Electricity Industry Participation Code 2010
Part 11: Registry information management
11.1
Contents of this Part
- This Part—
- (a) provides for the management of information in the registry; and
- (b) prescribes a process for switching ICPs between traders; and
- (ba) prescribes a period of protection for gaining retailers during which a losing retailer may not approach a customer to persuade the customer to stay with the losing retailer or to switch back to the losing retailer; and
- (bb) imposes restrictions on the use of customer information held by a losing retailer during a switch protected period; and
- (c) prescribes a process for a distributor to change the record in the registry of an ICP so that the ICP is recorded as being usually connected to an NSP in the distributor’s network; and
- (d) prescribes a process for switching responsibility for metering installations for ICPs between metering equipment providers; and
- (e) prescribes a process for dealing with trader events of default; and
- (f) requires retailers to give consumers information about their own consumption of electricity; and
- (g) requires retailers to give information about their generally available retail tariff plans to any person on request; and
- (h) prevents traders from electrically disconnecting an ICP within 25 days of the termination of an agreement with a retailer relating to the supply of electricity at that ICP.
Compare: Electricity Governance Rules 2003 rule 1 part E
Clause 11.1(a) and (c): amended, on 5 October 2017, by clause 194 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 11.1(b): amended, on 1 November 2018, by clause 33 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
Clause 11.1(ba) and (bb): inserted, on 31 March 2020, by clause 5 of the Electricity Industry Participation Code Amendment (Prohibition of Save and Win-Back Approaches by Losing Retailers During a Switch Protected Period) 2020.
Clause 11.1(c): amended, on 23 February 2015, by clause 75 of the Electricity Industry Participation Code Amendment (Distributed Generation) 2014.
Clause 11.1(d): inserted, on 29 August 2013, by clause 6 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011.
Clause 11.1(e): inserted, on 16 December 2013, by clause 5 of the Electricity Industry Participation (Managing Retailer Default Situations) Code Amendment 2013.
Clause 11.1(e): amended, on 28 February 2015, by clause 5 of the Electricity Industry Participation Code Amendment (Trader Default) 2014.
Clause 11.1(e): amended, on 1 February 2016, by clause 4(1) of the Electricity Industry Participation Code Amendment (Access to Retail Data) 2014.
Clause 11.1(f): inserted, on 1 February 2016, by clause 4(2) of the Electricity Industry Participation Code Amendment (Access to Retail Data) 2014.
Clause 11.1(f): amended, on 1 February 2016, by clause 5(1) of the Electricity Industry Participation Code Amendment (Access to Retail Tariff Information) 2015.
Clause 11.1(g): inserted, on 1 February 2016, by clause 5(2) of the Electricity Industry Participation Code Amendment (Access to Retail Tariff Information) 2015.
Clause 11.1(g): amended, on 15 May 2025, by clause 5(1) of the Electricity Industry Participation Code Amendment (Retailer Default) 2025.
Clause 11.1(h): inserted, on 15 May 2025, by clause 5(2) of the Electricity Industry Participation Code Amendment (Retailer Default) 2025.
11.2
Requirement to provide complete and accurate information
- (1) A participant must take all practicable steps to ensure that information that the participant is required to provide to any person under this Part (including customers) is—
- (a) complete and accurate; and
- (b) not misleading or deceptive; and
- (c) not likely to mislead or deceive.
- (2) If a participant becomes aware that the information the participant provided under this Part does not comply with subclause (1)(a) to (c), even if the participant has taken all practicable steps to ensure that the information complies, the participant must, as soon as practicable, provide such further information as is necessary to ensure that the information complies with subclause (1)(a) to (c).
Compare: Electricity Governance Rules 2003 rule 1A part E
Clause 11.2(1): amended, on 31 March 2020, by clause 6 of the Electricity Industry Participation Code Amendment (Prohibition of Save and Win-Back Approaches by Losing Retailers During a Switch Protected Period) 2020.
Clause 11.2(2): substituted, on 19 December 2014, by clause 26 of the Electricity Industry Participation Code Amendment (Minor Code Amendments) (No 3) 2014.
11.2A
Use of contractors
- (1) A participant may perform its obligations and exercise its rights under this Part by using a contractor.
- (2) A participant who uses a contractor to perform the participant’s obligation under this Part—
- (a) remains responsible and liable for, and is not released from the obligation or any other obligation under this Part; and
- (b) cannot assert that it is not responsible or liable for the obligation on the ground that the contractor—
- (i) has done or not done something; or
- (ii) has failed to meet a relevant standard; and
- (c) must ensure that the contractor has at least the specified level of skill, expertise, experience, or qualification that the participant would be required to have if it were performing the obligation itself.
- (3) If a participant is a party to a contract or arrangement containing a provision, or part of a provision, which is inconsistent with this Part, the provision, or part of the provision, has no effect.
Clause 11.2A: inserted, on 29 August 2013, by clause 7 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011.
11.3
Certain points of connection must have ICP identifiers
- (1) This clause applies to the following:
- (a) a trader who has agreed to purchase electricity from an embedded generator or sell electricity to a consumer:
- (b) an embedded generator who sells electricity directly to the clearing manager:
- (c) a direct purchaser connected to a local network or an embedded network:
- (d) an embedded network owner in relation to a point of connection on an embedded network that is settled by differencing:
- (e) a network owner in relation to a shared unmetered load point of connection to the network owner’s network:
- (f) a network owner in relation to a point of connection between the network owner’s network and an embedded network.
- (2) A participant to whom this clause applies must, before the participant assumes responsibility for a point of connection described in subclause (3) on a local network or embedded network, obtain an ICP identifier for the point of connection.
- (3) The points of connection for which ICP identifiers must be obtained under subclause (2) are points of connection at which any of the following occurs:
- (a) a consumer purchases electricity from a trader:
- (b) a trader purchases electricity from an embedded generator:
- (c) a direct purchaser purchases electricity from the clearing manager:
- (d) an embedded generator sells electricity directly to the clearing manager:
- (e) a network is settled by differencing:
- (f) there is a distributor status ICP—
- (i) at the point of connection between an embedded network and the distributor’s network; or
- (ii) at the point of connection of shared unmetered load.
Compare: Electricity Governance Rules 2003 rule 2 part E
Clause 11.3(1)(c): amended, on 23 February 2015, by clause 75 of the Electricity Industry Participation Code Amendment (Distributed Generation) 2014.
Clause 11.3(1)(c): amended, on 5 October 2017, by clause 195 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
11.4
Distributors must create ICP identifiers for ICPs
- (1) Each distributor must create an ICP identifier in accordance with clause 1 of Schedule 11.1 for each ICP on each network for which the distributor is responsible.
- (2) A distributor must create an ICP identifier for the point of connection at which an embedded network connects to the distributor’s network in accordance with subclause (1).
- (3) An ICP identifier for an ICP may not be changed.
Compare: Electricity Governance Rules 2003 rule 3 part E
11.5
Participants may request that distributors create ICP identifiers for ICPs
- (1) A participant to whom clause 11.3 applies may request that a distributor create an ICP identifier for an ICP on a network for which the distributor is responsible.
- (2) A participant that is a trader may make a request under subclause (1) only if the trader has,—
- (a) in the case of a trader to whom Schedule 12A.1 or Schedule 12A.3 of Part 12A applies, a distributor agreement with the distributor in accordance with clause 11.16; or
- (b) for all other traders, an arrangement with the distributor for distribution services in accordance with clause 11.6.
- (3) A distributor to whom a request is made must, within 3 business days of receiving the request, create a new ICP identifier for each ICP to which the request relates in accordance with clause 1 of Schedule 11.1, or advise the participant of the distributor’s reasons for not complying with the request.
Compare: Electricity Governance Rules 2003 rule 4 part E
Clause 11.5(2): amended, on 1 February 2016, by clause 39 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2015.
Clause 11.5(2): replaced, on 20 July 2020, by clause 5 of the Electricity Industry Participation Code Amendment (Default Distributor Agreement) 2020.
11.6
ICP status
- The participant specified in clause 12 of Schedule 11.1 must manage the status of an ICP in accordance with clause 12 of Schedule 11.1.
Compare: Electricity Governance Rules 2003 rule 5 part E
11.7
Provision of ICP information
- (1) A distributor whose network includes 1 or more ICPs must provide information about each of those ICPs to the registry manager in accordance with Schedule 11.1.
- (2) A trader must provide information about each ICP at which the trader trades electricity to the registry manager in accordance with Schedule 11.1.
Compare: Electricity Governance Rules 2003 rule 6 part E
Clause 11.7(1) and (2): amended, on 5 October 2017, by clause 196 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
11.8
Provision of and changes to ICP information and NSP information by participants
- (1) This clause applies if—
- (a) an NSP is to be created or decommissioned; or
- (b) a distributor wishes to change the record in the registry of an ICP that is not recorded as being usually connected to an NSP in the distributor’s network, so that the ICP is recorded as being usually connected to an NSP in the distributor’s network.
- (2) The participant specified in clause 25(3) of Schedule 11.1 must give the notice required by clause 25(1) of Schedule 11.1.
- (3) A distributor to whom subclause (1)(b) applies must comply with clause 25(2) of Schedule 11.1.
- (4) The participants specified in clauses 25 to 27 of Schedule 11.1 must comply with those clauses.
- (5) If a network owner acquires all or part of an existing network, the network owner must give the notice required by clause 29 of Schedule 11.1.
Compare: Electricity Governance Rules 2003 rule 8 part E
Clause 11.8(1)(a) and (b): amended, on 5 October 2017, by clause 197 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 11.8(1)(b): amended, on 23 February 2015, by clause 75 of the Electricity Industry Participation Code Amendment (Distributed Generation) 2014.
Clause 11.8(1)(b): amended, on 20 December 2021, by clause 34 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
Clause 11.8(2) and (5): amended, on 1 November 2018, by clause 34 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
11.8A
Metering equipment providers to provide registry metering records to registry manager
- (1) A metering equipment provider must, for each metering installation described in subclause (2) for which it is responsible,—
- (a) provide to the registry manager the registry metering records for the metering installation in the prescribed form; and
- (b) update the registry metering records in accordance with Schedule 11.4.
- (2) Subclause (1) applies to a metering installation that is—
- (a) a category 1 metering installation, or higher category of metering installation; and
- (b) for an ICP that is not also an NSP.
Clause 11.8A Heading: amended, on 5 October 2017, by clause 198(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 11.8A: inserted, on 29 August 2013, by clause 8 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011.
Clause 11.8A(1)(a): amended, on 5 October 2017, by clause 198(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
11.8B
Metering equipment providers to arrange for regular audits
- Each metering equipment provider must arrange to be audited regularly in accordance with Part 16A in respect of the metering equipment provider's obligations under this Part.
Clause 11.8B: inserted, on 29 August 2013, by clause 8 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011.
Clause 11.8B: replaced, on 1 June 2017, by clause 18 of the Electricity Industry Participation Code Amendment (Requirements and Processes for Audits) 2016.
11.9
[Revoked]
Compare: Electricity Governance Rules 2003 rule 8 part E
Clause 11.9: revoked, on 29 August 2013, by clause 9 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011.
11.10
Distributors to arrange for regular audits
- Each distributor must arrange to be audited regularly in accordance with Part 16A in respect of the distributor’s obligations under this Part.
Compare: Electricity Governance Rules 2003 rule 10 part E
Clause 11.10(1)(c): substituted, on 29 August 2013, by clause 5(1) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2013.
Clause 11.10(1A): inserted, on 29 August 2013, by clause 5(2) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2013.
Clause 11.10: replaced, on 1 June 2017, by clause 19 of the Electricity Industry Participation Code Amendment (Requirements and Processes for Audits) 2016.
11.11
Authority and participant requested audits
- (1) The Authority may at any time carry out, or appoint an auditor to carry out, an audit of a participant in respect of the participant's obligations under this Part.
- (2) If a participant considers that another participant may not have complied with this Part, the participant may request that the Authority carry out, or appoint an auditor to carry out, an audit of the other participant.
- (3) Part 16A applies to an audit carried out under this clause.
Compare: Electricity Governance Rules 2003 rule 10A part E
Clause 11.11: replaced, on 1 June 2017, by clause 20 of the Electricity Industry Participation Code Amendment (Requirements and Processes for Audits) 2016.
11.12
[Revoked]
Compare: Electricity Governance Rules 2003 rule 10B part E
Clause 11.12: revoked, on 1 June 2017, by clause 21 of the Electricity Industry Participation Code Amendment (Requirements and Processes for Audits) 2016.
11.13
[Revoked]
Compare: Electricity Governance Rules 2003 rule 10C part E
Clause 11.13: revoked, on 1 June 2017, by clause 22 of the Electricity Industry Participation Code Amendment (Requirements and Processes for Audits) 2016.
11.14
Process for maintaining shared unmetered load
- (1) This clause applies if shared unmetered load is connected to a distributor’s network.
- (2) The distributor must give written notice to the registry manager, and each trader responsible under clause 11.18(1) for the ICPs across which the unmetered load is shared, of the ICP identifiers of those ICPs.
- (3) A trader who receives written notice under subclause (2) must give written notice to the distributor if it wishes to add an ICP to or omit an ICP from the ICPs across which the unmetered load is shared.
- (3A) A trader giving notice under subclause (3) must give a notice to add or omit an ICP only to—
- (a) add an ICP if the consumer at the ICP benefits from the shared unmetered load; or
- (b) omit an ICP if the consumer at the ICP no longer receives benefit from the shared unmetered load.
- (4) A distributor who receives written notice under subclause (3) must give written notice to the registry manager and each trader responsible for any of the ICPs across which the unmetered load is shared of the addition or omission of the ICP.
- (5) If a distributor becomes aware of a change to the capacity of an ICP across which the unmetered load is shared or that an ICP across which the unmetered load is shared is decommissioned, it must give written notice to all traders who receive written notice under subclause (2) of the change or decommissioning as soon as practicable after the change or decommissioning.
- (6) A trader who receives written notice under subclause (5) must, as soon as practicable after receiving the written notice, adjust the unmetered load information for each ICP for which it is responsible, so that the unmetered load is shared equally across each of those ICPs.
- (7) A trader must take responsibility for shared unmetered load assigned to an ICP for which the trader becomes responsible as a result of a switch in accordance with this Part.
- (8) A trader must not relinquish responsibility for shared unmetered load assigned to an ICP if there would then be no ICPs left across which the load could be shared.
- (9) A trader who changes the status of an ICP across which the unmetered load is shared to inactive in accordance with clause 19 of Schedule 11.1 is not required to give written notice to the distributor of the change under subclause (3). The amount of electricity attributable to that ICP becomes UFE.
Compare: Electricity Governance Rules 2003 rule 14 part E
Clause 11.14(1): amended, on 23 February 2015, by clause 75 of the Electricity Industry Participation Code Amendment (Distributed Generation) 2014.
Clause 11.14(1), (2), (3), (4), (5) and (9): amended, on 5 October 2017, by clause 199 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 11.14(3), (4), (5) and (6): amended, on 1 November 2018, by clause 35 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
Clause 11.14(3A): inserted, on 1 March 2024, by clause 43 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2024.
11.15
Process for customer or embedded generator switching
- (1) This clause applies if a trader (“the gaining trader”) has an arrangement with a customer or embedded generator to—
- (a) commence trading electricity with the customer or embedded generator at an ICP at which another trader (“the losing trader”) trades electricity with the customer or embedded generator; or
- (b) assume responsibility under clause 11.18(1) for such an ICP.
- (2) The gaining trader and the losing trader must comply with Schedule 11.3.
Compare: Electricity Governance Rules 2003 rule 15 part E
Clause 11.15(1): amended, on 1 November 2018, by clause 36 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
11.15AA
Restrictions during switch protected period
- A losing retailer must not, by any means, including by using a third party or agent acting on its behalf, contact any customer who is switching from the losing retailer to a gaining retailer to attempt to persuade the customer to terminate the arrangement with the gaining retailer during the switch protected period, including by –
- (a) making a counter-offer to the customer; or
- (b) offering an enticement to the customer.
Clause 11.15AA: inserted, on 12 January 2015, by clause 4 of the Electricity Industry Participation Code Amendment (Switch Saving Protection) 2014.
Clause 11.15AA(2) and (3): amended, on 5 October 2017, by clause 200 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 11.15AA: replaced, on 31 March 2020, by clause 7 of the Electricity Industry Participation Code Amendment (Prohibition of Save and Win-Back Approaches by Losing Retailers During a Switch Protected Period) 2020.
11.15AB
Retailer may communicate with customers for certain purposes
- (1) Despite clause 11.15AA, a losing retailer may contact a customer who is switching to a gaining retailer for any or all of the following purposes -
- (a) to contact the customer to advise the customer of any termination fees that the customer is required to pay as a result of the customer ceasing to trade with the losing retailer; or
- (b) to contact a customer regarding administrative matters, including –
- (i) any fees the customer owes the losing retailer:
- (ii) the customer’s final meter reading:
- (iii) how the losing retailer will return any keys it holds on the customer’s behalf:
- (iv) the effect of the customer ceasing to buy electricity from the losing retailer on other contracts between the customer and the losing retailer, for example, for the supply of gas; or
- (c) to provide a factual response to a question asked by a customer; or
- (d) to make a counter-offer or offer an enticement to a customer where the customer has:
- (i) contacted the losing retailer without the losing retailer having first prompted the customer to do so; and
- (ii) invited the losing retailer to attempt to persuade the customer not to complete the switch to the gaining retailer but to remain with or return to the losing retailer instead; or
- (e) to offer an enticement to a customer as part of a general marketing campaign: or
- (f) to contact the customer to address network fault issues or to follow up customer complaints.
- (2) If a losing retailer contacts a customer under subclause (1), the losing retailer must not communicate with the customer for any other purpose other than a purpose specified in subclause (1).
- (3) Without limiting any of its other obligations, a retailer (whether a gaining retailer or a losing retailer) must not harass or coerce a customer.
Clause 11.15AB: inserted, on 12 January 2015, by clause 4 of the Electricity Industry Participation Code Amendment (Switch Saving Protection) 2014.
Clause 11.15AB(2), (3) and (4): amended, on 1 November 2018, by clause 37 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
Clause 11.15AB: replaced, on 31 March 2020, by clause 8 of the Electricity Industry Participation Code Amendment (Prohibition of Save and Win-Back Approaches by Losing Retailers During a Switch Protected Period) 2020.
11.15AC
Restrictions on use of customer information by retailer prior to or during switch protected period
- (1) A losing retailer must not use information relating to a customer that it obtained prior to or during the switch protected period, including information that may be used to contact the customer, during the switch protected period to do any of the following:
- (a) contact the customer for any purpose other than a purpose specified in clause 11.15AB;
- (b) include the customer in a marketing campaign other than a general marketing campaign; or
- (c) enable any other retailer, except the gaining retailer, to contact the customer.
- (2) This clause does not limit any other requirement to maintain the confidentiality of any information relating to a customer that is imposed by the contract entered into between the losing retailer and the customer or otherwise by law.
Clause 11.15AC: inserted, on 12 January 2015, by clause 4 of the Electricity Industry Participation Code Amendment (Switch Saving Protection) 2014.
Clause 11.15AC: amended, on 1 November 2018, by clause 38 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
Clause 11.15AC: replaced, on 31 March 2020, by clause 9 of the Electricity Industry Participation Code Amendment (Prohibition of Save and Win-Back Approaches by Losing Retailers During a Switch Protected Period) 2020.
11.15AD
[Revoked]
Clause 11.15AD: inserted, on 12 January 2015, by clause 4 of the Electricity Industry Participation Code Amendment (Switch Saving Protection) 2014.
Clause 11.15AD: revoked, on 31 March 2020, by clause 10 of the Electricity Industry Participation Code Amendment (Prohibition of Save and Win-Back Approaches by Losing Retailers During a Switch Protected Period) 2020.
11.15A
Application of Schedule 11.4
- The following parties must comply with Schedule 11.4:
- (a) a trader that gives written notice to the registry manager of the gaining metering equipment provider responsible for each metering installation for an ICP:
- (b) the registry manager:
- (c) the gaining metering equipment provider.
Clause 11.15A: inserted, on 29 August 2013, by clause 10 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011.
Clause 11.15A(a) and (b): amended, on 5 October 2017, by clause 201 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
11.15B
Trader and retailer contracts with customers to permit assignment by Authority
- (1) Each trader or retailer must at all times ensure that the terms of each contract under which a customer of the trader or retailer purchases electricity from the trader or retailer permit—
- (a) the Authority to:
- (i) assign the rights and obligations of the trader under the contract to another trader if the trader commits an event of default under paragraph (a), (b), (f), (h) or (i) of clause 14.41(1); or
- (ii) assign the rights and obligations of the retailer under the contract to a trader if the retailer commits an event of default under paragraph (j) of clause 14.41(l); and
- (b) the terms of the assigned contract to be amended on such an assignment to—
- (i) the standard terms that the recipient trader would normally have offered to the customer immediately before the event of default occurred; or
- (ii) such other terms that are more advantageous to the customer than the standard terms, as the recipient trader and the Authority agree; and
- (c) the terms of the assigned contract to be amended on such an assignment to include a minimum term in respect of which the customer must pay an amount for cancelling the contract before the expiry of the minimum term; and
- (d) the trader or retailer to provide information about the customer to the Authority and for the Authority to provide the information provided by:
- (i) the trader to another trader if required under Schedule 11.5; or
- (ii) the retailer to a trader if required under Schedule 11.5; and
- (e) the:
- (i) trader to assign the rights and obligations of the trader to another trader; or
- (ii) retailer to assign the rights and obligations of the retailer to a trader.
- (a) the Authority to:
- (2) The terms specified in subclause (1) must—
- (a) be expressed to be for the benefit of the Authority for the purposes of subpart 1 of Part 2 of the Contract and Commercial Law Act 2017; and
- (b) not be able to be amended without the consent of the Authority.
- (3) [Revoked]
Clause 11.15B: inserted, on 16 December 2013, by clause 6 of the Electricity Industry Participation (Managing Retailer Default Situations) Code Amendment 2013.
Heading clause 11.15B: amended, on 28 February 2015, by clause 6(1) of the Electricity Industry Participation Code Amendment (Trader Default) 2014.
Heading clause 11.15B: amended, on 15 May 2025, by clause 6(1) of the Electricity Industry Participation Code Amendment (Retailer Default) 2025.
Clause 11.15B(1): amended, on 28 February 2015, by clause 6(2)(a) of the Electricity Industry Participation Code Amendment (Trader Default) 2014.
Clause 11.15B(1): amended, on 1 November 2018, by clause 39(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
Clause 11.15B(1): amended, on 15 May 2025, by clause 6(2) of the Electricity Industry Participation Code Amendment (Retailer Default) 2025.
Clause 11.15B(1)(a): amended, on 28 February 2015, by clause 6(2)(b) of the Electricity Industry Participation Code Amendment (Trader Default) 2014.
Clause 11.15B(1)(a): amended, on 1 February 2016, by clause 40 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2015.
Clause 11.15B(1)(a): amended, on 5 October 2017, by clause 202 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 11.15B(1)(a): amended, on 15 May 2025, by clause 6(3) of the Electricity Industry Participation Code Amendment (Retailer Default) 2025.
Clause 11.15B(1)(d): amended, on 15 May 2025, by clause 6(4) of the Electricity Industry Participation Code Amendment (Retailer Default) 2025.
Clause 11.15B(1)(e): amended, on 15 May 2025, by clause 6(5) of the Electricity Industry Participation Code Amendment (Retailer Default) 2025.
Clause 11.15B(2)(a): amended, on 1 November 2018, by clause 39(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
Clause 11.15B(3): revoked, on 28 August 2015, by clause 6(3) of the Electricity Industry Participation Code Amendment (Trader Default) 2014.
11.15C
Process for trader or retailer events of default
- (1) This clause applies if the Authority is satisfied that a trader has committed an event of default under paragraph (a), (b), (f), (h) or (i) of clause 14.41(1).
- (1A) This clause applies if the Authority is satisfied that a retailer has committed an event of default under paragraph (j) of clause 14.41(1).
- (2) The Authority and each participant must comply with Schedule 11.5.
- (3) This clause ceases to apply, and the Authority and each participant must cease to comply with Schedule 11.5, if the Authority is advised under clause 14.41(2), 14.41(3), 14.43(3B), or 14.43(4A) that the relevant participant considers that the event of default has been remedied.
Clause 11.15C: inserted, on 16 December 2013, by clause 6 of the Electricity Industry Participation (Managing Retailer Default Situations) Code Amendment 2013.
Heading, clause 11.15C: amended, on 28 February 2015, by clause 7(1) of the Electricity Industry Participation Code Amendment (Trader Default) 2014.
Heading, clause 11.15C: amended, on 15 May 2025, by clause 7(1) of the Electricity Industry Participation Code Amendment (Retailer Default) 2025.
Clause 11.15C(1): amended, on 28 February 2015, by clause 7(2) of the Electricity Industry Participation Code Amendment (Trader Default) 2014.
Clause 11.15C(1): amended, on 24 March 2015, by clause 5 of the Electricity Industry Participation Code Amendment (Settlement and Prudential Security) 2014.
Clause 11.15C(1): amended, on 20 December 2021, by clause 35 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
Clause 11.15C(1): amended, on 1 July 2025, by clause 16 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2025.
Clause 11.15C(1A): inserted, on 15 May 2025, by clause 7(2) of the Electricity Industry Participation Code Amendment (Retailer Default) 2025.
Clause 11.15C(2): amended, on 15 May 2014, by clause 21 of the Electricity Industry Participation (Minor Code Amendments) Code Amendment 2014.
Clause 11.15C(3): inserted, on 1 February 2016, by clause 41 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2015.
Clause 11.15C(3): amended, on 15 May 2025, by clause 7(3) of the Electricity Industry Participation Code Amendment (Retailer Default) 2025.
11.16
Trader to ensure arrangements for distribution services and metering
- Before providing the registry manager with information in accordance with clause 11.7(2) or clause 11.18(4), a trader must have—
- (a) either,—
- (i) if the trader is a trader to whom Schedule 12A.1 or Schedule 12A.3 of Part 12A applies, a distributor agreement with the distributor on whose network the ICP is located; or
- (ii) in all other cases, entered into an arrangement for the provision of distribution services in relation to the ICP with the distributor; and
- (b) entered into an arrangement with a metering equipment provider to be responsible for each metering installation for the ICP.
- (a) either,—
Compare: Electricity Governance Rules 2003 rule 15 part E
Clause 11.16: substituted, on 29 August 2013, by clause 11 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011.
Clause 11.16: amended, on 5 October 2017, by clause 203 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 11.16: replaced, on 20 July 2020, by clause 6 of the Electricity Industry Participation Code Amendment (Default Distributor Agreement) 2020.
Clause 11.16(a): amended, on 1 February 2016, by clause 42 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2015.
Clause 11.16(a): amended, on 1 November 2018, by clause 40 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
11.17
Connecting ICP that is not also NSP
- (1A) A distributor must, when connecting an ICP that is not also an NSP, follow the connection process set out in clause 10.31.
- (1) A distributor must not connect an ICP across which unmetered load is shared unless a trader is recorded in the registry as accepting responsibility for the shared unmetered load.
- (2) A distributor must not connect an ICP of any other kind unless a trader is recorded in the registry as accepting responsibility for the ICP.
- (3) Subclause (2) does not apply to an ICP that is—
- (a) the point of connection between a network and an embedded network; or
- (b) the point of connection of shared unmetered load.
Compare: Electricity Governance Rules 2003 rule 17 part E
Clause 11.17: heading amended, on 29 August 2013, by clause 12(1) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011.
Clause 11.17: heading amended, on 29 August 2013, by clause 5 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).
Clause 11.17 Heading: amended, on 5 October 2017, by clause 204(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 11.17(1A): inserted, on 29 August 2013, by clause 12 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011.
Clause 11.17(1A): substituted, on 29 August 2013, by clause 5 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011 Amendment 2013 (No 2).
Clause 11.17(1A), (1) and (2): amended, on 23 February 2015, by clause 75 of the Electricity Industry Participation Code Amendment (Distributed Generation) 2014.
Clause 11.17(1A), (1) and (2): amended, on 5 October 2017, by clause 204(2) and (3) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
11.18
Trader responsibility for ICP
- (1) If a trader is recorded in the registry as accepting responsibility for an ICP identifier that is not also an NSP, the trader is responsible for all obligations in this Part that—
- (a) apply to traders; and
- (b) relate to an ICP that is not also an NSP.
- (2) A trader ceases to be responsible for obligations in this Part relating to an ICP that is not also an NSP if―
- (a) another trader is recorded in the registry as being responsible for the ICP identifier; or
- (b) the ICP is decommissioned in accordance with clause 20 of Schedule 11.1.
- (3) If an ICP is to be decommissioned, the trader who is responsible for the ICP identifier must―
- (a) arrange for a final interrogation to take place before or on removal of the meter; and
- (b) advise the metering equipment provider responsible for each metering installation for the ICP that it is to be decommissioned.
- (4) A trader who is responsible for an ICP identifier, other than an ICP at which there is only unmetered load, must ensure that a metering equipment provider is recorded in the registry as being responsible for each metering installation for the ICP.
- (5) The trader must not trade at an ICP if a metering equipment provider is not recorded in the registry as being responsible for each metering installation for the ICP, unless the trader trades only unmetered load at that ICP.
Compare: Electricity Governance Rules 2003 rule 17 part E
Clause 11.18: substituted, on 29 August 2013, by clause 13 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011.
Clause 11.18(5): amended, on 15 May 2014, by clause 22 of the Electricity Industry Participation (Minor Code Amendments) Code Amendment 2014.
Clause 11.18(1): amended, on 31 October 2023, by clause 4(1) of the Electricity Industry Participation Code Amendment (Clarification of Trader Obligations) 2023.
Clause 11.18(2): amended, on 31 October 2023, by clause 4(2) of the Electricity Industry Participation Code Amendment (Clarification of Trader Obligations) 2023.
Clause 11.18(3): amended, on 31 October 2023, by clause 4(3) of the Electricity Industry Participation Code Amendment (Clarification of Trader Obligations) 2023.
Clause 11.18(4): amended, on 31 October 2023, by clause 4(4) of the Electricity Industry Participation Code Amendment (Clarification of Trader Obligations) 2023.
11.18A
Registry manager to advise metering equipment providers
- The registry manager must, within 1 business day of being advised by a trader of a metering equipment provider’s participant identifier for an ICP identifier, —
- (a) if there is not already a metering equipment provider assigned to the ICP identifier, advise the gaining metering equipment provider that the registry manager has been advised that it is the gaining metering equipment provider for each metering installation for the ICP; or
- (b) if there is a losing metering equipment provider, advise both the gaining metering equipment provider and the losing metering equipment provider of the advice.
Clause 11.8A Heading: amended, on 5 October 2017, by clause 205(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 11.18A: inserted, on 29 August 2013, by clause 13 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011.
Clause 11.18A: amended, on 5 October 2017, by clause 205(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
11.18B
Metering equipment provider responsibility for metering installation for ICP
- (1) This clause applies to a metering equipment provider who assumes responsibility, or is appointed to be responsible, as the metering equipment provider for an ICP.
- (2) The obligations under this Part, of a metering equipment provider to whom this clause applies,—
- (a) commence at the same time as the metering equipment provider's obligations under clause 10.21(1):
- (b) terminate when the metering equipment provider's obligations under Part 10 terminate under clause 10.23.
- (3) [Revoked]
Clause 11.18B: inserted, on 29 August 2013, by clause 13 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011.
Clause 11.18B(3): revoked, on 1 November 2018, by clause 41 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
11.19
Authority to specify timeframes and formats of information
- (1) Subject to subclause (3), subclause (2) applies if a participant is required to provide information under this Part, but this Code does not specify any 1 or more of the following:
- (a) the time by which, or the period within which, the information must be provided:
- (b) the format in which the information must be provided:
- (c) the method by which the information must be provided.
- (2) The participant must provide the information in accordance with requirements as to those matters specified by the Authority.
- (3) Unless otherwise specified in this Part, information or notices that must be provided under this Part by the registry manager or to the registry manager, must be provided using the registry.
Compare: Electricity Governance Rules 2003 rule 20 part E
Clause 11.19(1): amended, on 5 October 2017, by clause 206(a) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 11.19(3): inserted, on 5 October 2017, by clause 206(b) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
11.20
Registry must be available between 0730 and 1930 each day
- (1) The registry manager must ensure that the registry is available to receive and provide information under this Part between 0730 hours and 1930 hours each day.
- (2) Information provided to the registry manager after 1930 hours is deemed to be provided at 0730 the next day.
Compare: Electricity Governance Rules 2003 rule 21 part E
Clause 11.20 Heading: amended, on 5 October 2017, by clause 207(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 11.20: amended, on 5 October 2017, by clause 207(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
11.21
Confirmation of receipt of data
- (1) Information provided to the registry manager is deemed, for the purposes of this Part, not to have been received until the registry manager has confirmed receipt in accordance with this clause.
- (2) The registry manager must confirm receipt of information received by it in accordance with this Part within 4 hours of the information being provided to it.
- (3) In determining whether the registry manager has confirmed receipt within the time specified in subclause (2), no account is to be taken of any period during which the registry is not required to be available under clause 11.20.
- (4) If the participant providing the information does not receive confirmation that the registry manager has received the participant's information, the participant must contact the registry manager to check whether the registry manager has received the information.
- (5) If the registry manager has not received the information, the participant must re-send the information. This process must be repeated until the registry manager has confirmed receipt of the information in accordance with this clause.
Compare: Electricity Governance Rules 2003 rules 22.1 and 22.2 part E
Clause 11.21(1), (2), (4) and (5): amended, on 5 October 2017, by clause 208(1) and (3) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 11.21(3): replaced, on 5 October 2017, by clause 208(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
11.22
Registry manager must maintain register of information
- (1) The registry manager must maintain a register of information received by it and updated in accordance with this Code.
- (2) The registry manager must ensure that a complete audit trail exists for all information received by it in accordance with this Code.
Compare: Electricity Governance Rules 2003 rule 22.3 part E
Clause 11.22 Heading: amended, on 5 October 2017, by clause 209(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 11.22: amended, on 5 October 2017, by clause 209(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 11.22(2): amended, on 1 November 2018, by clause 42 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
11.23
Reports from registry manager
- By 1600 hours on the 6th business day of each reconciliation period, the registry manager must publish a report containing the following information:
- (a) the number of ICPs in the registry at the end of the immediately preceding consumption period:
- (b) the number of notifications received by the registry manager in accordance with clause 2 of Schedule 11.3 during the previous reconciliation period:
- (c) such other information as may be agreed from time to time between the registry manager and the Authority.
Compare: Electricity Governance Rules 2003 rule 23 part E
Clause 11.23 Heading: amended, on 5 October 2017, by clause 210(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 11.23: amended, on 5 October 2017, by clause 210(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 11.23(a): amended, on 1 November 2018, by clause 43 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
11.24
Registry manager delivers reports to specific participants
- The registry manager must deliver the reports specified in clauses 11.25 to 11.27 in the manner specified in those clauses.
Compare: Electricity Governance Rules 2003 rule 24.1A part E
Clause 11.24 Heading: amended, on 5 October 2017, by clause 211(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 11.24: amended, on 5 October 2017, by clause 211(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
11.25
Reports to clearing manager, system operator or reconciliation manager
- (1) The clearing manager, or the system operator, or the reconciliation manager may request in writing, no later than 5 business days before the last day of the month before the 1st month for which the report is requested, a report that includes any or all of the following information:
- (a) all active NSPs connected to a local network during the immediately preceding 14 calendar months:
- (b) all active NSPs connected to a network for which a trader is, and has over the immediately preceding 14 calendar months been, responsible:
- (c) the dates on which each trader’s responsibility under this Code at an NSP commenced and ceased.
- (2) The system operator may at any time request, in writing, a report that sets out every switch made under clauses 2, 9 or 14 of Schedule 11.3, the effect of which is that a trader has commenced trading at an NSP or a trader has ceased trading at an NSP.
- (3) A request made under subclauses (1) or (2) may—
- (a) be a one-off request; or
- (b) specify a frequency over a particular period; or
- (c) specify a frequency over an indefinite period until terminated by the requesting person.
- (4) If the request is received by the time specified in this clause, the registry manager must provide the report by 1000 hours on the 1st business day of the month following the month in which the request was made, or if the request for the report specifies a later date, by the later date.
- (5) The person who requested the report may vary any of the details set out in the request, by giving notice to the registry manager of the relevant details in writing by no later than 5 business days before the last day of the month before the 1st month for which the person requests the variation.
- (6) The registry manager must comply with a request made in accordance with subclause (5) by 1000 hours on the 1st business day of the month following the month in which the request was made.
Compare: Electricity Governance Rules 2003 rule 24.1 part E
Clause 11.25 Heading: amended, on 5 October 2017, by clause 212(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 11.25(1)(a) and (b): amended, on 23 February 2015, by clause 75 of the Electricity Industry Participation Code Amendment (Distributed Generation) 2014.
Clause 11.25(1), (4), (5) and (6): amended, on 5 October 2017, by clause 212(2) to (4) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 11.25(5): amended, on 1 November 2018, by clause 44 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
11.26
Reports to reconciliation manager
- By 1600 hours on the 4th business day of each calendar month, in respect of the immediately preceding consumption period, and by 1600 hours on the 13th business day of each calendar month in respect of the immediately preceding 14 consumption periods, the registry manager must deliver the following reports to the reconciliation manager:
- (a) a report identifying the number of ICP days per NSP, differentiated by half-hour metering type or non half-hour metering type (for the purpose of this clause, half-hour metering type on the registry must be reported as half hour, and all other metering types must be reported as non half hour) attributable to each trader for those NSPs that are recorded on the registry as consuming electricity at any time during, as the case may be, that consumption period or any of those consumption periods:
- (b) a report detailing the loss factor values for each loss category code recorded in the registry in respect of all trading periods:
- (c) a report detailing the balancing area to which each NSP belongs recorded in the registry in respect of all trading periods (including any changes during that month):
- (d) a report detailing the half hour ICP identifiers and the NSPs to which they are assigned for each individual trader (including any changes during that month):
- (e) a report that sets out every switch made under clauses 2, 9 or 14 of Schedule 11.3, the effect of which is that a trader has commenced trading at an NSP or a trader has ceased trading at an NSP.
Compare: Electricity Governance Rules 2003 rule 24.2 part E
Clause 11.26 Heading: amended, on 5 October 2017, by clause 213(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 11.26: amended, on 5 October 2017, by clause 213(2) and (3) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
11.27
Reports to Authority
- By 1600 hours on the 1st business day of each calendar month, the registry manager must deliver to the Authority a report summarising the number of events—
- (a) that a participant has not notified to the registry manager within the timeframes specified in this Part; and
- (b) of which the registry manager is aware, despite the participant not having notified the registry manager.
Compare: Electricity Governance Rules 2003 rule 24.3 part E
Clause 11.27 Heading: amended, on 5 October 2017, by clause 214(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 11.27: amended, on 5 October 2017, by clause 214(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 11.27: amended, on 1 November 2018, by clause 45 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
11.28
Access to registry
- (1) A participant that requires access to the registry must apply to the Authority to have access to the registry.
- (1A) The Authority must specify and publish the terms and conditions that apply to participants that are granted access to the registry.
- (1B) For the avoidance of doubt, the terms and conditions specified and published by the Authority for access to the registry as at 18 April 2019–
- (a) are the terms and conditions for the purposes of subclause (1A); and
- (b) apply to a participant that has access to the registry as at 18 April 2019.
- (2) If the Authority grants a participant's application,—
- (a) the registry manager must provide the participant with access to the registry in accordance with the terms and conditions specified and published by the Authority under subclause (1A):
- (b) the participant must comply with the terms and conditions specified and published by the Authority under subclause (1A), including any amendments under subclause (2A):
- (c) the Authority may restrict or suspend a participant's access to the registry if the participant does not comply with those terms and conditions, even though such a restriction or suspension may affect a participant's ability to meet its obligations under this Code.
- (2A) The Authority may, from time to time, specify and publish amendments to the terms and conditions under which the Authority grants access to the registry. Such amendments will apply—
- (a) to those participants the Authority has already granted access to the registry; and
- (b) to future applications for access to the registry.
- (3) The Authority must consult with the participants referred to in subclause (2A)(a) on any proposed amendments to the terms and conditions specified and published by the Authority under subclause (1A).
- (4) If the Authority grants a participant access to information in the registry, and the participant requests a report, the registry manager must provide the report to the participant within 4 hours of receiving the request.
- (5) In determining whether the registry manager has provided the report within the time specified in subclause (4), no account is to be taken of any period during which the registry is not required to be available under clause 11.20.
Compare: Electricity Governance Rules 2003 rule 25 part E
Clause 11.28(1): replaced, on 18 April 2019, by clause 4(1) of the Electricity Industry Participation Code Amendment (Terms and Conditions for Access to Registry and WITS) 2019.
Clause 11.28(1A) and (1B): inserted, on 18 April 2019, by clause 4(2) of the Electricity Industry Participation Code Amendment (Terms and Conditions for Access to Registry and WITS) 2019.
Clause 11.28(2): replaced, on 18 April 2019, by clause 4(3) of the Electricity Industry Participation Code Amendment (Terms and Conditions for Access to Registry and WITS) 2019.
Clause 11.28(1), (2), (3) and (5): amended, on 5 October 2017, by clause 215(1) to (3) and (5) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 11.28(2A): inserted, on 29 August 2013, by clause 14(2) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011.
Clause 11.28(2A): replaced, on 18 April 2019, by clause 4(4) of the Electricity Industry Participation Code Amendment (Terms and Conditions for Access to Registry and WITS) 2019.
Clause 11.28(3): replaced, on 18 April 2019, by clause 4(5) of the Electricity Industry Participation Code Amendment (Terms and Conditions for Access to Registry and WITS) 2019.
Clause 11.28(4): replaced, on 5 October 2017, by clause 215(4) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
11.29
Registry information change
- If a change to registry information is provided in accordance with clause 11.7, the registry manager must, within 1 business day of receiving the information, advise affected participants of the change.
Compare: Electricity Governance Rules 2003 rule 26 part E
Clause 11.29: substituted, on 29 August 2013, by clause 15 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011.
Clause 11.29: amended, on 5 October 2017, by clause 216 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
11.30
Use of ICP identifier on invoices
- Each trader must ensure that the relevant ICP identifier is printed on every invoice or associated document relating to the sale of electricity rendered by the trader, and that the ICP identifier is clearly labelled "ICP" on the invoice.
Compare: Electricity Governance Rules 2003 rule 27 part E
11.30A
Provision of information on dispute resolution scheme
- (1) Each retailer and distributor must provide information in the circumstances specified in subclauses (2) and (3) about the dispute resolution scheme identified under clause 3 of Schedule 4 of the Act.
- (2) The information required by subclause (1) must be clearly and prominently published on any website that—
- (a) is maintained by, or on behalf of, the retailer or distributor; and
- (b) deals with, describes or offers the supply of electricity or line function services by the retailer or distributor, or by an agent or related entity of the retailer or the distributor.
- (3) The information required by subclause (1) must also be clearly and prominently provided—
- (a) as part of or accompanying any communication personalised for a specific named consumer (whether in print, electronic or other medium) from the retailer or distributor, or by an agent or related entity of the retailer or distributor, about—
- (i) billing or charges to, or payments owed by or made by, the consumer for the supply of electricity or line function services, including any invoice, request for payment or statement of account; or
- (ii) the terms and conditions for the supply of electricity or line function services to the consumer, including the prices, tariffs, energy plan, price plan, tariff plan and terms of service for the consumer; and
- (b) in association with or in the course of the retailer or distributor, or any person on behalf of the retailer or distributor, responding in any form, to any query from a consumer, including—
- (i) in association with or in the course of any telephone call from a consumer; or
- (ii) in any emails.
- (a) as part of or accompanying any communication personalised for a specific named consumer (whether in print, electronic or other medium) from the retailer or distributor, or by an agent or related entity of the retailer or distributor, about—
- (4) A retailer or distributor may meet the requirement in sub-paragraph (3)(b)(i) by providing the information as part of initial automatic answering systems or call holding systems, provided in each case the information is reasonably likely to come to the attention of the consumer.
Clause 11.30A: inserted, on 1 April 2021, by clause 4 of the Electricity Industry Participation Code Amendment (Requirements to Improve Awareness of Dispute Resolution Scheme and the Electricity Plan Comparison Site) 2020.
Clause 11.30A(1): amended, on 1 March 2024, by clause 44 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2024.
11.30B
Provision of information on electricity plan comparison site
- (1) Each retailer that supplies electricity at any ICP for which the relevant business classification code for the purposes of clause 9(1)(k) of Schedule 11.1 is “000000” or “Residential” must provide clear information in the circumstances specified in subclauses (2) to (4) about the electricity plan comparison website or other platform, as identified on the Authority’s website.
- (2) The information required by subclause (1) must be clearly and prominently published on any website that—
- (a) is maintained by, or on behalf of, the retailer; and
- (b) deals with, describes or offers the supply of electricity at any such ICP by the retailer, or by an agent or related entity of the retailer.
- (3) The information required by subclause (1) must also be clearly and prominently provided as part of or accompanying any communication personalised to a specific named consumer (whether in print, electronic or other medium) from the retailer, or by an agent or related entity of the retailer, about—
- (a) billing or charges to, or payments owed or made by, the consumer for the supply of electricity at any such ICP, including any invoice, request for payment or statement of account; or
- (b) the terms and conditions for the supply of electricity at any such ICP, including the prices, tariffs, energy plan, price plan, tariff plan and terms of service for the consumer.
- (4) The information required by subclause (1) must also be clearly and prominently provided at least once every calendar year to each customer the retailer supplies electricity to at an ICP referred to in subclause (1).
- (5) If the Authority changes the web address of the electricity plan comparison website, establishes a new platform to perform the same purpose, or changes that platform or its location descriptor, each retailer must change the information published or provided under clause 11.30A to refer to the new address, platform or location descriptor as soon as reasonably possible and no later than 3 months from the date the change is notified on the Authority’s website.
Clause 11.30B: inserted, on 1 April 2021, by clause 4 of the Electricity Industry Participation Code Amendment (Requirements to Improve Awareness of Dispute Resolution Scheme and the Electricity Plan Comparison Site) 2020.
Clause 11.30B(4): amended, on 1 March 2024, by clause 45 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2024.
11.30C
Specific requirements for information provided on websites and by other electronic means
- The information provided under clauses 11.30A(2) and 11.30B(2)—
- (a) must be prominently provided on, or linked to, a page or pages of the retailer’s or distributor’s website, which a consumer seeking information on or in relation to the supply of electricity or line function services, or on the complaint processes of the retailer or distributor, is reasonably likely to view; but
- (b) does not need to be provided on every such page or every part, provided a consumer seeking such information is reasonably likely to come across the information in the course of visiting the website.
Clause 11.30C: inserted, on 1 April 2021, by clause 4 of the Electricity Industry Participation Code Amendment (Requirements to Improve Awareness of Dispute Resolution Scheme and the Electricity Plan Comparison Site) 2020.
11.30D
Limitations on required information disclosure under clause 11.30A and 11.30B
- (1) If a retailer or a distributor has provided the information required by clause 11.30A or 11.30B to a consumer—
- (a) in a consumer communication under clause 11.30A(3)(a) or 11.30B(3), the retailer or distributor does not need to continue to provide the information in any subsequent consumer communication on the same matter; or
- (b) in response to any query under clause 11.30A(3)(b), the retailer or distributor does not need to continue to provide the information in any further responses to the same or related queries.
- (2) Under subclause (1):
- (a) an invoice and any request for payment, reminder notice, notice of late payment, demand, or disconnection notice in respect of the amount in the invoice are on the same matter; but
- (b) invoices that apply to different periods are not on the same matter.
Clause 11.30D: inserted, on 1 April 2021, by clause 4 of the Electricity Industry Participation Code Amendment (Requirements to Improve Awareness of Dispute Resolution Scheme and the Electricity Plan Comparison Site) 2020.
11.30E
Meaning of “related entity”
- For the purposes of clause 11.30A and 11.30B, the term “related entity” has the meaning set out in section 2(3) of the Companies Act 1993, where the reference in that section to “company” is read as if it referred to either a “company” or a “body corporate”.
Clause 11.30E: inserted, on 1 April 2021, by clause 4 of the Electricity Industry Participation Code Amendment (Requirements to Improve Awareness of Dispute Resolution Scheme and the Electricity Plan Comparison Site) 2020.
11.31
Customer and embedded generator queries
- (1) If a trader receives a request from a customer of the trader or a person authorised by a customer of the trader for the customer’s ICP identifier, the trader must provide that information no later than 3 business days after receiving the request.
- (2) If a distributor receives a request from a customer or embedded generator whose ICP is connected to the distributor’s network for the customer’s or embedded generator’s ICP identifier, or a person authorised by such a customer or embedded generator, the distributor must provide that information no later than 3 business days after receiving the request.
Compare: Electricity Governance Rules 2003 rule 28 part E
Clause 11.31(1): amended, on 1 November 2018, by clause 46(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
Clause 11.31(2): amended, on 23 February 2015, by clause 75 of the Electricity Industry Participation Code Amendment (Distributed Generation) 2014.
Clause 11.31(2): amended, on 5 October 2017, by clause 217 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 11.31(2): amended, on 1 November 2018, by clause 46(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
11.32
Reliance on registry
- A participant does not breach this Code just because the participant does something relying on an incorrect record in the registry.
Compare: Electricity Governance Rules 2003 rule 29 part E
Access by consumers to their own electricity information
Cross Heading: inserted, on 1 February 2016, by clause 5 of the Electricity Industry Participation Code Amendment (Access to Retail Data) 2014.
Cross Heading: amended, on 1 June 2025, by clause 5 of the Electricity Industry Participation Code Amendment (Improving Consumer Access to their Electricity Information) 2025.
11.32A
Retailers must give consumers their electricity information
- (1) Each retailer must, if requested by a consumer with whom the retailer has a contract to supply electricity, or with whom the retailer has had such a contract in the last 24 months, give the consumer any of the information specified in subclause (2) that the consumer requests.
- (2) The information referred to in subclause (1) is information relating to any period in the 24 months preceding the request—
- (a) about the consumer's consumption of electricity, injection of electricity into a network, or services provided to the consumer, at each ICP at which the retailer had a contract to supply electricity to the consumer, including raw meter data; and
- (b) used by the retailer to—
- (i) calculate the amount of electricity consumed or injected into a network by the consumer at each ICP; or
- (ii) provide any service to the consumer.
Clause 11.32A: inserted, on 1 February 2016, by clause 5 of the Electricity Industry Participation Code Amendment (Access to Retail Data) 2014.
Clause 11.32A heading: amended, on 1 June 2025, by clause 6(1) of the Electricity Industry Participation Code Amendment (Improving Consumer Access to their Electricity Information) 2025.
Clause 11.32A (2): amended, on 1 June 2025, by clause 6(2) of the Electricity Industry Participation Code Amendment (Improving Consumer Access to their Electricity Information) 2025.
11.32B
Requests for information
- (1) A retailer to which a request is made must give the information to the consumer no later than 5 business days after the date on which the request is made.
- (2) In responding to a request, the retailer must comply with the procedures, and any relevant EIEP, published by the Authority under clause 11.32F.
- (3) A retailer must not charge a fee for responding to a request, but if a consumer makes more than 12 requests in the 12 month period before 1 June 2026, the retailer may impose a reasonable charge for further requests in that period.
Clause 11.32B: inserted, on 1 February 2016, by clause 5 of the Electricity Industry Participation Code Amendment (Access to Retail Data) 2014.
Clause 11.32B(2): amended, on 1 February 2016, by clause 43 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2015.
Clause 11.32B(2): amended, on 5 October 2017, by clause 218 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 11.32B (3): amended, on 1 June 2025, by clause 7 of the Electricity Industry Participation Code Amendment (Improving Consumer Access to their Electricity Information) 2025.
11.32C
Retailers must give written notice to consumers of availability of information
- Each retailer must give written notice to each consumer with whom it has a contract to supply electricity of the consumer's ability to make a request to the retailer under clause 11.32B, so that the consumer is given written notice at least once in each year.
Clause 11.32C Heading: amended, on 5 October 2017, by clause 219(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 11.32C: inserted, on 1 February 2016, by clause 5 of the Electricity Industry Participation Code Amendment (Access to Retail Data) 2014.
Clause 11.32C: amended, on 5 October 2017, by clause 219(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
11.32D
Information security
- A retailer that receives a request for information under clause 11.32B—
- (a) must not give access to that information unless it is satisfied as to the identity of the consumer making the request; and
- (b) must ensure, by the adoption of appropriate procedures, that any information intended for a consumer is received—
- (i) only by the consumer; or
- (ii) where the request is made by an agent of the consumer, only by the consumer or the consumer's agent.
Clause 11.32D: inserted, on 1 February 2016, by clause 5 of the Electricity Industry Participation Code Amendment (Access to Retail Data) 2014.
11.32E
Agents
- If a consumer authorises an agent to request information under clause 11.32B on behalf of the consumer, a retailer must deal with any request from the agent for information about the consumer under clause 11.32B in accordance with:
- (a) clauses 11.32A and 11.32EB;
- (b) clause 11.32ED, if a request:
- (i) includes a statement from the agent that the agent has obtained, or the request is accompanied by, a written authority from the consumer in the form and containing the information required by Schedule 11.6; and
- (ii) the request is made through the EIE System; and
- (c) the Privacy Act 2020, where applicable.
Clause 11.32E: inserted, on 1 February 2016, by clause 5 of the Electricity Industry Participation Code Amendment (Access to Retail Data) 2014.
Clause 11.32E: amended, on 1 March 2020, by clause 5(a) and (b) of the Electricity Industry Participation Code Amendment (Requirements and Processes for Information Requests by Agents) 2020.
Clause 11.32E(c): amended, on 1 March 2024, by clause 46 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2024.
11.32EA
Retailer actions on receipt of requests from agents
- (1) A retailer, after receiving a request under clause 11.32B from an agent on behalf of a consumer, must:
- (a) make a decision on the request, and advise the agent of that decision, as soon as reasonably practicable; and
- (b) provide the information requested within the timeframe required by clause 11.32B unless there are grounds for refusing the request under clause 11.32EB.
- (2) If the retailer considers, in accordance with subclause (1), that there are grounds for refusing the request, the retailer must, before refusing the request:
- (a) consider whether any further information could reasonably be provided by the agent to satisfy the retailer; and
- (b) request any such further information from the agent, specifying the further information required in detail.
- (3) If further information is provided under subclause (2)(b), the retailer upon receiving the further information must:
- (a) make a final decision on the request, and advise the agent of that decision, as soon as reasonably practicable; and
- (b) provide the information requested within the timeframe required by clause 11.32B as calculated from the time the retailer receives the further information, unless there are grounds for refusing the request under clause 11.32EB.
- (4) If a retailer decides to refuse a request, in advising the agent of that decision, the retailer must:
- (a) indicate the ground or grounds under clause 11.32EB(1) that the retailer is relying on to refuse the request; and
- (b) provide the agent with the detailed reasons as to why that ground or grounds applies or apply.
- (5) If a retailer decides to grant a request in full, the retailer meets the obligation to advise the agent of that decision by providing the information to the agent in accordance with subclauses (1)(b) and (3)(b).
- (6) The obligations in subclauses (1)(a) and (3)(a) do not detract from the obligations in subclauses (1)(b) and (3)(b), respectively.
Clause 11.32EA: inserted, on 1 March 2020, by clause 6 of the Electricity Industry Participation Code Amendment (Requirements and Processes for Information Requests by Agents) 2020.
11.32EB
Decisions on requests
- (1) A retailer that receives a request under clause 11.32B from an agent on behalf of a consumer must grant the request and provide the information unless the retailer believes on reasonable grounds:
- (a) that the consumer has not authorised the request;
- (b) that complying with the request would otherwise cause the retailer to breach its obligations under the Privacy Act 2020 (where it applies); or
- (c) that:
- (i) if the request is accompanied by a written authority in the form and containing the information required by Schedule 11.6 or the agent subsequently provides a copy of such an authority, any of the information required by Schedule 11.6 is incorrect in a material way, such that the retailer cannot be satisfied of the matters in paragraphs (a) or (b) or is unable to identify the consumer the request relates to; or
- (ii) in any other situation, the retailer is unable to identify the consumer the request relates to.
- (2) A retailer may not refuse a request under clause 11.32B from an agent on behalf of a consumer on the basis that the request or any authorisation relating to the request is not in a particular form, or does not follow a particular process.
Clause 11.32EB: inserted, on 1 March 2020, by clause 6 of the Electricity Industry Participation Code Amendment (Requirements and Processes for Information Requests by Agents) 2020.
Clause 11.32EB(1)(b): amended, on 1 March 2024, by clause 47 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2024.
11.32EC
Requirements for agents who are participants
- (1) This clause applies to each participant who wishes to make or who makes a request for information to a retailer under clause 11.32B as an agent on behalf of a consumer.
- (2) Before making the request, the participant must obtain an authorisation from the consumer for the participant to request the transfer of the information to the agent on behalf of the consumer.
- (3) The participant must:
- (a) retain a copy of the authorisation under subclause (2) or otherwise retain evidence that the consumer has provided the authorisation required by subclause (2); and
- (b) provide a copy of the authorisation or other evidence to the retailer, if requested by the retailer.
Clause 11.32EC: inserted, on 1 March 2020, by clause 6 of the Electricity Industry Participation Code Amendment (Requirements and Processes for Information Requests by Agents) 2020.
11.32ED
Additional requirements on retailers for authorisations in prescribed form and requests received through the EIE System
- (1) This clause applies where an agent requests information from a retailer on behalf of a consumer under clause 11.32B and:
- (a) subject to clause 11.32EE, either:
- (i) the request includes a statement from the agent that the agent has obtained a written authority from the consumer in the form and containing the information required by Schedule 11.6 (being an authority that remains in force at the date the request is made); or
- (ii) the agent separately provides a written authority in the form and containing the information required by Schedule 11.6 or a copy of such a written authority (being an authority that remains in force at the date the request is made); and
- (b) the request is made through the EIE System.
- (a) subject to clause 11.32EE, either:
- (2) If this clause applies:
- (a) the retailer must use all reasonable endeavours to take the steps in clauses 11.32EA(1)(a) and 11.32EA(2), as applicable, within 2 business days of the later of:
- (i) receiving the request; or
- (ii) receiving a copy of a written authority under subparagraph (1)(a)(ii); and
- (b) where clause 11.32EA(3) applies, the retailer must use all reasonable endeavours, within 2 business days of receiving further information from the agent, to take the steps in clause 11.32EA(3)(a).
- (a) the retailer must use all reasonable endeavours to take the steps in clauses 11.32EA(1)(a) and 11.32EA(2), as applicable, within 2 business days of the later of:
- (3) Where clause 11.32EA(2) applies, the request may include a request that the agent provide a copy of the written authority referred to in subclause (1)(a), if not provided with the request.
- (4) If a request is made through the EIE System, but the retailer believes on reasonable grounds that the request does not meet the requirements of the EIEP, subclauses (2) and (3) do not apply but, for the avoidance of doubt, the retailer must still comply with clauses 11.32B, 11.32EB and 11.32EC.
Clause 11.32ED: inserted, on 1 March 2020, by clause 6 of the Electricity Industry Participation Code Amendment (Requirements and Processes for Information Requests by Agents) 2020.
11.32EE
Requirements for written authorities under Schedule 11.6
- (1) Each written authority, for the purposes of clause 11.32ED, must include or be accompanied by:
- (a) if the consumer is an individual (being a natural person), an electronic signature or physical signature of the consumer or of a person on behalf of the consumer (in which case, evidence of that person’s authority to sign on behalf of the consumer is required) or other evidence that the consumer has approved the authority; or
- (b) if the consumer is not an individual (not being a natural person), an electronic signature or physical signature of an authorised representative of the consumer or other evidence that the consumer has approved the authority.
- (2) Each electronic signature, for the purposes of subclause (1), must meet the requirements of sections 226 and 228 of the Contract and Commercial Law Act 2017.
Clause 11.32EE: inserted, on 1 March 2020, by clause 6 of the Electricity Industry Participation Code Amendment (Requirements and Processes for Information Requests by Agents) 2020.
11.32EF
Revocation of authority
- (1) If a retailer receives notification from a consumer that the consumer has revoked an authority, the retailer must notify the agent within 2 business days of receiving the notification that the authority is revoked.
- (2) If an agent that is a participant receives notification from a consumer that the consumer has revoked the agent’s authority, the agent must notify the retailer within 2 business days of receiving the notification that the authority is revoked.
Clause 11.32EF: inserted, on 1 March 2020, by clause 6 of the Electricity Industry Participation Code Amendment (Requirements and Processes for Information Requests by Agents) 2020.
11.32EG
Authority may prescribe EIE System
- (1) The Authority may prescribe a system for the purpose of clauses 11.32E to 11.32ED for the:
- (a) exchange of information between participants;
- (b) the provision of information by participants to other participants or other persons; and
- (c) the making of requests for information by participants or other persons to participants.
- (2) The Authority must advise participants and other parties of any system it prescribes under subclause (1) by posting a notice of the prescribed system on the Authority’s website.
Clause 11.32EG: inserted, on 1 March 2020, by clause 6 of the Electricity Industry Participation Code Amendment (Requirements and Processes for Information Requests by Agents) 2020.
11.32F
Authority to publish procedures for responding to requests for consumption information
- (1) The Authority must—
- (a) publish, and keep published, procedures under which a retailer must respond to a request from a consumer under clause 11.32B; and
- (b) prescribe 1 or more EIEPs with which a retailer must comply when responding to such a request.
- (1A) The Authority must publish an EIEP it prescribes under subclause (1).
- (2) The procedures published by the Authority must specify the manner in which information must be given to consumers.
- (3) Each EIEP prescribed by the Authority must specify 1 or more formats in which information must be given to consumers.
- (4) Before the Authority prescribes an EIEP under subclause (1), or amends an EIEP that it has prescribed under subclause (1), it must consult with the participants that the Authority considers are likely to be affected by the EIEP.
- (5) The Authority need not comply with subclause (4) if it proposes to amend an EIEP prescribed under subclause (1) if the Authority is satisfied that—
- (a) the nature of the amendment is technical and non-controversial; or
- (b) there has been adequate prior consultation so that the Authority has considered all relevant views.
Clause 11.32F Heading: amended, on 5 October 2017, by clause 220(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 11.32F: inserted, on 1 February 2016, by clause 5 of the Electricity Industry Participation Code Amendment (Access to Retail Data) 2014.
Clause 11.32F: substituted, on 1 February 2016, by clause 44 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2015.
Clause 11.32F(1): replaced, on 5 October 2017, by clause 220(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 11.32F(1A): inserted, on 5 October 2017, by clause 220(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 11.32F(2) to (5): amended, on 5 October 2017, by clause 220(3) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
11.32G
Retailers must provide information about generally available retail tariff plans
- (1) If any person asks a retailer to provide information about 1 or more of the retailer's current generally available retail tariff plans, the retailer must give the requested information to the person no later than 5 business days after receiving the request.
- (2) If the person requests that information be provided under subclause (1) in a manner or format that differs from the manner or format the retailer typically uses to provide such information, the retailer may impose a reasonable charge for providing the information in the manner or form requested.
Clause 11.32G: inserted, on 1 February 2016, by clause 6 of the Electricity Industry Participation Code Amendment (Access to Retail Tariff Information) 2015.
11.33
[Expired]
Clause 11.33: inserted, from 24 May 2013 to 29 December 2013, by clause 4 of the Electricity Industry Participation (Transitional Provisions for New Metering Arrangements) Code Amendment 2013.
11.34
[Expired]
Clause 11.34: inserted, from 24 May 2013 to 29 December 2013, by clause 4 of the Electricity Industry Participation (Transitional Provisions for New Metering Arrangements) Code Amendment 2013.
11.35
[Expired]
Clause 11.35: inserted, from 24 May 2013 to 29 December 2013, by clause 4 of the Electricity Industry Participation (Transitional Provisions for New Metering Arrangements) Code Amendment 2013.
11.36
[Expired]
Clause 11.36: inserted, from 24 May 2013 to 29 December 2013, by clause 4 of the Electricity Industry Participation (Transitional Provisions for New Metering Arrangements) Code Amendment 2013.
Restrictions on electrical disconnection
Cross Heading: inserted, on 15 May 2025, by clause 8(1) of the Electricity Industry Participation Code Amendment (Retailer Default) 2025.
11.37
Restrictions on electrical disconnection
- (1) This clause applies if:
- (a) a retailer has a contract to supply electricity to a consumer at an ICP; and
- (b) the retailer is not the trader recorded in the registry as being responsible for the relevant ICP (the responsible trader).
- (2) The responsible trader must not electrically disconnect the ICP:
- (a) if its agreement with the retailer for the supply of electricity to the relevant ICP has not been terminated; or
- (b) earlier than 25 days after the date the agreement for the supply of electricity to the relevant ICP is terminated if the responsible trader terminates its agreement with the retailer for the supply of electricity to the relevant ICP for serious financial breach (trader/retailer).
Clause 11.37: inserted, on 15 May 2025, by clause 8(2) of the Electricity Industry Participation Code Amendment (Retailer Default) 2025.
Schedule 11.1
cl 11.7Creation and management of ICPs, ICP identifiers and NSPs
ICPs and ICP identifiers
1
ICP identifiers
- (1) A distributor must create an ICP identifier for each ICP on each network for which the distributor is responsible in accordance with the following format:
yyyyyyyyyyxxccc
where
yyyyyyyyyy
is a numerical sequence provided by the distributor
xx
is a code assigned by the Authority to the issuing distributor that ensures the ICP is unique
ccc
is a checksum generated according to the algorithm provided by the Authority.
- (2) The ICP identifier must be used by a participant in all communications with the registry manager to identify—
- (a) the point at which a trader is deemed to convey electricity to a consumer or from an embedded generating station; and
- (b) the point of connection between an embedded network and its parent network, or the point of connection between a shared unmetered load and its network.
- (3) Despite any clause to the contrary, only the obligations in this clause and clauses 2, 6 and 7(1)(a) to (e), (l) and (m) apply if an ICP identifier is used to identify a—
- (a) point of connection between an embedded network and its parent network; or
- (b) point of connection between shared unmetered load and its network.
- (4) If an ICP identifier is used in the management of the status of the ICP, the obligations in clauses 13, 16 and 20 also apply.
Compare: Electricity Governance Rules 2003 clause 1.1 schedule E1
Clause 1(1) and (2): amended, on 5 October 2017, by clause 221 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
2
Address
- (1) Each ICP identifier must have a location address that allows the ICP to be readily located.
- (2) Despite subclause (1), the address of an ICP identifier for distributed unmetered load may be the location of the distributed unmetered load database.
Compare: Electricity Governance Rules 2003 clause 1.2 schedule E1
Clause 2(2): inserted, on 29 August 2013, by clause 6 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2013.
3
Electrically disconnecting
- (1) Subject to subclause (2), a distributor must not create an ICP identifier or connect an ICP created after 7 October 2002 unless—
- (a) the ICP identifier is for an ICP that can be electrically disconnected without electrically disconnecting another ICP; and
- (b) the ICP can be electrically disconnected without electrically disconnecting another ICP.
- (2) Subclause (1) does not apply if the ICP is—
- (a) the point of connection between a network and an embedded network; or
- (b) an ICP that represents the consumption calculated by the difference between the total consumption for the embedded network and all other ICPs on the embedded network.
- (3) A distributor must not—
- (a) connect a new ICP to an existing ICP in series unless the existing ICP is of the type described in subclause (2)(a) or (2)(b); or
- (b) create a new ICP identifier for a new or existing ICP in series with an existing ICP unless the existing ICP is of the type described in subclause (2)(a) or (2)(b) and the distributor is responsible for both the new and existing ICPs.
Compare: Electricity Governance Rules 2003 clause 1.3 schedule E1
Clause 3 Heading: replaced, on 5 October 2017, by clause 222(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 3: amended, on 5 October 2017, by clause 222(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 3: replaced, on 1 March 2024 by clause 48 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2024.
4
Authority may grant dispensation
- The Authority may, by giving written notice, grant a dispensation from the requirements of clause 3 for an ICP that cannot be electrically disconnected without electrically disconnecting another ICP.
Compare: Electricity Governance Rules 2003 clause 1.4 schedule E1
Clause 4: amended, on 5 October 2017, by clause 223 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 4: amended, on 1 November 2018, by clause 47 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
5
Electrical load
- The electrical load associated with an ICP is deemed to be supplied through 1 network supply point only.
Compare: Electricity Governance Rules 2003 clause 1.5 schedule E1
6
Loss category
- An ICP must have a single loss category code that is referenced in such a way as to identify the associated loss factors.
Compare: Electricity Governance Rules 2003 clause 1.6 schedule E1
Provision of ICP information to the registry manager
Cross heading: amended, on 5 October 2017, by clause 224 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
7
Distributors to provide ICP information to registry manager
- (1) A distributor must, for each ICP on the distributor’s network, provide the following information to the registry manager:
- (a) the location address of the ICP identifier:
- (b) subject to subclause (4), the NSP identifier of the NSP to which the ICP is usually connected:
- (c) the installation type code assigned to the ICP:
- (d) the reconciliation type code assigned to the ICP:
- (e) the loss category code and loss factors for each loss category code assigned to the ICP:
- (f) if the ICP connects the distributor's network to an embedded generating station that has a capacity of 10 MW or more, the information required by subclause (6), in accordance with subclause (7):
- (g) the price category code assigned to the ICP, which may be a placeholder price category code only if the distributor is unable to assign the actual price category code because the capacity or volume information required to assign the actual price category code cannot be determined before electricity is traded at the ICP:
- (h) if the price category code assigned under paragraph (g) requires one or more values for the capacity of the ICP, the chargeable capacity of the ICP, as follows:
- (i) if the chargeable capacity cannot be determined before electricity is traded at the ICP, a placeholder chargeable capacity:
- (ii) if the capacity value or values can be determined for a billing period from the metering information collected for that billing period, no chargeable capacity:
- (iia) if there is more than one capacity value at the ICP, and one or more, but not all, of those capacity values can be determined for a billing period from the metering information collected for that billing period—
- (A) no capacity value recorded in the registry field for the chargeable capacity; and
- (B) either the term "POA" or all other capacity values, recorded in the registry field in which the distributor installation details are also recorded:
- (iib) if there is more than one capacity value at the ICP, and none of those capacity values can be determined for a billing period from the metering information collected for that billing period—
- (A) the annual capacity value recorded in the registry field for the chargeable capacity; and
- (B) either the term "POA" or all other capacity values, recorded in the registry field in which the distributor installation details are also recorded:
- (iii) in any other case, the actual chargeable capacity:
- (i) the distributor installation details of the ICP determined by the price category code assigned to the ICP (if any), which may be placeholder distributor installation details only if the distributor is unable to assign the actual distributor installation details because the capacity or volume information required to assign the actual distributor installation details cannot be determined before electricity is traded at the ICP:
- (j) the participant identifier of the first trader who has entered into an arrangement with a customer or an embedded generator to sell or purchase electricity at the ICP (only if the information is provided by the first trader):
- (k) the status of the ICP determined in accordance with clauses 12 to 20:
- (l) designation of the ICP as "Dedicated" if the ICP is located in a balancing area that has more than 1 NSP located within it, and—
- (i) the ICP will be supplied only from the NSP with the NSP identifier provided under paragraph (b); or
- (ii) the ICP is a point of connection between a network and an embedded network:
- (m) if unmetered load, other than distributed unmetered load, is associated with the ICP, the type and capacity in kW of the unmetered load (if the distributor knows that information):
- (n) if shared unmetered load is associated with the ICP, a list of the ICP identifiers of the ICPs that are associated with the unmetered load:
- (o) if the ICP connects the distributor’s network to distributed generation,—
- (i) the nameplate capacity of the distributed generation; and
- (ii) the generation fuel type of the distributed generation:
- (p) the date on which the ICP is initially electrically connected.
- (1A) For the purposes of subclause (1)(h), if the price category assigned to the ICP requires information additional to chargeable capacity to unambiguously define the line charges, the additional information may be contained in the distributor installation details field of the registry.
- (2) The distributor must provide the information specified in subclauses (1)(a) to (1)(o) to the registry manager as soon as practicable after the ICP identifier for the ICP to which the information relates is created, and before electricity is traded at the ICP.
- (2A) The distributor must provide the information specified in subclause (1)(p) to the registry manager no later than 10 business days after the date on which the ICP is initially electrically connected.
- (2B) Despite subclause (2A), the distributor is not required to provide the information specified in subclause (1)(p) if the date on which the ICP is initially electrically connected is earlier than 29 August 2013.
- (3) The distributor must provide the following information to the registry manager no later than 10 business days after the trading of electricity at the ICP commences:
- (a) the actual price category code assigned to the ICP:
- (b) the actual chargeable capacity of the ICP determined by the price category code assigned to the ICP (if any):
- (c) the actual distributor installation details of the ICP determined by the price category code assigned to the ICP (if any).
- (4) If a distributor cannot identify the NSP that is connected to an ICP, the distributor must nominate the NSP that the distributor thinks is most likely to be connected to the ICP, taking into account the flow of electricity within the distributor’s network.
- (5) An ICP is deemed to be connected to the NSP nominated by the distributor under subclause (1)(b).
- (6) If a distributor assigns a loss category code to an ICP on the distributor’s network that connects the distributor’s network to an embedded generating station that has a capacity of 10MW or more—
- (a) the loss category code assigned to the ICP must be unique and must not be assigned to any other ICP on the distributor’s network; and
- (b) the distributor must provide the following information to the reconciliation manager:
- (i) the unique loss category code assigned to the ICP:
- (ii) the ICP identifier of the ICP:
- (iii) the NSP identifier of the NSP to which the ICP is connected:
- (iv) the plant name of the embedded generating station.
- (7) The distributor must provide the information in subclause (6) no later than 5 business days before the distributor assigns the loss category code.
- (8) A distributor may provide the registry manager with global positioning system coordinates for each ICP on the distributor’s network.
- (9) If a distributor provides the global positioning system coordinates of an ICP to the registry manager under subclause (8), it must provide the coordinates—
- (a) as New Zealand Transverse Mercator 2000 (NZTM2000) coordinates as defined in Land Information New Zealand’s LINZS25002 standard (Standard for New Zealand Geodetic Datum 2000 Projections); or
- (b) in a format specified by the Authority.
Compare: Electricity Governance Rules 2003 clause 2 schedule E1
Clause 7(1) Heading: amended, on 5 October 2017, by clause 225(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 7(1): amended, on 15 May 2014, by clause 23 of the Electricity Industry Participation (Minor Code Amendments) Code Amendment 2014.
Clause 7(1), (2), (2A), (3), (8) and (9): amended, on 5 October 2017, by clause 225(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 7(1)(a): amended, on 29 August 2013, by clause 16 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011.
Clause 7(1)(b): amended, on 23 February 2015, by clause 75 of the Electricity Industry Participation Code Amendment (Distributed Generation) 2014.
Clause 7(1)(b), (4), (5) and (6)(b)(iii): amended, on 5 October 2017, by clause 225(3) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 7(1)(h): substituted, on 29 August 2013, by clause 7(1) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2013.
Clause 7(1)(h): amended, on 1 February 2019, by clause 48(1)(a) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
Clause 7(1)(h)(ii): replaced, on 1 February 2019, by clause 48(1)(b) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
Clause 7(1)(h)(iia): inserted, on 1 February 2019, by clause 48(1)(b) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
Clause 7(1)(h)(iib): inserted, on 1 February 2019, by clause 48(1)(b) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
Clause 7(1)(j): amended, on 1 November 2018, by clause 48(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
Clause 7(1)(o) and (p): inserted, on 29 August 2013, by clause 5(1) of the Electricity Industry Participation (Additional Registry Fields) Code Amendment 2012.
Clause 7(1)(p), (2A) and (2B): amended, on 5 October 2017, by clause 225(4) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 7(1A): inserted, on 29 August 2013, by clause 7(2) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2013.
Clause 7(2): amended, on 29 August 2013, by clause 5(2) of the Electricity Industry Participation (Additional Registry Fields) Code Amendment 2012.
Clause 7(2A) and (2B): inserted, on 29 August 2013, by clause 5(3) of the Electricity Industry Participation (Additional Registry Fields) Code Amendment 2012.
Clause 7(4): amended, on 23 February 2015, by clause 75 of the Electricity Industry Participation Code Amendment (Distributed Generation) 2014.
Clause 7(5): amended, on 23 February 2015, by clause 75 of the Electricity Industry Participation Code Amendment (Distributed Generation) 2014.
Clause 7(6): amended, on 21 September 2012, by clause 15(1) of the Electricity Industry Participation (Minor Amendments) Code Amendment 2012.
Clause 7(6)(b)(iii): amended, on 23 February 2015, by clause 75 of the Electricity Industry Participation Code Amendment (Distributed Generation) 2014.
Clause 7(8) and (9): inserted, on 29 August 2013, by clause 5(4) of the Electricity Industry Participation (Additional Registry Fields) Code Amendment 2012.
8
Distributors to change ICP information provided to registry manager
- (1) If information about an ICP provided to the registry manager in accordance with clause 7 changes, the distributor in whose network the ICP is located must give written notice to the registry manager of the change.
- (2) Subject to subclause (2A), the distributor must give the notice—
- (a) in the case of a change to the information referred to in clause 7(1)(b) (other than a change that is the result of the commissioning or decommissioning of an NSP), no later than 8 business days after the change takes effect; and
- (aa) in the case of a change to the information provided under clauses 7(1)(g), 7(1)(h) and 7(1)(i), where the change is backdated, no later than 3 business days after the distributor and the trader responsible for the ICP have agreed on the change; and
- (ab) in the case of decommissioning an ICP, by the later of—
- (i) 3 business days after the registry manager has advised the distributor under clause 11.29 that the ICP is ready to be decommissioned; and
- (ii) 3 business days after the distributor has decommissioned the ICP; and
- (b) in every other case, no later than 3 business days after the change takes effect.
- (2A) Where the functioning of the registry prevents the distributor from updating the registry until after a metering equipment provider has completed its obligations relating to the ICP in accordance with Schedule 11.4, the timeframes in subclause (2) start from the day the metering equipment provider completes those obligations.
- (3) A distributor is not required to give written notice if information provided in accordance with clause 7(1)(b) changes, and applies for less than 10 business days.
- (4) If information provided under clause 7(1)(b) changes, and applies for 10 business days or more, the distributor must—
- (a) give the notice under subclause (1) no later than 13 business days after the change takes effect; and
- (b) include in the notice the date the change occurred as the effective date for the change.
Compare: Electricity Governance Rules 2003 clause 2A schedule E1
Clause 8 Heading: amended, on 5 October 2017, by clause 226(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 8(1): amended, on 5 October 2017, by clause 226(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 8(2): amended, on 5 October 2017, by clause 226(3) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 8(2): amended, on 1 March 2024, by clause 49(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2024.
Clause 8(2)(a): amended, on 1 November 2018, by clause 49(1)(a) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
Clause 8(2)(a): amended, on 1 March 2024, by clause 49(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2024.
Clause 8(2)(aa): inserted, on 31 November 2021, by clause 36 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
Clause 8(2)(aa): amended, on 1 March 2024, by clause 49(3) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2024.
Clause 8(2)(ab): inserted, on 1 November 2018, by clause 49(1)(b) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
Clause 8(2)(ab)(ii): amended, on 1 March 2024, by clause 49(4) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2024.
Clause 8(2A): inserted, on 1 March 2024, by clause 49(5) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2024.
Clause 8(3): amended, on 1 August 2019, by clause 49(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
Clause 8(3): amended, on 5 October 2017, by clause 226(4) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 8(4): replaced, on 1 August 2019, by clause 49(3) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
9
Traders to provide ICP information to registry manager
- (1) Each trader must provide the following information to the registry manager for each ICP for which it is recorded in the registry as having responsibility:
- (a) the participant identifier of the trader:
- (b) the profile code of each profile at that ICP approved by the Authority in accordance with clause 13 of Schedule 15.5:
- (c) the participant identifier of the metering equipment provider for each category 1 metering installation, or higher category metering installation, for the ICP:
- (d) [Revoked]
- (e) [Revoked]
- (ea) the type of submission information that the trader will provide to the reconciliation manager for the ICP:
- (f) if the settlement type UNM is assigned to the ICP—
- (i) if the load is profiled through an engineering profile in accordance with profile class 2.1, the code ENG; or
- (ii) in all other cases, the daily average unmetered load in kWh at the ICP:
- (g) the type and capacity of the unmetered load at the ICP (if any):
- (h) [Revoked]
- (i) [Revoked]
- (j) the status of the ICP determined in accordance with clauses 12 to 20.
- (k) except as provided in subclause (1A), the relevant business classification code applicable to the customer at the ICP, in accordance with business classification codes published by the Authority.
- (1A) A trader must not provide the information specified in subclause (1)(k) if—
- (a) the ICP exists for the purpose of reconciling embedded network residual load; or
- (b) the ICP has "Distributor" status as specified in clause 16.
- (2) The trader must provide the information specified in subclause (1)(a) to subclause (1)(j) to the registry manager no later than 5 business days after the trader commences trading at the ICP to which the information relates.
- (3) The trader must provide the information specified in subclause (1)(k) to the registry manager no later than 20 business days after the trader commences trading at the ICP to which the information relates.
Compare: Electricity Governance Rules 2003 clause 3 schedule E1
Clause 9 Heading: amended, on 5 October 2017, by clause 227(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 9(1): amended, on 29 August 2013, by clause 8(1) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2013.
Clause 9(1): amended, on 5 October 2017, by clause 227(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 9(1)(c): amended, on 29 August 2013, by clause 8(2) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2013.
Clause 9(1)(d): substituted, on 1 December 2011, by clause 14 of the Electricity Industry Participation Code (Distributor Use-of-System Agreements and Distributor Tariffs) Amendment 2011.
Clause 9(1)(d): amended, on 21 September 2012, by clause 15(2) of the Electricity Industry Participation (Minor Amendments) Code Amendment 2012.
Clause 9(1)(d): revoked, on 29 August 2013, by clause 8(3) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2013.
Clause 9(1)(e): revoked, on 15 May 2014, by clause 24 of the Electricity Industry Participation (Minor Code Amendments) Code Amendment 2014.
Clause 9(1)(ea): inserted, on 29 August 2013, by clause 8(5) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2013.
Clause 9(1)(f): amended, on 29 August 2013, by clause 8(6) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2013.
Clause 9(1)(h) and (i): revoked, on 29 August 2013, by clause 8(7) and (8) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2013.
Clause 9(1)(k): inserted, on 29 August 2013, by clause 5(5) of the Electricity Industry Participation (Additional Registry Fields) Code Amendment 2012 and Clause 8(9) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2013.
Clause 9(1)(k): amended, on 1 November 2018, by clause 50 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
Clause 9(1A): inserted, on 29 August 2013, by clause 8(9) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2013.
Clause 9(2): amended, on 29 August 2013, by clause 8(10) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2013.
Clause 9(2) and (3): amended, on 5 October 2017, by clause 227(3) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 9(3): inserted, on 29 August 2013, by clause 8(11) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2013.
10
Traders to change ICP information provided to registry manager
- (1) If information about an ICP provided to the registry manager in accordance with clause 9 changes, the trader who trades at the ICP must give written notice to the registry manager of the change.
- (2) Subject to subclause (2A) the trader must give the notice no later than 5 business days after the change.
- (2A) Where the functioning of the registry prevents the trader from updating the registry until after the metering equipment provider has completed its obligations relating to the ICP in accordance with Schedule 11.4, the timeframes in subclause (2) start from the day the metering equipment provider has completed those obligations.
- (3) [Revoked]
- (4) [Revoked]
Compare: Electricity Governance Rules 2003 clause 3A schedule E1
Clause 10 Heading: amended, on 5 October 2017, by clause 228(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 10(1): amended, on 5 October 2017, by clause 228(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 10(2): amended, on 1 March 2024, by clause 50(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2024.
Clause 10(2A): inserted, on 1 March 2024, by clause 50(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2024.
Clause 10(2) and (3): amended, on 5 October 2017, by clause 228(3) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 10(3) and (4): inserted, on 29 August 2013, by clause 9 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2013 and expire on 26 September 2013.
Clauses 10(3) and (4): revoked, on 1 March 2024, by clause 50(3) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2024.
11
Correction of errors in the registry
- (1) By 0900 hours on the 1st business day of each reconciliation period, the registry manager must provide to each participant who is required to submit submission information, the following:
- (a) a list of the ICPs at which the participant is recorded on the registry as trading during each consumption period being revised in the reconciliation period:
- (b) all information associated with the participant’s participant identifier, including the profiles for each ICP.
- (2) If there is an error in the information provided under subclause (1), the participant must change the information in the registry as soon as practicable after becoming aware of the error.
Compare: Electricity Governance Rules 2003 clause 3B schedule E1
Clause 11(1): amended, on 5 October 2017, by clause 229 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Management of ICP status
12
Management of ICP status by distributors and traders
The status of an ICP, as recorded on the registry, must be managed by distributors and traders in accordance with clauses 13 to 20.
Compare: Electricity Governance Rules 2003 clause 4 schedule E1
13
“New” status
- The ICP status of “New” must be managed by the relevant distributor and indicates that—
- (a) the associated electrical facilities are in the construction phase; and
- (b) the ICP is not ready for the trader to authorise the electrical connection of the ICP.
Compare: Electricity Governance Rules 2003 clause 4.1 schedule E1
Clauses 13(a): amended, on 1 March 2024, by clause 51 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2024.
Clause 13(b): amended, on 5 October 2017, by clause 230 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
14
“Ready” status
- (1) The ICP status of “Ready” must be managed by the relevant distributor and indicates that—
- (a) the associated electrical facilities are ready for connecting to the electricity supply; or
- (b) the ICP is ready for the trader to authorise the electrical connection of the ICP.
- (2) Before an ICP is given the "Ready" status, the relevant distributor must—
- (a) identify the trader that has taken responsibility for the ICP; and
- (b) ensure that the ICP has a single price category code.
Compare: Electricity Governance Rules 2003 clauses 4.2 and 4.3 schedule E1
Clause 14(1): amended, on 5 October 2017, by clause 231 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 14(1)(a): amended, on 15 May 2014, by clause 25 of the Electricity Industry Participation (Minor Code Amendments) Code Amendment 2014.
Clause 14(1)(a): amended, on 23 February 2015, by clause 75 of the Electricity Industry Participation Code Amendment (Distributed Generation) 2014.
Clause 14(1)(a): amended, on 1 March 2024, by clause 52 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2024.
15
"New" or "Ready" status for 24 months or more
- (1) Subclause (2) applies if—
- (a) an ICP has had the status of "New" for 24 months or more; or
- (b) an ICP has had the status of "Ready" for 24 months or more.
- (2) The distributor must—
- (a) ask the trader who intends to trade at the ICP whether the ICP should continue to have that status; and
- (b) decommission the ICP if the trader advises that the ICP should not continue to have that status.
Compare: Electricity Governance Rules 2003 clause 4.3A schedule E1
Clause 15 Heading: amended, on 5 October 2017, by clause 232 (1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 15: substituted, on 15 May 2014, by clause 26 of the Electricity Industry Participation (Minor Code Amendments) Code Amendment 2014.
Clause 15(1): amended, on 5 October 2017, by clause 232(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 15(2)(b): amended, on 5 October 2017, by clause 232(3) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
16
“Distributor” status
- (1) The ICP status of “Distributor” must be managed by the relevant distributor and indicates that the ICP record represents a shared unmetered load installation or the point of connection between an embedded network and its parent network.
- (2) A trader cannot change the status of an ICP record with the ICP status of “Distributor”.
Compare: Electricity Governance Rules 2003 clause 4.4 schedule E1
17
“Active” status
- (1) The ICP identifier status of “Active” must be managed by the relevant trader and indicates that—
- (a) the associated electrical facilities are electrically connected; and
- (b) a trader must provide information related to the ICP identifier, in accordance with Part 15, to the reconciliation manager for the purpose of compiling reconciliation information.
- (2) Before an ICP is given the “Active” status, the trader must ensure that—
- (a) the ICP identifier has only 1 embedded generator, direct purchaser, or customer of a retailer; and
- (b) the electricity consumed is quantified by a metering installation or a method of calculation approved by the Authority.
Compare: Electricity Governance Rules 2003 clauses 4.5 and 4.6 schedule E1
Clause 17(1)(a): amended, on 29 August 2013, by clause 18 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011.
Clause 17(1)(a): amended, on 5 October 2017, by clause 233 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 17(2)(a): amended, on 1 November 2018, by clause 51 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
Clause 17(1): amended, on 31 October 2023, by clause 5 of the Electricity Industry Participation Code Amendment (Clarification of Trader Obligations) 2023.
Clause 17(2)(a): amended, on 31 October 2023, by clause 5 of the Electricity Industry Participation Code Amendment (Clarification of Trader Obligations) 2023.
Clause 17(1)(a): amended, on 1 March 2024, by clause 53 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2024.
18
[Revoked]
Compare: Electricity Governance Rules 2003 clause 4.6A schedule E1
Clause 18: revoked, on 29 August 2013, by clause 5(7) of the Electricity Industry Participation (Additional Registry Fields) Code Amendment 2012.
19
“Inactive” status
- (1) Except as provided in subclause (2), the ICP status of “Inactive” must be managed by the relevant trader and indicates that—
- (a) the ICP is electrically disconnected; or
- (b) submission information related to the ICP is not required by the reconciliation manager for the purpose of compiling reconciliation information.
- (2) The ICP status of “Inactive” may be managed by the relevant distributor only to indicate that—
- (a) there has been an interruption in electricity supply affecting the ICP; or
- (b) the ICP cannot be electrically disconnected following a request for electrical disconnection.
Compare: Electricity Governance Rules 2003 clause 4.7 schedule E1
Clause 19(a): substituted, on 29 August 2013, by clause 20 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011.
Clause 19(a): amended, on 5 October 2017, by clause 234 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 19: replaced, on 25 November 2024, by clause 5 of the Electricity Industry Participation Code Amendment (Distributor Agreement Amendments) 2024.
20
“Decommissioned” status
- (1) The ICP status of “Decommissioned” must be managed by the relevant distributor and indicates that the ICP is permanently removed from future switching and reconciliation processes.
- (2) Decommissioning occurs when—
- (a) electrical facilities associated with the ICP are physically removed; or
- (b) there is a change in the allocation of electrical loads between ICPs with the effect of making the ICP obsolete; or
- (c) in the case of a distributor-only ICP for an embedded network, the embedded network no longer exists.
Compare: Electricity Governance Rules 2003 clause 4.8 schedule E1
Clause 20(2): amended, on 5 October 2017, by clause 235 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 20(2)(a): amended, on 1 March 2024, by clause 54 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2024.
Updating registry standing information
21
Updating table of loss category codes
- (1) Each distributor must keep up to date the table in the registry of the loss category codes that may be assigned to ICPs on each distributor’s network, by entering in the table any new loss category codes that may be assigned to an ICP on the distributor’s network.
- (2) Each entry in the table must specify the date on which each loss category code takes effect.
- (3) The date that a loss category code takes effect must not be earlier than 2 months after the date on which the loss category code is entered in the table.
- (4) A loss category code takes effect on the specified date.
- (5) To avoid doubt, subclause (3) does not apply to the creation of an ICP or to the transfer of an ICP from 1 distributor's network to another distributor's network.
Compare: Electricity Governance Rules 2003 clause 5 schedule E1
22
Updating loss factors for loss category codes
- (1) A distributor must enter loss factors in the registry for each loss category code entered on the table in the registry under clause 21.
- (2) A distributor must ensure that—
- (a) each loss category code has no more than 2 loss factors in a calendar month; and
- (b) each loss factor covers a range of trading periods within that month so that all trading periods have a single applicable loss factor.
- (3) A distributor who wishes to replace an existing loss factor on the table in the registry must enter the replaced loss factor on the table in the registry.
- (4) Each entry in the table must specify the date on which the replaced loss factor takes effect.
- (5) The date that a loss factor takes effect must not be earlier than 2 months after the date on which the loss factor is entered in the table.
- (6) A replaced loss factor takes effect on the specified date.
- (7) To avoid doubt, subclause (5) does not apply to the creation of an ICP or to the transfer of an ICP from 1 distributor's network to another distributor's network.
- (8) The registry manager must publish an updated schedule of all loss category codes and the loss factors for each loss category code no later than 1 business day after receiving notice of a change.
Compare: Electricity Governance Rules 2003 clause 5A schedule E1
Clause 22(1): amended, on 5 October 2017, by clause 236(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 22(8): amended, on 21 September 2012, by clause 15(3) of the Electricity Industry Participation (Minor Amendments) Code Amendment 2012.
Clause 22(8): amended, on 5 October 2017, by clause 236(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
23
Updating table of price category codes
- (1) Each distributor must keep up to date the table in the registry of the price category codes that may be assigned to ICPs on each distributor’s network, by entering in the table any new price category codes that may be assigned to an ICP on the distributor’s network.
- (2) Each entry in the table must specify the date on which each price category code takes effect.
- (3) The date that a price category code takes effect must not be earlier than 2 months after the date on which the price category code is entered in the table.
- (4) A price category code takes effect on the specified date.
- (5) To avoid doubt, subclause (3) does not apply to the creation of an ICP or to the transfer of an ICP from 1 distributor's network to another distributor's network.
Compare: Electricity Governance Rules 2003 clause 6 schedule E1
24
Balancing area information
- (1) A distributor must give written notice to the reconciliation manager of the establishment of a balancing area associated with an NSP supplying the distributor’s network, in accordance with clause 26.
- (2) A distributor must give written notice to the reconciliation manager of any change to the information provided under subclause (1).
- (3) The notice must―
- (a) specify the date and trading period from which the change takes effect; and
- (b) be given no later than 3 business days after the change takes effect.
- (4) The reconciliation manager must give written notice to the registry manager of changes to balancing areas within 1 business day after receiving the notice.
- (5) The registry manager must publish an updated schedule of the mapping between NSPs and balancing areas within 1 business day after receiving the notice.
- (6) The schedule must specify the date and trading period from which the change took effect.
Compare: Electricity Governance Rules 2003 clause 7 schedule E1
Clause 24(1), (2) and (4): amended, on 5 October 2017, by clause 237(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 24(3), (4) and (5): amended, on 5 October 2017, by clause 237(3) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 24(4) and (5): amended, on 5 October 2017, by clause 237(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
25
Creation and decommissioning of NSPs and transfer of ICPs from 1 distributor's network to another distributor's network
- (1) If an NSP is to be created or decommissioned,—
- (a) the participant specified in subclause (3) in relation to the NSP must give written notice to the reconciliation manager of the creation or decommissioning; and
- (b) the reconciliation manager must give written notice to the Authority and affected reconciliation participants of the creation or decommissioning no later than 1 business day after receiving the notice in paragraph (a).
- (2) If a distributor wishes to change the record in the registry of an ICP that is not recorded as being usually connected to an NSP in the distributor’s network, to transfer the ICP so that it is recorded as being usually connected to an NSP in the distributor’s network, the distributor must give written notice to the reconciliation manager, the Authority, and each affected reconciliation participant of the transfer.
- (3) The notice required by subclause (1) must be given by—
- (a) the grid owner, if—
- (i) the NSP is a point of connection between the grid and a local network; or
- (ii) if the NSP is a point of connection between a generator and the grid; or
- (b) the distributor for the local network who initiated the creation or decommissioning, if the NSP is an interconnection point between 2 local networks; or
- (c) the embedded network owner who initiated the creation or decommissioning, if the NSP is an interconnection point between 2 embedded networks; or
- (d) the distributor for the embedded network, if the NSP is a point of connection between an embedded network and another network.
- (a) the grid owner, if—
- (4) A distributor who is required to give written notice of a transfer under subclause (2) or subclause (3)(d) must comply with Schedule 11.2.
- (5) The participant required to give notice under subclause (1) must give notice no later than 30 days prior to the intended date of creation or decommissioning of the NSP.
- (6) If a participant changes the intended date of creation or decommissioning after giving notice under subclause (1), the new intended date of creation or decommissioning must not be earlier than the original intended date of creation or decommissioning given in the notice under subclause (1), and the participant must give a replacement notice advising the new intended date of creation or decommissioning, as soon as possible after the participant decides to change the intended date.
- (7) An embedded network owner must not give written notice of decommissioning an NSP under subclause (3)(c) or subclause (3)(d) unless—
- (a) the embedded network owner has changed the status in the registry of all ICPs recorded as being usually connected to the NSP to ‘Decommissioned’; or
- (b) a distributor has changed the record in the registry of each ICP previously recorded as being usually connected to the NSP, and with a status in the registry of ‘Active’ or ‘Inactive’, to record the ICP as being usually connected to an NSP in the distributor’s network; or
- (c) a combination of the changes described in paragraphs (a) and (b) has occurred, so that no ICP with a status in the registry of ‘Active’ or ‘Inactive’ is recorded as being connected to the NSP that is to be decommissioned.
Compare: Electricity Governance Rules 2003 clause 8 schedule E1
Clause 25(1), (2), (3) and (4): amended, on 5 October 2017, by clause 238(1) to (6) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 25(2): amended, on 23 February 2015, by clause 75 of the Electricity Industry Participation Code Amendment (Distributed Generation) 2014.
Clause 25(2): amended, on 1 March 2022, by clause 37(1)(a) and (b) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
Clause 25(5) and 25(6): inserted, on 1 February 2021, by clause 45 of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.
Clause 25(6): amended, on 1 April 2025, by clause 17 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2025.
Clause 25(7): inserted, on 1 March 2022, by clause 37(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
26
Information to be provided if NSPs are created or ICPs are transferred from 1 distributor's network to another distributor's network
- (1) If a participant gives notice under clause 25(1) or (2) of the creation of an NSP or the transfer of an ICP from 1 distributor's network to another distributor's network, the participant must request that the reconciliation manager create a unique NSP identifier for the NSP.
- (2) The participant must make the request―
- (a) in the case of notice given under clause 25(3)(b) or (c), at least 10 business days before the NSP is electrically connected; and
- (b) in every other case, at least 1 month before the NSP is electrically connected or the ICP is transferred.
- (3) If a participant gives notice under clause 25(1) of the creation of an NSP, the distributor on whose network the NSP is located must give the reconciliation manager the following information:
- (a) if the NSP is to be located in a new balancing area to be created—
- (i) all relevant details necessary for the balancing area to be created; and
- (ii) notice that the NSP to be created is to be assigned to the new balancing area; and
- (b) in every other case, notice of the balancing area in which the NSP is located.
- (a) if the NSP is to be located in a new balancing area to be created—
- (4) If a participant gives notice under clause 25(1) or (2) of a creation or transfer that relates to an NSP between a network and an embedded network, the distributor who owns the embedded network must give written notice to the reconciliation manager of the following:
- (a) the network on which the NSP will be located after the creation or transfer:
- (b) the ICP identifier for the ICP that connects the network and the embedded network:
- (c) the date on which the creation or transfer will take effect.
- (5) The distributor must give the notice at least 1 month before the creation or transfer.
Compare: Electricity Governance Rules 2003 clause 9 schedule E1
Clause 26(1): amended, on 5 October 2017, by clause 239(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 26(2): amended, on 5 October 2017, by clause 239(2) and (3) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 26(2)(a) and (b): amended, on 23 February 2015, by clause 75 of the Electricity Industry Participation Code Amendment (Distributed Generation) 2014.
Clause 26(3): amended, on 21 September 2012, by clause 15(4) of the Electricity Industry Participation (Minor Amendments) Code Amendment 2012.
Clause 26(3): amended, on 5 October 2017, by clause 239(4) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 26(4): amended, on 5 October 2017, by clause 239(1) and (5) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 26(5): amended, on 5 October 2017, by clause 239(3) and (6) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
27
Information to be provided if ICPs become NSPs
- (1) If a transfer for which notice is given under clause 25 results in an ICP becoming an NSP at which an embedded network connects to a network, or in an ICP becoming an NSP that is an interconnection point, the distributor who owns the network on which the NSP will be located after the change must give written notice to any trader trading at the ICP of the transfer.
- (2) The distributor must give the notice at least 1 month before the transfer.
Compare: Electricity Governance Rules 2003 clause 10 schedule E1
Clause 27(1): amended, on 5 October 2017, by clause 240(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 27(2): amended, on 5 October 2017, by clause 240(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
28
Reconciliation manager to allocate new identifiers
- The reconciliation manager must, within 1 business day of receiving notice under clause 25(1) or (2), allocate a unique NSP identifier to each point of connection or interconnection point to which the notice relates in accordance with the following format:
bbbqqqz nnnn
where
bbbqqqz
is, in the case of a local network, the code for the GXP or GIP or, in the case of an embedded network or the point of connection between 2 local networks, the code for the point of connection to its parent network
where
bbb
is a combination of 3 alpha characters that form a unique location identifier
qqq
is the voltage in kV of the supply bus
z
is a numeral allocated to distinguish it from any other supply bus of the same voltage at the same location
nnnn
is a participant identifier for the network owner who from time to time owns the network being supplied.
Compare: Electricity Governance Rules 2003 clause 11 schedule E1
Clause 28: amended, on 5 October 2017, by clause 241 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
29
Obligations concerning change in network owner
- (1) If a network owner acquires all or part of an existing network, the network owner must give written notice to the following of the acquisition:
- (a) the previous network owner:
- (b) the reconciliation manager:
- (c) the Authority:
- (d) every reconciliation participant who trades at an ICP connected to the network or part of the network acquired.
- (2) The network owner must give the notice at least 1 month before the acquisition.
- (3) The notice must specify―
- (a) the ICP identifiers for which the network owner’s participant identifier must be amended to reflect the acquisition of the network or part of the network by the network owner; and
- (b) the effective date of the acquisition.
- (4) A network owner who acquires all or part of an existing network must comply with Schedule 11.2.
Compare: Electricity Governance Rules 2003 clause 12 schedule E1
Clause 29(1): amended, on 5 October 2017, by clause 242(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 29(1)(d): amended, on 23 February 2015, by clause 75 of the Electricity Industry Participation Code Amendment (Distributed Generation) 2014.
Clause 29(2): amended, on 5 October 2017, by clause 242(2) and (3) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 29(3): amended, on 5 October 2017, by clause 242(3) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
30
Reconciliation manager to advise registry manager
- (1) The reconciliation manager must—
- (a) advise the registry manager of any new or deleted NSP identifier no later than 1 business day after receiving notice of its creation or deletion; and
- (b) advise the registry manager of any changes to supporting NSP information provided by a distributor in accordance with clause 26(4) no later than 1 business day after receiving the notice.
- (2) The registry manager must publish an updated schedule of all NSP identifiers and supporting information within 1 business day of receiving notice in accordance with subclause (1).
Compare: Electricity Governance Rules 2003 clause 13 schedule E1
Clause 30 Heading: amended, on 5 October 2017, by clause 243(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 30(1): amended, on 5 October 2017, by clause 243(2) and (3) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 30(2): amended, on 5 October 2017, by clause 243(3) and (4) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Schedule 11.2
cls 25 and 29 of Schedule 11.1Transfer of ICPs between distributors' networks
1
This Schedule applies if a distributor (the applicant distributor) wishes to change the record in the registry of an ICP that is not recorded as being usually connected to an NSP in the distributor's network, to transfer the ICP so that it is recorded as being usually connected to an NSP in the applicant distributor’s network.
Compare: Electricity Governance Rules 2003 clause 1 schedule E1A
Clause 1: amended, on 23 February 2015, by clause 75 of the Electricity Industry Participation Code Amendment (Distributed Generation) 2014.
Clause 1: amended, on 5 October 2017, by clause 244 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 1: amended, on 1 March 2022, by clause 38(1)(a) and (b) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
2
The applicant distributor must give written notice to the Authority of the transfer.
Compare: Electricity Governance Rules 2003 clause 2 schedule E1A
Clause 2: amended, on 5 October 2017, by clause 245 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
3
The notice must be in the prescribed form.
Compare: Electricity Governance Rules 2003 clause 3 schedule E1A
Clause 3: amended, on 5 October 2017, by clause 246 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
4
The notice must be given no later than 3 business days before the transfer takes effect.
Compare: Electricity Governance Rules 2003 clause 4 schedule E1A
Clause 4: amended, on 5 October 2017, by clause 247 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
5
The applicant distributor must give the Authority confirmation that the applicant distributor has received written consent to the proposed transfer from—
- (a) the distributor whose network is associated with the NSP to which the ICP is recorded as being connected immediately before the notice, except if the notice relates to the creation of an embedded network; and
- (b) every trader who trades electricity at any ICP nominated at the time of notice as being supplied from the same NSP to which the notice relates.
Compare: Electricity Governance Rules 2003 clause 5 schedule E1A
Clause 5(a): amended, on 23 February 2015, by clause 75 of the Electricity Industry Participation Code Amendment (Distributed Generation) 2014.
Clause 5: amended, on 5 October 2017, by clause 248 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
5A
For the purposes of clause 5, the distributor (under subclause 5(a)) or the trader (under subclause 5(b)) is deemed to have consented to the proposed transfer if the applicant distributor has requested in writing the distributor’s or trader’s written consent and—
- (a) the distributor or trader (as the case may be)—
- (i) has not provided written consent; and
- (ii) has not indicated in writing that it refuses to give written consent; and
- (b) more than 40 business days (or such other period as the applicant distributor agrees with the distributor or trader) have passed since the applicant distributor requested the distributor’s or trader’s written consent; and
- (c) during the 40 business days (or such other period as the applicant distributor agrees with the distributor or trader) the applicant distributor has—
- (i) checked the registry to ensure it has sought consent from the correct distributor or trader; and
- (ii) made reasonable endeavours to contact the distributor or trader and obtain a response.
Clause 5A: inserted, on 1 March 2022, by clause 38(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
5B
For the purposes of clause 5, the distributor (under subclause 5(a)) or the trader (under subclause 5(b)) must not unreasonably withhold consent to the proposed transfer.
Clause 5B: inserted, on 1 March 2022, by clause 38(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
6
If a notice relates to an embedded network, it must relate to every ICP on the embedded network.
Compare: Electricity Governance Rules 2003 clause 6 schedule E1A
Clause 6: amended, on 5 October 2017, by clause 249 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
7
The Authority must not authorise the change of any information in the registry if clauses 2 to 5 are not complied with.
Compare: Electricity Governance Rules 2003 clause 7 schedule E1A
Clause 7: amended, on 29 August 2013, by clause 10 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2013.
Clause 7: amended, on 15 May 2014, by clause 27 of the Electricity Industry Participation (Minor Code Amendments) Code Amendment 2014.
Clause 7: amended, on 5 October 2017, by clause 250 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
7A
Despite clause 7, the Authority may authorise the change if the applicant distributor has not given written notice to the Authority within the time frame required under clause 4, if—
- (a) the applicant distributor has complied with clauses 2, 3 and 5; and
- (b) the Authority considers that it has not been materially disadvantaged by the applicant distributor's failure to comply with clause 4.
Clause 7A: inserted, on 15 May 2014, by clause 28 of the Electricity Industry Participation (Minor Code Amendments) Code Amendment 2014.
Clause 7A: amended, on 5 October 2017, by clause 251 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
8
The notice must include any information requested by the Authority from time to time.
Compare: Electricity Governance Rules 2003 clause 8 schedule E1A
Clause 8: amended, on 5 October 2017, by clause 252 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
9
The registry manager must remove from the registry any information the registry manager has received under clause 7 of Schedule 11.1 if the information—
- (a) relates to an ICP for which an applicant distributor has given written notice of a transfer under this Schedule; and
- (b) was to come into effect after the date on which the Authority authorises the change of information in the registry under this Schedule.
Compare: Electricity Governance Rules 2003 clause 9 schedule E1A
Clause 9: replaced, on 5 October 2017, by clause 253 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
10
A transfer may take effect on a date that is before the date on which the notice is given only with the consent of the Authority.
Compare: Electricity Governance Rules 2003 clause 10 schedule E1A
Clause 10: amended, on 5 October 2017, by clause 254 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
11
Each reconciliation participant must take a validated meter reading or permanent estimate on the date a transfer becomes effective for use in the creation of the reconciliation participant’s submission file, unless the Authority authorises the reconciliation manager to provide additional seasonal adjustment shapes under clause 12.
Compare: Electricity Governance Rules 2003 clause 11 schedule E1A
12
The Authority may authorise the reconciliation manager to provide additional seasonal adjustment shapes for use in the creation of each reconciliation participant's submission file.
Compare: Electricity Governance Rules 2003 clause 12 schedule E1A
Schedule 11.3
cl 11.15Switching
Overview
Cross heading: inserted on 9 October 2015, by clause 5(1) of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
1A
Application of Schedule
- (1) This Schedule prescribes 3 processes for switching ICPs as follows:
- (a) a standard switch process that applies in the circumstances described in clause 1(1):
- (b) a switch move process that applies in the circumstances described in clause 8(1):
- (c) a gaining trader switch process that applies in the circumstances described in clause 13(1).
- (2) If a trader proposes switching an ICP, the trader must use one of the switch processes set out in this Schedule.
Clause 1A Heading: amended, on 1 November 2018, by clause 52(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
Clause 1A: inserted on 9 October 2015, by clause 5(2) of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
Clause 1A(2): inserted, on 1 November 2018, by clause 52(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
Standard switch process
Cross heading: amended on 9 October 2015, by clause 6 of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
1
Standard switch process for ICPs
- (1) A standard switch process applies only when a trader (the "gaining trader") has an arrangement with a customer or embedded generator to commence trading electricity with the customer or embedded generator at, or to otherwise assume responsibility under clause 11.18(1) for, an ICP at which another trader (the "losing trader") trades electricity, and the gaining trader switch process under clauses 13 to 16 does not apply.
- (1A) This clause and clauses 2 to 7 apply to a standard switch process.
- (2) If subpart 2 of Part 4A of the Fair Trading Act 1986 applies to an arrangement described in subclause (1),―
- (a) the gaining trader must identify the period within which the customer or embedded generator may cancel the arrangement in accordance with section 36M of the Fair Trading Act 1986; and
- b) for the purpose of this Schedule, the arrangement is deemed to come into effect on the day after the expiry of the period.
Compare: Electricity Governance Rules 2003 clauses 1.1A and 1.1B schedule E2
Clause 1 Heading: amended, on 29 August 2013, by clause 11(1) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2013.
Clause 1 Heading: amended on 9 October 2015, by clause 7(1) of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
Clause 1(1) and 1(1A): substituted on 9 October 2015, by clause 7(2) of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
Clause 1(1): amended, on 1 November 2018, by clause 53(1) and (2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
Clause 1(1)(a): substituted, on 29 August 2013, by clause 11(2) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2013.
Clause 1(2): amended, on 6 November 2014, by clause 7(3) of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
Clause 1(2)(a): amended, on 6 November 2014, by clause 7(4) of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
Clause 1(2)(a): amended, on 1 November 2018, by clause 53(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
2
Gaining trader advises registry manager of standard switch request
- (1) For each ICP to which a switch relates, the gaining trader must advise the registry manager of the switch no later than 2 business days after the arrangement to trade electricity with the customer or the embedded generator comes into effect.
- (2) The gaining trader must include in its advice to the registry manager—
- (a) [Revoked]
- (b) that the switch type is TR; and
- (c) 1 or more profile codes of a profile at the ICP.
Compare: Electricity Governance Rules 2003 clause 1.1 schedule E2
Clause 2 Heading: substituted on 9 October 2015, by clause 8(1) of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
Clause 2 Heading: amended, on 5 October 2017, by clause 255(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 2(1) and (2): amended, on 5 October 2017, by clause 255(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 2(1): amended, on 1 November 2018, by clause 54 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
Clause 2(2): inserted on 9 October 2015, by clause 8(2) of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
Clause 2(2)(a): revoked on 9 October 2015, by clause 4 of the Electricity Industry Participation Code Amendment (ICP Switching) 2015.
3
Losing trader response to standard switch request
- No later than 3 business days after the date on which the registry manager, under clause 22(a), makes written notice of a switch request available to the losing trader, the losing trader must,—
- (a) either—
- (i) acknowledge the switch request by providing the following information to the registry manager:
- (A) the proposed event date; and
- (B) a valid switch response code approved by the Authority; or
- (ii) provide the final information specified in clause 5(a) to (c) to complete the switch; or
- (i) acknowledge the switch request by providing the following information to the registry manager:
- (b) [Revoked]
- (c) request that the switch be withdrawn in accordance with clause 17.
- (a) either—
Compare: Electricity Governance Rules 2003 clause 1.2 schedule E2
Clause 3: substituted on 9 October 2015, by clause 9 of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
Clause 3: amended, on 5 October 2017, by clause 256 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 3: amended, on 1 March 2022, by clause 39(a) & (b) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
Clause 3(a): substituted on 9 October 2015, by clause 5(1) of the Electricity Industry Participation Code Amendment (ICP Switching) 2015.
Clause 3(b): revoked on 9 October 2015, by clause 5(2) of the Electricity Industry Participation Code Amendment (ICP Switching) 2015.
4
Event dates
- (1) The losing trader must establish event dates so that—
- (a) no event date is more than 10 business days after the date on which the registry manager, under clause 22(a), makes written notice available to the losing trader; and
- (b) in any 12 month period at least 50% of the event dates established by the losing trader are no more than 5 business days after the date on which the registry manager, under clause 22(a), makes written notice available to the losing trader.
- (2) For the purpose of determining whether it complies with subclause (1)(b), the losing trader may disregard every event date it has established for an ICP for which, on the date on which the registry manager, under clause 22(a), made written notice available to the losing trader, the losing trader had been responsible for less than 2 months.
Compare: Electricity Governance Rules 2003 clause 1.2A schedule E2
Clause 4: replaced, on 1 March 2022, by clause 40 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
Clause 4(1): amended on 9 October 2015, by clause 6 of the Electricity Industry Participation Code Amendment (ICP Switching) 2015.
Clause 4(1): amended, on 5 October 2017, by clause 257(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 4(1)(a): amended, on 15 May 2014, by clause 29 of the Electricity Industry Participation (Minor Code Amendments) Code Amendment 2014.
Clause 4(2): amended on 9 October 2015, by clause 10 of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
Clause 4(2): amended, on 5 October 2017, by clause 257(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 4(2): replaced, on 1 November 2018, by clause 55 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
5
Losing trader must provide final information
- If the losing trader has provided information under clause 3(a)(i) rather than under clause 3(a)(ii), no later than 5 business days after the event date, the losing trader must complete the switch by providing final information to the registry manager, including—
- (a) the event date; and
- (b) a switch event meter reading as at the event date for each meter or data storage device that is recorded in the registry with an accumulator type of C and a settlement indicator of Y; and
- (c) if the switch event meter reading is not a validated meter reading, the date of the last meter reading of the meter or data storage device described in paragraph (b).
Compare: Electricity Governance Rules 2003 clause 1.3 schedule E2
Clause 5: substituted on 9 October 2015, by clause 11 of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
Clause 5: amended on 9 October 2015, by clause 7 of the Electricity Industry Participation Code Amendment (ICP Switching) 2015.
Clause 5: amended, on 5 October 2017, by clause 258 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
6
Traders must use same reading
- (1) The losing trader and the gaining trader must both use the same switch event meter reading for the event date as determined by the following procedure:
- (a) if the switch event meter reading provided by the losing trader differs by less than 200 kWh from a value established by the gaining trader, the gaining trader must use the losing trader’s switch event meter reading; or
- (b) if the switch event meter reading provided by the losing trader differs by 200 kWh or more from a value established by the gaining trader, the gaining trader may dispute the switch event meter reading.
- (2) Despite subclause (1), subclause (3) applies if—
- (a) the losing trader trades electricity at the ICP through a metering installation with a submission type of non half hour in the registry; and
- (b) the gaining trader will trade electricity at the ICP through a metering installation with a submission type of half hour in the registry, as a result of the gaining trader’s arrangement to trade electricity with the customer or the embedded generator; and
- (c) a switch event meter reading provided by the losing trader under subclause (1) has not been obtained from an interrogation of a certified metering installation with an AMI flag of Y in the registry.
- (3) No later than 5 business days after the date on which the registry manager, under clause 22(d), makes written notice of switch completion information available to the gaining trader—
- (a) the gaining trader may provide the losing trader with a switch event meter reading obtained from an interrogation of a certified metering installation with an AMI flag of Y in the registry; and
- (b) the losing trader must use that switch event meter reading.
Compare: Electricity Governance Rules 2003 clause 1.4 schedule E2
Clause 6: amended on 9 October 2015, by clause 12(1) of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
Clause 6(a): amended on 9 October 2015, by clause 12(2) of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
Clause 6(b): substituted on 9 October 2015, by clause 12(3) of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
Clause 6(2) and (3): inserted on 9 October 2015, by clause 8 of the Electricity Industry Participation Code Amendment (ICP Switching) 2015.
Clause 6(2)(b): amended, on 1 November 2018, by clause 56 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
Clause 6(3): amended, on 5 October 2017, by clause 259 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 6(3): amended, on 1 March 2022, by clause 41 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
6A
Gaining trader disputes reading
- (1) If a gaining trader disputes a switch event meter reading under clause 6(1)(b), the gaining trader must, no later than 4 months after the date on which the registry manager made written notice under clause 22(d) of switch completion information available to the gaining trader, provide to the losing trader a revised switch event meter reading supported by 2 validated meter readings.
- (2) On receipt of a revised switch event meter reading from the gaining trader under subclause (1), the losing trader must either,—
- (a) if the losing trader accepts the revised switch event meter reading, or does not respond to the gaining trader, use the revised switch event meter reading; or
- (b) if the losing trader does not accept the revised switch event meter reading, advise the gaining trader (giving all relevant details) no later than 5 business days after receiving the revised switch event meter reading.
Clause 6A: inserted on 9 October 2015, by clause 13 of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
Clause 6A Heading: amended on 9 October 2015, by clause 9(a) of the Electricity Industry Participation Code Amendment (ICP Switching) 2015.
Clause 6A: amended on 9 October 2015, by clause 9(b) and (c) of the Electricity Industry Participation Code Amendment (ICP Switching) 2015.
Clause 6A: replaced, on 5 October 2017, by clause 260 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 6A(1): amended, on 1 February 2019, by clause 57 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
Clause 6A(1): replaced, on 1 March 2022, by clause 42 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
7
Disputes
- (1) A losing trader or a gaining trader may give written notice to the other trader that it disputes a switch event meter reading provided under clauses 1 to 6.
- (2) The dispute must be resolved in accordance with the disputes procedure in clause 15.29 (with all necessary amendments).
Compare: Electricity Governance Rules 2003 clause 1.5 schedule E2
Clause 7(1): amended on 9 October 2015, by clause 14 of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
Clause 7(1): amended, on 5 October 2017, by clause 261 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Switch move process
8
Switch move process for ICPs
- (1) A standard switch process applies only when a trader (the “gaining trader”) has an arrangement with a customer or embedded generator to commence trading electricity with the customer or embedded generator at, or to otherwise assume responsibility under clause 11.18(1) for, an ICP for which no trader has an agreement to trade electricity and the gaining trader switch process under clauses 13 to 16 does not apply.
- (1A) This clause and clauses 9 to 12 apply to a switch move process.
- (2) If subpart 2 of Part 4A of the Fair Trading Act 1986 applies to an arrangement described in subclause (1)―
- (a) the gaining trader must identify the period within which the customer or embedded generator may cancel the arrangement in accordance with section 36M of the Fair Trading Act 1986; and
- (b) for the purpose of this Schedule, the arrangement is deemed to come into effect on the day after the expiry of the period.
Compare: Electricity Governance Rules 2003 clauses 2.1A and 2.1B schedule E2
Clause 8 Heading: amended, on 29 August 2013, by clause 12(1) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2013.
Clause 8(1) and 8(1A): substituted on 9 October 2015, by clause 15 of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
Clause 8(1)(a): substituted, on 29 August 2013, by clause 12(2) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2013.
Clause 8(1): amended, on 1 November 2018, by clause 58(1) and (2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
Clause 8(2): amended, on 6 November 2014, by clause 15(2) of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
Clause 8(2)(a): amended, on 6 November 2014, by clause 15(3) of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
Clause 8(2)(a): amended, on 1 November 2018, by clause 58(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
9
Gaining trader informs registry manager of switch request
- (1) For each ICP to which a switch relates, the gaining trader must advise the registry manager of the switch request no later than 2 business days after the arrangement to trade electricity with the customer or the embedded generator comes into effect.
- (2) The gaining trader must include in its advice to the registry manager—
- (a) a proposed event date; and
- (b) that the switch type is MI; and
- (c) 1 or more profile codes of a profile at the ICP.
Compare: Electricity Governance Rules 2003 clause 2.1 schedule E2
Clause 9 Heading: amended, on 5 October 2017, by clause 262(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 9(1): amended, on 9 October 2015, by clause 16(1)(a) and 16)(1)(b) of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
Clause 9(1): amended, on 1 November 2018, by clause 59 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
Clause 9(2): inserted, on 9 October 2015, by clause 16(2) of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
Clause 9(1) and (2): amended, on 5 October 2017, by clause 262(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
10
Losing trader response to switch move request
- (1) The trader that is recorded in the registry as being responsible for an ICP that is subject to a switch request (the “losing trader”) must, no later than 5 business days after the date on which the registry manager makes written notice under clause 22(a) of the switch request available to the losing trader,—
- (a) if the losing trader accepts the event date proposed by the gaining trader, complete the switch by providing to the registry manager—
- (i) [Revoked]
- (ia) confirmation of the event date; and
- (ib) a valid switch response code approved by the Authority; and
- (ii) final information in accordance with clause 11; or
- (b) if the losing trader does not accept the event date proposed by the gaining trader, acknowledge the switch request to the registry manager and determine a different event date that—
- (i) is not earlier than the gaining trader’s proposed event date; and
- (ii) is no later than 10 business days after the date on which the registry manager, under clause 22(a), made written notice of the switch request available to the losing trader; or
- (c) request that the switch be withdrawn in accordance with clause 17.
- (a) if the losing trader accepts the event date proposed by the gaining trader, complete the switch by providing to the registry manager—
- (2) If the losing trader determines a different event date under subclause (1)(b), the losing trader must, no later than 10 business days after the date on which the registry manager made written notice referred to in subclause (1) available to the losing trader, also complete the switch by providing to the registry manager the information described in subclause (1)(a), but in that case the event date is the event date determined by the losing trader.
Compare: Electricity Governance Rules 2003 clause 2.2 schedule E2
Clause 10: substituted, on 9 October 2015, by clause 17 of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
Clause 10(1): amended, on 9 October 2015, by clause 10(1) of the Electricity Industry Participation Code Amendment (ICP Switching) 2015.
Clause 10(1): amended, on 5 October 2017, by clause 263(1), (2) and (3) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 10(1)(a)(i): revoked, on 9 October 2015, by clause 10(2)(a) of the Electricity Industry Participation Code Amendment (ICP Switching) 2015.
Clause 10(1)(a)(ia) and (ib): inserted, on 9 October 2015, by clause 10(2)(b) of the Electricity Industry Participation Code Amendment (ICP Switching) 2015.
Clause 10(1)(b): amended, on 9 October 2015, by clause 10(3) of the Electricity Industry Participation Code Amendment (ICP Switching) 2015.
Clause 10(1)(c): amended, on 9 October 2015, by clause 10(4) of the Electricity Industry Participation Code Amendment (ICP Switching) 2015.
Clause 10(2): amended, on 5 October 2017, by clause 263(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 10(2): amended, on 1 November 2018, by clause 60 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
Clause 10: replaced, on 1 March 2022, by clause 43 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
11
Losing trader must provide final information
- The losing trader must provide final information to the registry manager for the purposes of clause 10(1)(a)(ii), including—
- (a) the event date; and
- (b) a switch event meter reading as at the event date for each meter or data storage device that is recorded in the registry with an accumulator type of C and a settlement indicator of Y; and
- (c) if the switch event meter reading is not a validated meter reading, the date of the last meter reading of the meter or data storage device described in paragraph (b).
Compare: Electricity Governance Rules 2003 clause 2.3 schedule E2
Clause 11: substituted, on 9 October 2015, by clause 17 of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
Clause 11: amended, on 9 October 2015, by clause 11 of the Electricity Industry Participation Code Amendment (ICP Switching) 2015.
Clause 11: amended, on 5 October 2017, by clause 264 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
12
Gaining trader may change switch event meter reading
- (1) The gaining trader may use the switch event meter reading supplied by the losing trader or may, at its own cost, obtain its own switch event meter reading.
- (2) If the gaining trader elects to use the new switch event meter reading, the gaining trader must advise the losing trader of the new switch event meter reading and the event date to which it refers as follows:
- (a) if the switch event meter reading established by the gaining trader differs by less than 200 kWh from that provided by the losing trader, both traders must use the switch event meter reading provided by the gaining trader; or
- (b) if the switch event meter reading provided by the losing trader differs by 200 kWh or more from a value established by the gaining trader, the gaining trader may dispute the switch event meter reading.
- (2A) Despite subclauses (1) and (2), subclause (2B) applies if—
- (a) the losing trader trades electricity at the ICP through a metering installation with a submission type of non half hour in the registry; and
- (b) the gaining trader will trade electricity at the ICP through a metering installation with a submission type of half hour in the registry, as a result of the gaining trader’s arrangement with the customer or embedded generator; and
- (c) a switch event meter reading provided by the losing trader under subclause (1) has not been obtained from an interrogation of a certified metering installation with an AMI flag of Y in the registry.
- (2B) No later than 5 business days after the date on which the registry manager, under clause 22(d), makes written notice,—
- (a) the gaining trader may provide the losing trader with a switch event meter reading obtained from an interrogation of a certified metering installation with an AMI flag of Y in the registry; and
- (b) the losing trader must use that switch event meter reading
- (3) If the gaining trader disputes a switch event meter reading under subclause (2)(b), the gaining trader must, no later than 4 months after the date on which the registry manager, under clause 22(d), made written notice of switch completion information available to the gainer trader, provide to the losing trader a revised validated meter reading or a permanent estimate supported by 2 validated meter readings, and the losing trader must either,—
- (a) no later than 5 business days after receiving the switch event meter reading from the gaining trader, the losing trader, if it does not accept the switch event meter reading, must advise the gaining trader (giving all relevant details), and the losing trader and the gaining trader must use reasonable endeavours to resolve the dispute in accordance with the disputes procedure contained in clause 15.29 (with all necessary amendments); or
- (b) if the losing trader advises its acceptance of the switch event meter reading received from the gaining trader, or does not provide any response, the losing trader must use the switch event meter reading supplied by the gaining trader.
Compare: Electricity Governance Rules 2003 clause 2.4 schedule E2
Clause 12 Heading: amended, on 9 October 2015, by clause 18(1) of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
Clause 12(1) and (3): amended, on 9 October 2015, by clause 18(2) of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
Clause 12(2): substituted, on 9 October 2015, by clause 18(3) of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
Clause 12(2), (2B) and (3): amended, on 5 October 2017, by clause 265 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 12(2A) and (2B): inserted, on 9 October 2015, by clause 12 of the Electricity Industry Participation Code Amendment (ICP Switching) 2015.
Clause 12(2A)(b): amended, on 1 November 2018, by clause 61(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
Clause 12(2B): amended, on 1 March 2022, by clause 44(1)(a) and (b) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
Clause 12(3): amended, on 9 October 2015, by clause 18(4) of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
Clause 12(3): amended, on 1 February 2019, by clause 61(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
Clause 12(3): amended, on 1 March 2022, by clause 44(2)(a), (b) and (c) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
Clause 12(3)(a): amended, on 9 October 2015, by clause 18(5) of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
Clause 12(3)(b): amended, on 9 October 2015, by clause 18(6) of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
Gaining trader switch process
Cross heading: amended, on 9 October 2015, by clause 19 of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
13
Gaining trader switch processes
- (1) A gaining trader switch process applies only when a trader (the “gaining trader”) has an arrangement with a customer or embedded generator to―
- (a) trade electricity with the customer or embedded generator at an ICP at which another trader (the “losing trader”) trades electricity with the customer or embedded generator, and one of subparagraphs (i) to (iii) applies—
- (i) at the ICP, the gaining trader will trade electricity through a half-hour metering installation that is a category 3 or higher metering installation; or
- (ii) at the ICP—
- (A) the gaining trader will trade electricity through a half-hour metering installation, and in the registry the ICP will have a submission type of half hour and an AMI flag of “N”; and
- (B) the losing trader trades electricity through a non half-hour metering installation, and in the registry the ICP has a submission type of non half hour and an AMI flag of “N”; or
- (iii) at the ICP—
- (A) the gaining trader will trade electricity through a non half-hour metering installation, and the ICP will have a submission type of non half hour in the registry; and
- (B) the losing trader trades electricity through a half-hour metering installation, and in the registry the ICP has a submission type of half hour and an AMI flag of “N”; or
- (b) assume responsibility under clause 11.18(1) for an ICP described in subparagraph (a)(i), (a)(ii), or (a)(iii).
- (a) trade electricity with the customer or embedded generator at an ICP at which another trader (the “losing trader”) trades electricity with the customer or embedded generator, and one of subparagraphs (i) to (iii) applies—
- (1A) This clause and clauses 14 to 16 apply to a gaining trader switch process.
- (2) If subpart 2 of Part 4A of the Fair Trading Act 1986 applies to an arrangement described in subclause (1)―
- (a) the gaining trader must identify the period within which the customer or embedded generator may cancel the arrangement in accordance with section 36M of the Fair Trading Act 1986; and
- (b) for the purpose of this Schedule, the arrangement is deemed to come into effect on the day after the expiry of the period.
Compare: Electricity Governance Rules 2003 clauses 3.1 and 3.1A schedule E2
Clause 13 Heading: amended, on 9 October 2015, by clause 20(1) of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
Clause 13(1): amended, on 9 October 2015, by clause 20(2) of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
Clause 13(1): amended, on 1 November 2018, by clause 62(1)(a) and (b) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
Clause 13(1)(a): substituted, on 29 August 2013, by clause 13 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2013.
Clause 13(1)(a): replaced, on 1 February 2019, by clause 62(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
Clause 13(1)(a)(i): amended, on 9 October 2015, by clause 13(a) and (b) of the Electricity Industry Participation Code Amendment (ICP Switching) 2015.
Clause 13(1)(a)(i) and (1)(a)(ii): amended, on 5 October 2017, by clause 266 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 13(1)(b): amended, on 9 October 2015, by clause 20(3) of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
Clause 13(1)(b): amended, on 1 February 2019, by clause 62(3) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
Clause 13(1A): inserted, on 9 October 2015, by clause 20(4) of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
Clause 13(2): amended, on 6 November 2014, by clause 20(5) of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
Clause 13(2)(a): amended, on 6 November 2014, by clause 20(6) of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
Clause 13(2)(a): amended, on 1 November 2018, by clause 62(4) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
14
Gaining trader informs registry manager of switch request
- (1) For each ICP to which a switch relates, the gaining trader must advise the registry manager of the switch request no later than 3 business days after the arrangement to trade electricity with the customer or the embedded generator comes into effect.
- (2) The gaining trader must include in its advice to the registry manager—
- (a) a proposed event date; and
- (b) that the switch type is HH.
- (3) Unless subclause (4) applies, the proposed event date must be a date that is after the date on which the gaining trader advises the registry manager.
- (4) The proposed event date may be a date that is before the date on which the gaining trader advises the registry manager, if—
- (a) the proposed event date is in the same month as the date on which the gaining trader advises the registry manager; or
- (b) the proposed event date is no more than 90 days before the date on which the gaining trader advises the registry manager, and the losing trader and gaining trader agree on the proposed event date.
Compare: Electricity Governance Rules 2003 clause 3.2 schedule E2
Clause 14 Heading: amended, on 5 October 2017, by clause 267(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 14: amended, on 5 October 2017, by clause 267(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 14(1): amended, on 1 November 2018, by clause 63 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
Clause 14(1): amended, on 9 October 2015, by clause 21(1) of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
Clause 14(2), (3), and (4): inserted, on 9 October 2015, by clause 21(2) of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
15
Losing trader provides information
- No later than 3 business days after the date on which the registry manager, under clause 22(a), makes written notice available to the losing trader, must—
- (a) provide the registry manager with a valid switch response code approved by the Authority; or
- (b) request that the switch be withdrawn in accordance with clause 17.
Compare: Electricity Governance Rules 2003 clause 3.3 schedule E2
Clause 15: amended, on 9 October 2015, by clause 22(1) of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
Clause 15: amended, on 9 October 2015, by clause 14 of the Electricity Industry Participation Code Amendment (ICP Switching) 2015.
Clause 15: amended, on 5 October 2017, by clause 268 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 15: amended, on 1 March 2022, by clause 45(1) and (2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
Clause 15(a): amended, on 9 October 2015, by clause 22(2) of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
Clause 15(b): amended, on 9 October 2015, by clause 22(3) of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
16
Gaining trader obligations
- (1) The gaining trader must complete the switch by advising the registry manager of the event date no later than 3 business days after the date on which the registry manager, under clause 22(c), makes written notice of a valid switch response code available to the gaining trader.
- (2) If the ICP is being electrically disconnected or if metering equipment is being removed, the gaining trader must either—
- (a) give the losing trader or the metering equipment provider for the ICP an opportunity to interrogate the metering installation immediately before the ICP is electrically disconnected or the metering equipment is removed; or
- (b) carry out an interrogation and, no later than 5 business days after the metering installation is electrically disconnected or removed, advise the losing trader of—
- (i) the results of the interrogation; and
- (ii) the metering component numbers for each data channel in the metering installation.
Compare: Electricity Governance Rules 2003 clause 3.4 schedule E2
Clause 16 Heading: amended, on 9 October 2015, by clause 23(1) of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
Clause 16(1): amended, on 9 October 2015, by clause 23(2) of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
Clause 16(1): amended, on 9 October 2015, by clause 15 of the Electricity Industry Participation Code Amendment (ICP Switching) 2015.
Clause 16(1): amended, on 1 March 2022, by clause 46(a) and (b) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
Clause 16(1) and (2): amended, on 5 October 2017, by clause 269 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 16(2): inserted, on 9 October 2015, by clause 23(3) of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
Withdrawing a switch request
17
Withdrawal of switch requests
- A losing trader or gaining trader may request that a switch request be withdrawn at any time until the expiry of 2 months after the event date.
Compare: Electricity Governance Rules 2003 clause 3A schedule E2
Clause 17: amended, on 9 October 2015, by clause 24 of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
18
Withdrawing a switch request
- If a trader requests the withdrawal of a switch under clause 17, the following provisions apply:
- (a) the Authority must determine the valid codes for withdrawing a switch request (“withdrawal advisory codes”):
- (b) the Authority must publish the withdrawal advisory codes:
- (c) for each ICP, the trader withdrawing the switch request must provide the registry manager with the following information:
- (i) the participant identifier of the trader; and
- (ii) the withdrawal advisory code published by the Authority in accordance with paragraph (b):
- (d) no later than 5 business days after the date on which the registry manager, under clause 22(b), makes written notice available to the trader receiving the withdrawal, the trader must advise the registry manager that the switch withdrawal request is accepted or rejected. A switch withdrawal request must not become effective until accepted by the trader who received the withdrawal:
- (e) on receipt of a rejection notice from the registry manager in accordance with paragraph (d), a trader may re-submit a switch withdrawal request for an ICP in accordance with paragraph (c). All switch withdrawal requests must be resolved no later than 10 business days after the date of the initial switch withdrawal request:
- (f) if a trader requests that a switch request be withdrawn and the resolution of that switch withdrawal request results in the switch proceeding, no later than 2 business days after the date on which the registry manager, under clause 22(b), makes written notice available to the losing trader, the losing trader must comply with clauses 3, 5, 10 and 11 (whichever is appropriate) and the gaining trader must comply with clause 16.
Compare: Electricity Governance Rules 2003 clause 4 schedule E2
Clause 18(b): amended, on 21 September 2012, by clause 16(1) of the Electricity Industry Participation (Minor Amendments) Code Amendment 2012.
Clause 18(c)(i): amended, on 21 September 2012, by clause 16(2) of the Electricity Industry Participation (Minor Amendments) Code Amendment 2012.
Clause 18(c) to (f): amended, on 5 October 2017, by clause 270 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 18(d): amended, on 1 March 2022, by clause 47(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
Clause 18(d), (e), and (f): amended, on 9 October 2015, by clause 25 of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
Clause 18(f): amended, on 1 March 2022, by clause 47(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
Exchange of information
19
Participants to use file formats
- Participants who exchange information in accordance with this Schedule must use the file formats determined and published by the Authority.
Compare: Electricity Governance Rules 2003 clause 5.1 schedule E2
20
Method of exchanging files
- (1) The Authority may, from time to time, after consultation with participants, do all or any of the following:
- (a) determine the method by which participants exchange information:
- (b) determine the file formats that participants must use to exchange information:
- (c) alter the file formats or the method by which participants exchange information.
- (2) The Authority must publish the file formats.
Compare: Electricity Governance Rules 2003 clause 5.2 schedule E2
Clause 20(1): substituted, on 15 May 2014, by clause 30 of the Electricity Industry Participation (Minor Code Amendments) Code Amendment 2014.
21
Metering information
- For each interrogation or switch event meter reading carried out in accordance with this Schedule,—
- (a) the trader who carries out the interrogation or switch event meter reading must ensure that the interrogation is as accurate as possible, or that the switch event meter reading is fair and reasonable (as the case may be); and
- (b) the cost of each interrogation or switch event meter reading must be met as follows:
- (i) for each interrogation or switch event meter reading carried out in accordance with clauses 5(b) or 11(b) or (c), the cost must be met by the losing trader; and
- (ii) in every other case, the cost must be met by the gaining trader.
Compare: Electricity Governance Rules 2003 clause 5.3 schedule E2
Clause 21: amended, on 9 October 2015, by clause 26(1) of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
Clause 21(a): amended, on 9 October 2015, by clause 26(2) of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
Clause 21(b), and (c): substituted, on 9 October 2015, by clause 26(3) of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
22
Registry manager notices
- The registry manager must provide notice to participants required by this Schedule as follows:
- (a) on receipt of information about a switch request in accordance with clauses 2, 9 and 14, the registry manager must make written notice available to the losing trader of the information received:
- (b) on receipt of information about a withdrawal request in accordance with clauses 18(c) and (d), the registry manager must make written notice available to the other relevant trader of the information received:
- (c) on receipt of information about a switch acknowledgement in accordance with clauses 3(a) and 15, the registry manager must make written notice available to the gaining trader of the information received:
- (d) on receipt of information about a switch completion in accordance with clauses 3(a)(ii), 5, 10 and 16, the registry manager must make written notice available to the gaining trader, the losing trader, the metering equipment provider, and the relevant distributor of the information received.
Compare: Electricity Governance Rules 2003 clause 5.4 schedule E2
Clause 22 Heading: amended, on 5 October 2017, by clause 271(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 22: amended, on 5 October 2017, by clause 271(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 22(a), (b), (c) and (d): amended, on 1 March 2022, by clause 48 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
Clause 22(d): amended, on 29 August 2013, by clause 14 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2013.
Clause 22(d): amended, on 9 October 2015, by clause 16 of the Electricity Industry Participation Code Amendment (ICP Switching) 2015.
Schedule 11.4
cls 11.8A and 11.15AMetering equipment provider switching and registry metering records
Schedule 11.4: inserted on 29 August 2013, by clause 22 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011.
1
Metering equipment provider receives notice for ICP identifier
- (1) Within 10 business days of being advised by the registry manager under clause 11.18A, a gaining metering equipment provider,—
- (a) must, if it intends to accept responsibility for each metering installation for the ICP—
- (i) enter into an arrangement with the trader; and
- (ii) advise the registry manager in the prescribed form that it accepts responsibility for each metering installation for the ICP and of the proposed date on which the metering equipment provider will assume responsibility for each metering installation for the ICP; or
- (b) may, if it intends to decline responsibility for each metering installation for the ICP, advise the registry manager in the prescribed form that it declines to accept responsibility for each metering installation for the ICP.
- (a) must, if it intends to accept responsibility for each metering installation for the ICP—
- (2) The registry manager must, within 1 business day of a metering equipment provider advising under subclause (1)(b) that it declines to accept responsibility for each metering installation for the ICP, advise the trader of the declinature.
- (3) The registry manager must, within 1 business day of a gaining metering equipment provider advising of acceptance under subclause (1)(a), advise the following participants for the ICP of the acceptance and proposed date on which the gaining metering equipment provider will assume responsibility for each metering installation for the ICP:
- (a) the trader; and
- (b) the distributor; and
- (c) if relevant, the losing metering equipment provider.
Clause 1 Heading: amended, on 5 October 2017, by clause 272(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 1: amended, on 5 October 2017, by clause 272(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 1(1): amended, on 29 August 2013, by clause 49 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).
Clause 1(1)(b): amended, on 1 November 2018, by clause 64 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
2
Gaining metering equipment provider to advise registry manager of registry metering records
- If the metering equipment provider who is responsible for a metering installation for an ICP changes, the metering equipment provider must, within 15 business days of becoming the metering equipment provider for the metering installation, advise the registry manager of the registry metering records for the metering installation.
Clause 2 Heading: amended, on 5 October 2017, by clause 273(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 2: amended, on 5 October 2017, by clause 273(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
3
Metering equipment provider to advise registry manager of changes to registry metering records
- If a metering equipment provider has an arrangement with a trader at an ICP that is not also an NSP, the metering equipment provider must advise the registry manager of the registry metering records, or any change to the registry metering records, for each metering installation for which it is responsible at the ICP, no later than—
- (a) [Revoked]
- (b) [Revoked]
- (c) if updating the registry metering records in accordance with clause 8(11)(b) of Schedule 10.6, 10 business days following the most recent unsuccessful interrogation; or
- (d) if updating the registry metering records in accordance with clause 8(13) of Schedule 10.6, 3 business days following—
- (i) the expiry of the time period under clause 8(12) of Schedule 10.6; or
- (ii) the date on which the metering equipment provider determines in an investigation under clause 8(11)(a) of Schedule 10.6 that it cannot restore communications or fully download the raw meter data; or
- (e) in all other cases, 10 business days following:
- (i) the electrical connection of an ICP that is not also an NSP; or
- (ii) any subsequent change in any matter covered by the metering records other than a change to which subparagraphs (c) and (d) apply.
Clause 3 Heading: amended, on 5 October 2017, by clause 274(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 3: amended, on 5 October 2017, by clause 274(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 3 amended, on 1 November 2018, by clause 65(a), (b) and (c) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
Clause 3 amended, on 1 February 2021, by clause 46(1) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.
Clause 3(a): amended, on 29 August 2013, by clause 50 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).
Clause 3(a): amended, on 1 November 2018, by clause 65(d) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
Clause 3(a) revoked, on 1 February 2021, by clause 46(2) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.
Clause 3(b): amended, on 1 November 2018, by clause 65(e) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
Clause 3(b) revoked, on 1 February 2021, by clause 46(2) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.
Clause 3(c), (d) and (e) inserted, on 1 February 2021, by clause 46(3) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.
4
Registry manager requirement to advise
- The registry manager must, within 1 business day of being advised—
- (a) under clauses 2 or 3, advise the trader and distributor of the registry metering records:
- (b) under clauses 3 or 6, advise—
- (i) the trader and distributor of the details of the change to the registry metering records; and
- (ii) the losing metering equipment provider of the date of change of the metering equipment provider for the ICP identifier.
Clause 4 Heading: amended, on 5 October 2017, by clause 275(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 4: amended, on 5 October 2017, by clause 275(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
5
Changes to registry metering records for ICP identifier
- The registry manager must, within 1 business day of being advised of 1 or more of the following changes relating to an ICP identifier record, advise the metering equipment provider of the change:
- (a) the trader participant identifier:
- (b) the distributor participant identifier:
- (c) the settlement type:
- (d) the status of the ICP.
Clause 5 Heading: amended, on 5 October 2017, by clause 276(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 5: amended, on 5 October 2017, by clause 276(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
6
Correction of errors in registry
- (1) A metering equipment provider must, by 0900 hours on the 13th business day of each reconciliation period, obtain the following information from the registry:
- (a) a list of the ICP identifiers for the ICPs for the metering installations for which the metering equipment provider is recorded in the registry as being responsible; and
- (b) the registry metering records for each ICP identifier obtained under paragraph (a).
- (2) A metering equipment provider must, as soon as reasonably practicable but not later than 5 business days after it obtains the information under subclause (1), compare the information obtained with its own records.
- (3) If the metering equipment provider finds a discrepancy between the information obtained under subclause (1) and its own records, the metering equipment provider must, within 5 business days of becoming aware of the discrepancy,—
- (a) correct its records that are in error; and
- (b) advise the registry manager of any necessary changes to the registry metering records.
Clause 6(3)(b): amended, on 5 October 2017, by clause 277 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 6(3)(b): amended, on 1 November 2018, by clause 66 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
7
Metering equipment provider to provide registry metering records to registry manager
- (1) A metering equipment provider must, if required under this Part, provide to the registry manager the information indicated in Table 1 as being "Required", in the prescribed form, for each metering installation for which it is responsible.
- (1A) Despite subclause (1) a metering equipment provider is not required to provide to the registry manager the information indicated in rows 23 to 30 of Table 1 as being "Required", if the information is used only for the purpose of a distributor direct billing consumers on its network.
Clause 7(1A) inserted, on 1 February 2021, by clause 47 of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.
- (2) Despite anything to the contrary in this Code (except clause 11.2) the metering equipment provider must—
- (a) provide the information set out in Table 1 indicated as being required for interim certified metering installations to the registry manager for all category 1 metering installations for which it is responsible; and
- (b) ensure that the registry metering records provided in accordance with this clause are, for not less than 50% of the category 1 metering installations for which it is responsible, complete, accurate, not misleading or deceptive, and not likely to mislead or deceive, by no later than 1 October 2014; and
- (c) ensure that the registry metering records provided in accordance with this clause are, for each category 1 metering installation for which it is responsible, complete, accurate, not misleading or deceptive, and not likely to mislead or deceive, by no later than 1 April 2015.
- (3) The metering equipment provider must derive the information provided under subclause (2)(a) from—
- (a) the metering equipment provider’s metering records; or
- (b) the metering records contained within the current trader’s system.
Clause 7 Heading: amended, on 5 October 2017, by clause 278(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 7(1) and 2(a): amended, on 5 October 2017, by clause 278(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 7(2): amended, on 29 August 2013, by clause 51 of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).
No | Registry term | Description | Fully certified metering installation | Interim certified metering installation |
---|---|---|---|---|
For each ICP identifier | ||||
1 | the metering equipment provider participant identifier | participant identifier | Required | Required |
For each metering installation for an ICP | ||||
2 | metering installation number | a sequential number that is unique to the ICP's identifier, to identify the metering installation | Required | Required |
3 | highest metering category | the category recorded in the metering installation certification report | Required | Required |
4 | metering installation location code | a code from the list of codes in the registry, that identifies the location of the metering installation on a premises | Required | Required |
5 | the ATH participant identifier | the participant identifier of the ATH who certified the metering installation | Required | Optional |
6 | metering installation certification type | the certification type of the metering installation which must be half hour or non half hour as identified in the metering installation certification report or, where both half hour and non half hour are specified as the certification type in the metering installation certification report, must be one of those certification types. | Required | Required |
7 | metering installation certification date | the effective certification date identified in the metering installation certification report | Required | Optional |
8 | the metering installation certification expiry date | the metering installation certification expiry date, identified in the metering installation certification report, or the date that the metering installation certification is cancelled | Required | Required |
9 | control device certification | confirmation that the control device used in the metering installation is included in the metering installation certification report | Required | Optional |
10 | certification variations |
(a) Does an exemption under the Act for the metering installation apply? (b) Has the alternate measuring transformer certification process been used? |
Required | Optional |
11 | certification variations expiry date |
the earlier of the expiry date of any certification variation under item 10 | Required | Optional |
12 | certification number |
the certification number assigned to a metering installation’s certification | Required | Optional |
13 | maximum interrogation cycle |
the maximum interrogation cycle for the metering installation included in its certification report |
Required | Required |
14 | price code | if the metering equipment provider considers it relevant, an identifier that may be used to indicate the price that would apply to a lease for the use of the metering installation | Optional | Optional |
The following details for each metering component in the metering installation for each ICP | ||||
15 | metering component type | an identifier used to identify the type of metering component in the metering installation selected from the list of codes in the registry | Required | Required |
16 | metering component identifier | an identifier visible on the installed metering component that is either the manufacturer's serial number or the owner's component asset number | Required |
Required for Optional for all other metering components. |
17 | meter or data storage device type | an identifier used to identify the type of meter or data storage device in the metering installation, which may be half hour, non half hour, or prepay selected from the list of codes in the registry | Required for meter or data storage device. | Required for meter or data storage device. |
18 | AMI type |
an identifieir to identify if the metering component is an advanced metering infrastructure device and the metering equipment provider's back office is the services access interface |
Required for meter or data storage device. Optional for all other metering components. |
Required for meter or data storage device. Optional for all other metering components. |
19 | registry compensation factor | the mathematical product of all compensation factors that the trader must apply to transform the raw meter data into volume information | Required for meter or data storage device. Optional for all other metering components. | Required for meter or data storage device. Optional for all other metering components. |
20 | owner of a metering component |
a free text field to identify the owner of a metering component, which may be a participant identifier if the owner is a participant | Optional | Optional |
21 | removal date of a meter or data storage device | a date that a meter or data storage device is removed | Optional for meter or data storage device | Optional for meter or data storage device |
The following details for each metering component identified in rows 15 to 21 above | ||||
22 | metering component type | the metering component type identifier selected from the list of codes in the registry | Required for meter or data storage device that returns any 1 or more of the following values as a result of an interrogation: (a) active energy: (b) reactive energy: (c) apparent energy: (d) apparent power. Optional for all other metering components. |
Required for meter or data storage device that returns any 1 or more of the following values as a result of an interrogation: (a) active energy: (b) reactive energy: (c) apparent energy: (d) apparent power. Optional for all other metering components. |
23 | register number | a sequential number that identifies each data channel that is present in the metering component | Required (except where clause 7(1A) of this Schedule applies) for meter or data storage device that returns any 1 or more of the following values as a result of an interrogation: (a) active energy: (b) reactive energy: (c) apparent energy: (d) apparent power. Optional for all other metering components. |
Required (except where clause 7(1A) of this Schedule applies) for meter or data storage device that returns any 1 or more of the following values as a result of an interrogation: |
24 | number of dials | the number of dials or digits that relate to the data channel | Required (except where clause 7(1A) of this Schedule applies) for meter or data storage device that returns any 1 or more of the following values as a result of an interrogation: (a) active energy: (b) reactive energy: (c) apparent energy: (d) apparent power. Optional for all other metering components. |
Required (except where clause 7(1A) of this Schedule applies) for meter or data storage device that returns any 1 or more of the following values as a result of an interrogation: (a) active energy: (b) reactive energy: (c) apparent energy: (d) apparent power. Optional for all other metering components. |
25 | register content code | an identifier for the contents of a channel or a data channel, selected from a list in the registry | Required (except where clause 7(1A) of this Schedule applies) for meter or data storage device that returns any 1 or more of the following values as a result of an interrogation: (a) active energy: (b) reactive energy: (c) apparent energy: (d) apparent power. Optional for all other metering components. |
Required (except where clause 7(1A) of this Schedule applies) for meter or data storage device that returns any 1 or more of the following values as a result of an interrogation: (a) active energy: (b) reactive energy: (c) apparent energy: (d) apparent power. Optional for all other metering components. |
26 | period of availability | an identifier for the period of availability for which a control device is configured, selected from a list in the registry |
Required (except where clause 7(1A) of this Schedule applies) for meter or data storage device that returns any 1 or more of the following values as a result of an interrogation: |
Required (except where clause 7(1A) of this Schedule applies) for meter or data storage device that returns any 1 or more of the following values as a result of an interrogation: (a) active energy: (b) reactive energy: (c) apparent energy: (d) apparent power. Optional for all other metering components. |
27 | unit of measurement | an identifier for the units recorded in a data channel, selected from a list in the registry | Required (except where clause 7(1A) of this Schedule applies) for meter or data storage device that returns any 1 or more of the following values as a result of an interrogation: (a) active energy: (b) reactive energy: (c) apparent energy: (d) apparent power. Optional for all other metering components. |
Required (except where clause 7(1A) of this Schedule applies) for meter or data storage device that returns any 1 or more of the following values as a result of an interrogation: (a) active energy: (b) reactive energy: (c) apparent energy: (d) apparent power. Optional for all other metering components. |
28 | energy flow direction | an identifier for the import or export recording in the data channel, selected from a list in the registry | Required (except where clause 7(1A) of this Schedule applies) for meter or data storage device that returns any 1 or more of the following values as a result of an interrogation: (a) active energy: (b) reactive energy: (c) apparent energy: (d) apparent power. Optional for all other metering components. |
Required (except where clause 7(1A) of this Schedule applies) for meter or data storage device that returns any 1 or more of the following values as a result of an interrogation: (a) active energy: (b) reactive energy: (c) apparent energy: (d) apparent power. Optional for all other metering components. |
29 | accumulator type | an identifier for either absolute or cumulative recording in the data channel, selected from a list in the registry | Required (except where clause 7(1A) of this Schedule applies) for meter or data storage device that returns any 1 or more of the following values as a result of an interrogation: (a) active energy: (b) reactive energy: (c) apparent energy: (d) apparent power. Optional for all other metering components. |
Required (except where clause 7(1A) of this Schedule applies) for meter or data storage device that returns any 1 or more of the following values as a result of an interrogation: (a) active energy: (b) reactive energy: (c) apparent energy: (d) apparent power. Optional for all other metering components. |
30 | settlement indicator | an identifier determined as follows: (a) if the relevant meter or data storage device has an AMI flag of "Y", the cumulative data channel identifier must be "Y" and the other data channel identifiers must be "N"; and (b) for any other meter or data storage device, or for a control device, the data channel identifier must be the appropriate identifier selected from the list in the registry |
Required (except where clause 7(1A) of this Schedule applies) for meter or data storage device that returns any 1 or more of the following values as a result of an interrogation: (a) active energy: (b) reactive energy: (c) apparent energy: (d) apparent power. Optional for all other metering components. |
Required (except where clause 7(1A) of this Schedule applies) for meter or data storage device that returns any 1 or more of the following values as a result of an interrogation: (a) active energy: (b) reactive energy: (c) apparent energy: (d) apparent power. Optional for all other metering components. |
31 | event reading | the event meter read of a meter or data storage device | Optional | Optional |
Table 1: row 6, column 2 amended, on 5 October 2017, by clause 279(a) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Table 1: row 6, column 3 amended, on 1 February 2021, by clause 48(a) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.
Table 1: row 16 amended, on 29 August 2013, by clause 52(1) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).
Table 1: row 18, column 3 amended, on 1 February 2021, by clause 48(b) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.
Table 1: row 19 amended, on 29 August 2013, by clause 52(2) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).
Table 1: row 19, column 2 amended, on 1 February 2021, by clause 48(c) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.
Table 1: row 19, column 3 replaced, on 1 February 2021, by clause 48(c) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.
Table 1: row 21 amended, on 29 August 2013, by clause 52(3) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 2).
Table 1: row 21 replaced, on 5 October 2017, by clause 279(b) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Table 1: row 23 amended, on 15 May 2014, by clause 31 of the Electricity Industry Participation (Minor Code Amendments) Code Amendment 2014.
Table 1: row 30 amended, on 29 August 2013, by clause 5(1) of the Electricity Industry Participation (Metering Arrangements) Code Amendment 2011, Amendment 2013 (No 3).
Table 1: rows 22 to 30 substituted, on 1 February 2016, by clause 45 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2015.
Table 1: rows 23 to 30, columns 4 and 5 amended, on 1 February 2021, by clause 48(d) of the Electricity Industry Participation Code Amendment (Metering and Related Registry Processes) 2020.
Schedule 11.5
cl 11.15CProcess for trader or retailer event of default
Schedule 11.5: inserted, on 16 December 2013, by clause 7 of the Electricity Industry Participation (Managing Retailer Default Situations) Code Amendment 2013.
Schedule 11.5, heading: amended, on 28 February 2015, by clause 8 of the Electricity Industry Participation Code Amendment (Trader Default) 2014.
Schedule 11.5, heading: amended, on 15 May 2025, by clause 9(1) of the Electricity Industry Participation Code Amendment (Retailer Default) 2025.
1
Purpose
- The purpose of this Schedule is to set out the process that the Authority and each participant must comply with when this Schedule applies in accordance with clause 11.15C.
Clause 1: amended, on 28 February 2015, by clause 9 of the Electricity Industry Participation Code Amendment (Trader Default) 2014.
Clause 1: amended, on 24 March 2015, by clause 6 of the Electricity Industry Participation Code Amendment (Settlement and Prudential Security) 2014.
Clause 1: amended, on 1 July 2025, by clause 18 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2025.
2
Notice to trader or retailer who has committed event of default
- (1) The Authority must give written notice to a defaulting trader or defaulting retailer who has committed an event of default of the kind referred to in clause 11.15C that—
- (a) the defaulting trader or defaulting retailer must—
- (i) remedy the event of default; or
- (ii) for a trader that has committed an event of default under clause 14.41(1)(a) or (b) or (f) or (h) or (i), assign its rights and obligations under every contract under which a customer of the defaulting trader purchases electricity from the defaulting trader to another trader, and assign to another trader all ICPs for which the defaulting trader is recorded in the registry as being responsible; or
- (iii) for a retailer that has committed an event of default under clause 14.41(1)(j), assign its rights and obligations under every contract under which a customer of the retailer purchases electricity from the retailer to a trader; and
- (b) if the defaulting trader or defaulting retailer does not comply with the requirements set out in paragraph (a) within 7 days of the notice, clause 4 will apply.
- (a) the defaulting trader or defaulting retailer must—
- (2) The Authority may give written notice to the defaulting trader or defaulting retailer requiring the defaulting trader or defaulting retailer to provide to the Authority, within a time specified by the Authority, information about the defaulting trader's or defaulting retailer’s customers.
- (3) The defaulting trader or defaulting retailer must provide the information requested by the Authority under subclause (2) within the time specified by the Authority.
Clause 2, heading: amended, on 28 February 2015, by clause 10(1) of the Electricity Industry Participation Code Amendment (Trader Default) 2014.
Clause 2, heading: amended, on 15 May 2025, by clause 9(2) of the Electricity Industry Participation Code Amendment (Retailer Default) 2025.
Clause 2(1): amended, on 28 February 2015, by clause 10(2) of the Electricity Industry Participation Code Amendment (Trader Default) 2014.
Clause 2(1): amended, on 24 March 2015, by clause 7 of the Electricity Industry Participation Code Amendment (Settlement and Prudential Security) 2014.
Clause 2(1)(a)(ii): amended, on 1 November 2018, by clause 67(a) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
Clause 2(1): amended, on 15 May 2025, by clause 9(3) of the Electricity Industry Participation Code Amendment (Retailer Default) 2025.
Clause 2(2): amended, on 28 February 2015, by clause 10(3) of the Electricity Industry Participation Code Amendment (Trader Default) 2014.
Clause 2(2): amended, on 1 November 2018, by clause 67(b) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
Clause 2(2): amended, on 15 May 2025, by clause 9(4) of the Electricity Industry Participation Code Amendment (Retailer Default) 2025.
Clause 2(3): amended, on 28 February 2015, by clause 10(4) of the Electricity Industry Participation Code Amendment (Trader Default) 2014.
Clause 2(3): amended, on 15 May 2025, by clause 9(5) of the Electricity Industry Participation Code Amendment (Retailer Default) 2025.
3A
Authority may require notifying trader to provide information
- (1) The Authority may, by notice in writing to the trader that notified the Authority under clause 14.41(1)(j), require the trader to provide to the Authority the information specified in the notice about the defaulting retailer’s ICPs within the period specified in the notice.
- (2) If the trader holds the information, the trader must provide the information to the Authority within the time specified by the Authority.
Clause 3A: inserted, on 15 May 2025, by clause 9(6) of the Electricity Industry Participation Code Amendment (Retailer Default) 2025.
3
Authority may require distributor, registry manager, and metering equipment provider to provide information
- (1) The Authority may, by notice in writing to a distributor on whose network a defaulting trader trades electricity, require the distributor to provide to the Authority the information specified in the notice about the defaulting trader's customers within the period specified in the notice.
- (2) If the distributor holds the information, the distributor must provide the information to the Authority within the time specified by the Authority.
- (3) The Authority may, by notice in writing to the registry manager, require the registry manager to provide to the Authority the information, specified in the notice, about ICPs for which a defaulting trader is recorded in the registry as being responsible, within the period specified in the notice.
- (4) If the registry manager holds the information, the registry manager must provide the information to the Authority within the time specified by the Authority.
- (5) The Authority may, by notice in writing to a metering equipment provider who is recorded in the registry as the metering equipment provider for an ICP for which a defaulting trader is responsible, require the metering equipment provider to provide to the Authority the information, specified in the notice, about the ICPs for which the defaulting trader is recorded in the registry as being responsible, within the period specified in the notice.
- (6) If the metering equipment provider holds the information, the metering equipment provider must provide the information to the Authority within the time specified by the Authority.
Clause 3 Heading: amended, on 5 October 2017, by clause 281(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 3 Heading: amended, on 7 September 2020, by clause 4(1) of the Electricity Industry Participation Code Amendment (Improving Trader Default Process) 2020.
Clause 3(1): amended, on 28 February 2015, by clause 11(1) of the Electricity Industry Participation Code Amendment (Trader Default) 2014.
Clause 3(1): amended, on 1 November 2018, by clause 68 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
Clause 3(1): amended, on 7 September 2020, by clause 4(2) of the Electricity Industry Participation Code Amendment (Improving Trader Default Process) 2020.
Clause 3(2): amended, on 7 September 2020, by clause 4(3) of the Electricity Industry Participation Code Amendment (Improving Trader Default Process) 2020.
Clause 3(3): amended, on 28 February 2015, by clause 11(2) of the Electricity Industry Participation Code Amendment (Trader Default) 2014.
Clause 3(3) and (4): replaced, on 7 September 2020, by clause 4(4) and (5) of the Electricity Industry Participation Code Amendment (Improving Trader Default Process) 2020.
Clause 3(3) and (4): amended, on 5 October 2017, by clause 281(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 3(5) and (6): inserted, on 7 September 2020, by clause 4(6) of the Electricity Industry Participation Code Amendment (Improving Trader Default Process) 2020.
4
Failure by defaulting trader or defaulting retailer to remedy event of default
- (1) This clause applies if—
- (a) 7 days or more have elapsed since the Authority gave notice to the defaulting trader or defaulting retailer under clause 2(1); and
- (b) the Authority considers that—
- (i) the defaulting trader or defaulting retailer has not remedied the event of default or, in the case of an event of default under clause 14.41(1)(b) in respect of which there is an unresolved invoice dispute under clause 14.25, has not reached an agreement with the Authority to resolve the event of default; and
- (ii) the defaulting trader or defaulting retailer still has 1 or more contracts under which a customer of the defaulting trader or defaulting retailer purchases electricity from the defaulting trader or defaulting retailer or is still recorded in the registry as being responsible for 1 or more ICPs.
- (2) The Authority must—
- (a) give written notice to the defaulting trader or defaulting retailer that the Authority considers that this clause applies; and
- (b) unless the Authority considers there is good reason not to, attempt to advise customers of the defaulting trader or defaulting retailer that the defaulting trader or defaulting retailer has committed an event of default and one or more of the following:
- (i) [Revoked]
- (ii) the customer should enter into a contract for the purchase of electricity with another trader or retailer by the date that is 14 days after the day on which the Authority gave written notice to the defaulting trader or defaulting retailer under clause 2(1):
- (iii) if the customer fails to enter into a contract with another trader or retailer by that date, the Authority may assign the defaulting trader's or defaulting retailer’s rights and obligations under the customer’s contract with the defaulting trader or defaulting retailer to another trader under clause 5:
- (iv) any other information the Authority considers appropriate.
- (3) [Revoked]
- (4) [Revoked]
Clause 4, heading: amended, on 28 February 2015, by clause 12(1) of the Electricity Industry Participation Code Amendment (Trader Default) 2014.
Clause 4(1): amended, on 28 February 2015, by clause 12(2) of the Electricity Industry Participation Code Amendment (Trader Default) 2014.
Clause 4(1)(a): amended, on 7 September 2020, by clause 5(1) of the Electricity Industry Participation Code Amendment (Improving Trader Default Process) 2020.
Clause 4(1)(b)(i): amended, on 24 March 2015, by clause 8 of the Electricity Industry Participation Code Amendment (Settlement and Prudential Security) 2014.
Clause 4(1)(b)(i): amended, on 1 April 2025 by clause 20 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2025.
Clause 4(1)(b)(ii): amended, on 1 November 2018, by clause 69(a) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
Clause 4(2)(a): amended, on 28 February 2015, by clause 12(3)(a) of the Electricity Industry Participation Code Amendment (Trader Default) 2014.
Clause 4(2)(a) and (b): amended, on 5 October 2017, by clause 282 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 4(2)(b): substituted, on 28 February 2015, by clause 12(3)(b) of the Electricity Industry Participation Code Amendment (Trader Default) 2014.
Clause 4(2)(b): amended, on 1 November 2018, by clause 69(b) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
Clause 4(2)(b): replaced, on 7 September 2020, by clause 5(2) of the Electricity Industry Participation Code Amendment (Improving Trader Default Process) 2020.
Clause 4(2)(b)(ii) and (iii): amended, on 1 November 2018, by clause 69(c) and (d) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
Clause 4(3) and 4(4): revoked, on 28 August 2015, by clause 12(4) of the Electricity Industry Participation Code Amendment (Trader Default) 2014.
Clause 4, heading and sub paragraphs (1) and (2): amended, on 15 May 2025, by clause 9(7) of the Electricity Industry Participation Code Amendment (Retailer Default) 2025.
4A
Trader to provide information about NSPs and ICPs at which it cannot trade
- (1) If the Authority gives written notice to a trader under clause 4, the Authority must give written notice to each trader (except the defaulting trader) that it must provide the information specified in subclause (2) to the registry manager by no later than 1600 on the business day following the day on which the notice under this subclause was given.
- (2) The information that a trader must provide to the registry manager is—
- (a) the NSPs at which the trader cannot trade because it does not have an arrangement with the relevant distributor on whose network the NSPs are located to trade at the NSP; and
- (b) the ICPs at which the trader cannot trade for any of the following reasons:
- (i) the type of each meter at the ICPs (for example, half hour, non half hour, or prepay):
- (ii) the price category code assigned to the ICPs:
- (iii) the metering installation category of the metering installation at the ICPs:
- (iv) the installation type code assigned to the ICPs; and
- (c) the reasons, being 1 or more reasons specified in paragraph (a) and (b), for the trader being unable to trade at the NSPs or ICPs.
- (3) A trader must comply with a notice given to it under subclause (1).
Clause 4A: inserted, on 28 August 2015, by clause 13 of the Electricity Industry Participation Code Amendment (Trader Default) 2014.
Clause 4A(1): amended, on 5 October 2017, by clause 283 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
4B
Authority may direct registry manager not to process certain ICP switching activities
- (1) If the Authority gives written notice to a trader under clause 2, the Authority may, by written notice to the registry manager, direct the registry manager not to—
- (a) process the initiation or completion of the switch of any ICP to the defaulting trader; or
- (b) process a switch withdrawal request under clauses 17 and 18 of Schedule 11.3 if processing the switch withdrawal request would mean the defaulting trader retained responsibility for the ICP to which the switch withdrawal request applies.
- (2) If the Authority gives written notice under subclause (1), the registry manager must comply with the notice.
Clause 4B: replaced, on 7 September 2020, by clause 6 of the Electricity Industry Participation Code Amendment (Improving Trader Default Process) 2020.
Clause 4B Heading: amended, on 5 October 2017, by clause 284(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 4B: amended, on 5 October 2017, by clause 284(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 4B: inserted, on 28 August 2015, by clause 13 of the Electricity Industry Participation Code Amendment (Trader Default) 2014.
5
Authority may assign contracts and ICPs
- (1) This clause applies if, by the end of the 17th day after the defaulting trader or defaulting retailer was given notice under clause 2(1),—
- (a) the defaulting trader or defaulting retailer has not remedied the event of default or, in the case of an event of default under clause 14.41(1)(b) in respect of which there is an unresolved invoice dispute under clause 14.25, has not reached an agreement with the Authority to resolve the event of default; and
- (b) the defaulting trader or defaulting retailer continues to have 1 or more contracts under which a customer of the defaulting trader or defaulting retailer purchases electricity from the defaulting trader or the defaulting retailer or the defaulting trader is still recorded in the registry as being responsible for 1 or more ICPs.
- (2) The Authority may—
- (a) exercise its right under a contract under which a customer purchases electricity from the defaulting trader or defaulting retailer to assign the rights and obligations of the defaulting trader or defaulting retailer under the contract to a recipient trader in accordance with the contract; and
- (b) assign an ICP to a recipient trader and direct the registry manager to amend the record in the registry so that the recipient trader is recorded as being responsible for the ICP; and
- (c) specify the recipient trader to whom the rights and obligations under the contract or the ICP will be assigned.
- (2A) When determining an assignment under subclause (2), the Authority may do 1 or both of the following:
- (a) exercise its discretion to determine the recipient trader without going through a tender or other competitive process:
- (b) undertake a tender or other competitive process to determine the recipient trader.
- (3) The Authority must, by notice in writing to each recipient trader, direct the recipient trader to accept an assignment under subclause (2).
- (4) Before the Authority gives notice to a recipient trader under subclause (3), the Authority may decide not to assign rights and obligations of the defaulting trader or defaulting retailer under a contract or an ICP to a recipient trader if the recipient trader satisfies the Authority that the assignment would pose a serious threat to the financial viability of the recipient trader.
- (5) A recipient trader must comply with a direction given to it under subclause (3).
- (6) The registry manager must comply with a direction given to it under subclause (2).
- (7) Before the Authority exercises its right to assign rights and obligations or an ICP under subclause (2), the Authority must, if the Authority considers it is practicable, consult with the defaulting trader or defaulting retailer as to the need for the notice.
Clause 5, heading: amended, on 28 February 2015, by clause 14(1) of the Electricity Industry Participation Code Amendment (Trader Default) 2014.
Clause 5(1): amended, on 28 February 2015, by clause 14(2) of the Electricity Industry Participation Code Amendment (Trader Default) 2014.
Clause 5(1)(a): amended, on 24 March 2015, by clause 9 of the Electricity Industry Participation Code Amendment (Settlement and Prudential Security) 2014.
Clause 5(1)(a): amended, on 1 April 2025 by clause 21 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2025.
Clause 5(1)(b): amended, on 1 November 2018, by clause 70 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
Clause 5(2) to (8): amended, on 28 February 2015, by clause 14(3) of the Electricity Industry Participation Code Amendment (Trader Default) 2014.
Clause 5(2)(a): amended, on 1 November 2018, by clause 70 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
Clause 5(2)(b): amended, on 5 October 2017, by clause 285(a) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 2A: inserted, on 7 September 2020, by clause 7(1) of the Electricity Industry Participation Code Amendment (Improving Trader Default Process) 2020.
Clause 5(6): amended, on 5 October 2017, by clause 285(b) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 5(8): deleted, on 7 September 2020, by clause 7(2) of the Electricity Industry Participation Code Amendment (Improving Trader Default Process) 2020.
Clause 5(1), (2), (4) and (7): amended, on 15 May 2025, by clause 9(8) of the Electricity Industry Participation Code Amendment (Retailer Default) 2025.
5A
Effect of assignment
- If the Authority assigns an ICP to a recipient trader under clause 5, and at the time of the assignment the recipient trader does not comply with clause 10.24(a) in relation to the ICP, the recipient trader is excused from complying with that clause for the first 3 months after the assignment.
Clause 5A: inserted, on 28 August 2015, by clause 15 of the Electricity Industry Participation Code Amendment (Trader Default) 2014.
6
Authority must provide information to recipient trader
- If the Authority exercises its right to assign rights and obligations or an ICP under clause 5(2), the Authority must provide the following information to each recipient trader:
- (a) the number of customer contracts (to the extent that the Authority has the information) and ICPs assigned to the trader; and
- (b) any information that the Authority holds about the customers and ICPs assigned to the trader.
Clause 6, heading: amended, on 28 February 2015, by clause 16(1) of the Electricity Industry Participation Code Amendment (Trader Default) 2014.
Clause 6: amended, on 28 February 2015, by clause 16(2) of the Electricity Industry Participation Code Amendment (Trader Default) 2014.
Clause 6(a) and (b): amended, on 1 November 2018, by clause 71(a) and (b) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
7
Authority may direct registry manager to process certain ICP switching activities
- (1) If the Authority gives written notice to a defaulting trader under clause 2, the Authority may, by written notice to the registry manager, even if the defaulting trader has not complied with its obligations under Schedule 11.3, direct the registry manager to—
- (a) initiate and complete the switch of an ICP away from the defaulting trader; or
- (b) process the initiation or completion of the switch of an ICP away from the defaulting trader; or
- (c) cancel the switch of an ICP to the defaulting trader; or
- (d) process the completion of a switch withdrawal request under clauses 17 and 18 of Schedule 11.3 for an ICP that is being switched to the defaulting trader; or
- (e) cancel a switch withdrawal request made under clauses 17 and 18 of Schedule 11.3 for an ICP that is being switched away from the defaulting trader.
- (2) The registry manager must, as soon as possible, comply with a direction given by the Authority in a written notice.
Clause 7: replaced, on 7 September 2020, by clause 8 of the Electricity Industry Participation Code Amendment (Improving Trader Default Process) 2020.
Clause 7 Heading: amended, on 5 October 2017, by clause 286(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Clause 7: amended, on 28 February 2015, by clause 17 of the Electricity Industry Participation Code Amendment (Trader Default) 2014.
Clause 7: amended, on 5 October 2017, by clause 286(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
8
Terms of assigned contract
- (1) If the Authority exercises its right to assign rights and obligations under clause 5(2), the Authority must attempt to advise the customer that the terms of the contract may be amended on assignment.
- (2) The recipient trader must use reasonable endeavours to advise the customer of those terms.
Clause 8(1) and (2): amended, on 1 November 2018, by clause 72 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2018.
Clause 8(2): amended, on 28 February 2015, by clause 18 of the Electricity Industry Participation Code Amendment (Trader Default) 2014.
Schedule 11.6
NoneForms for authorisation of an Agent to request consumption information
Schedule 11.6 inserted, on 1 March 2020, by clause 7 of the Electricity Industry Participation Code Amendment (Requirements and Processes for Information Requests by Agents) 2020.