Electricity Industry Participation Code Amendment (Backup Interim Price Method) 2025
Downloads
-
Backup interim price method - Certified instrument16 April 2025, 3 pages
Related documents
-
Decision paper - Code amendment omnibus #515 April 2025, 29 pages
-
Consultation paper - Code amendment omnibus #53 February 2025, 38 pages
Explanatory note
This note is not part of the amendment but is intended to indicate its general effect.
This amendment to the Electricity Industry Participation Code 2010 (Code) comes into force on 1 July 2025.
The amendment amends subpart 4 of Part 13 of the Code as part of the Authority’s Code amendment omnibus number five to provide a backup method for calculating spot prices for electricity and instantaneous reserves in the wholesale electricity market when market schedules have not been published for 36 hours or more.
The amendment is to the method for calculating interim prices and interim reserve prices. Interim prices and interim reserve prices become final prices and final reserve prices (the spot prices for electricity and instantaneous reserves in the wholesale electricity market) if there is no price error claim.
Legislative information
Title | Electricity Industry Participation Code Amendment (Backup Interim Price Method) 2025 |
---|---|
Principal or amendment | Amendment |
Consolidated version | No |
Empowering Act and provisions | Electricity Industry Act 2010, section 38 |
Replacement empowering Act and provisions | Not applicable |
Maker name | Electricity Authority |
Administering agency | Electricity Authority |
Date made | 14 April 2025 |
Publication date | 14 April 2025 |
Notification date | 14 April 2025 |
Commencement date | 1 July 2025 |
End date | Not applicable |
Consolidation as at date | Not applicable |
Related instruments | Electricity Industry Participation Code 2010 |