Code amendments
Electricity Industry Participation Code Amendment (Inflation Adjustment to Prescribed Maximum Fees) 2024
Downloads
-
Inflation Adjustment to Prescribed Maximum Fees 2024 - Certified instrument18 October 2024, 4 pages
Related documents
-
Decision paper - Code amendment omnibus #36 August 2024, 24 pages
-
Consultation paper - Code amendment omnibus #37 May 2024, 25 pages
Explanatory note
This note is not part of the amendment but is intended to indicate its general effect.
This amendment to the Electricity Industry Participation Code 2010 ("Code") comes into force on 1 November 2024.
The amendment amends Schedule 6.5 of the Electricity Industry Participation Code to increase the prescribed maximum fees that distributors charge distributed generators for applications under Part 1, Part 1A and Part 2 of Schedule 6.1. The increase to prescribed maximum fees is calculated using the industry-specific Labour Cost index.
Legislative information
Title | Electricity Industry Participation Code Amendment (Inflation Adjustment to Prescribed Maximum Fees) 2024 |
---|---|
Principal or amendment | Amendment |
Consolidated version | No |
Empowering Act and provisions | Electricity Industry Act 2010, section 38 |
Replacement empowering Act and provisions | Not applicable |
Maker name | Electricity Authority |
Administering agency | Electricity Authority |
Date made | 16 October 2024 |
Publication date | 18 October 2024 |
Notification date | 18 October 2024 |
Commencement date | 1 November 2024 |
End date | Not applicable |
Consolidation as at date | Not applicable |
Related instruments | Electricity Industry Participation Code 2010 |