies, calculations, and assumptions are appropriate, including reasons for that belief.