We’ve published a case study on participants’ obligations to meet payment deadlines with the reconciliation manager and keep the participant register up to date.

Case study: Meeting payment deadlines for cleared funds

The case study looks at the circumstances of a participant’s late payment to the clearing manager and subsequent failed attempts to contact them that constituted a breach of clause 14.34 of the Electricity Industry Participation Code 2010 and Section 29 (2) of the Electricity Industry Act 2010.

It is vital that participants remain on top of their obligations, have a strong compliance framework in place with well-established processes and controls and allocated roles and responsibilities.

The case is a reminder for all participants to keep their contact details up to date in the Participant register so that the Authority can communicate with organisation's most current contacts.

Related News

Authority notes decision on South Pacific Energy Limited

The Electricity Authority Te Mana Hiko acknowledges a Rulings Panel decision published today which fined electricity retailer South Pacific Energy Limited $88,…

Decision on 23 October 2025 under-frequency event

An under-frequency event occurred at about 10.12am on 23 October 2025, when HVDC Pole 3 tripped offline and the frequency in the North Island fell to 49.02…

Stress test disclosures due by 25 March 2026

The stress testing regime requires certain participants in the wholesale electricity market to test their exposure to changes in spot electricity prices and re…