Electricity Industry Participation Code 2010
Part 17—Transitional provisions
Transitional provisions relating to Part 1
17.1
Transitional provisions for definitions
- (1) Administrative costs agreed by the Board and the system operator in accordance with the definition of administrative costs in rule 1 of part A of the rules that were in force immediately before this Code came into force, are deemed to be administrative costs that have been agreed to by the Authority and the system operator in accordance with the definition of administrative costs in clause 1.1(1).
- (2) A declaration date nominated by a profile applicant in accordance with the definition of declaration date in rule 1 of part A of the rules that was in force immediately before this Code came into force, is deemed to be a declaration date nominated by a profile applicant in accordance with the definition of declaration date in clause 1.1(1).
- (3) A distributor kvar reference node approved by the system operator in accordance with the definition of distributor kvar reference node in rule 1 of part A of the rules that was in force immediately before this Code came into force, is deemed to be a distributor kvar reference node approved by the system operator in accordance with the definition of distributor kvar reference node in clause 1.1(1).
- (4) Expected interruption costs estimated by the Board under the definition of expected interruption costs in rule 1 of part A of the rules that were in force immediately before this Code came into force, are deemed to be expected interruption costs approved by the Authority in accordance with the definition of expected interruption costs in clause 1.1(1).
- (5) A grid exit point approved by the system operator under the definition of interruptible load group GXP in rule 1 of part A of the rules immediately before this Code came into force, is deemed to be a grid exit point approved by the system operator in accordance with the definition of interruptible load group GXP in clause 1.1(1).
- (6) A system operator register kept, maintained, or made available by the system operator in accordance with the definition of system operator register in rule 1 of part A of the rules immediately before this Code came into force, is deemed to be a system operator register kept, maintained, or made available, as the case may be, by the system operator in accordance with definition of system operator register in clause 1.1(1).
17.2
Special definition of purchaser and payer
- (1) A notice given under rule 5.2 of part A of the rules and in force immediately before this Code came into force, is deemed to be a notice given under clause 1.5(2), and may be—
- (a) approved by the Authority (if it has not been approved by the Board); and
- (b) revoked by the participant named in the notice as participant A or the participant in the notice named as participant B.
- (2) A notice published by the Board under rule 5.8 of part A of the rules before this Code came into force, is deemed to be a notice published by the Authority under clause 1.5(8).
Transitional provisions relating to Part 2
17.3
[Revoked]
Clause 17.3: revoked, on 20 December 2021, by clause 78 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
Transitional provisions relating to Part 3
17.4
[Revoked]
Clause 17.4: revoked, on 20 December 2021, by clause 79 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.5
Insurance cover
- (1) A requirement by the Commission that a service provider maintain insurance cover under regulation 36 of the Electricity Governance Regulations 2003 that was in force immediately before this Code came into force, is deemed to be a requirement by the Authority under clause 3.6.
- (2) An insurer approved by the Commission under regulation 36 of the Electricity Governance Regulations 2003 immediately before this Code came into force, is deemed to be approved by the Authority under clause 3.6 on the same terms and in respect of the same risks.
17.6
[Revoked]
Clause 17.6: revoked, on 20 December 2021, by clause 80 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.7
Disclosure to the Authority
- Information received by a service provider to which regulation 42 of the Electricity Governance Regulations 2003 applied immediately before this Code came into force, is deemed to be information received by the relevant market operation service provider on the day on which this Code came into force for the purposes of clause 3.11.
17.8
[Revoked]
Clause 17.8: revoked, on 20 December 2021, by clause 81 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.9
[Revoked]
Clause 17.9: revoked, on 20 December 2021, by clause 82 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.10
[Revoked]
Clause 17.10: revoked, on 20 December 2021, by clause 83 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.11
[Revoked]
Clause 17.11: revoked, on 20 December 2021, by clause 84 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
Transitional provisions relating to Part 4
17.12
[Revoked]
Clause 17.12: revoked, on 20 December 2021, by clause 85 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
Transitional provisions relating to Part 5
17.13
[Revoked]
Clause 17.13: revoked, on 20 December 2021, by clause 86 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
Transitional provisions relating to Part 6
17.14
Approval to connect
- An approval granted by a distributor to a generator to connect distributed generation under regulation 7 of the Electricity Governance (Connection of Distributed Generation) Regulations 2007 that was in force immediately before this Code came into force, is deemed to be an approval granted to connect distributed generation under clause 6.4.
17.15
Connection of distributed generation outside regulated terms
- A connection contract entered into by a distributor and a generator outside the regulated terms under regulation 8 of the Electricity Governance (Connection of Distributed Generation) Regulations 2007 that was in force immediately before this Code came into force, is deemed to be a connection contract outside the regulated terms under clause 6.5.
Clause 17.15: amended, on 23 February 2015, by clause 75 of the Electricity Industry Participation Code Amendment (Distributed Generation) 2014.
17.16
Connection of distributed generation on regulated terms
- (1) If distributed electricity was connected on regulated terms under regulation 9 of the Electricity Governance (Connection of Distributed Generation) Regulations 2007 immediately before this Code came into force, it is deemed to be connected on regulated terms under clause 6.6.
- (2) [Revoked]
Clause 17.16(1): amended, on 23 February 2015, by clause 75 of the Electricity Industry Participation Code Amendment (Distributed Generation) 2014.
Clause 17.16(2): revoked, on 20 December 2021, by clause 87 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.17
Obtaining approval to connect distributed generation under 10kW
- (1) [Revoked]
- (2) A generator approved to connect distributed generation under clause 3 of Schedule 1 of the Electricity Governance (Connection of Distributed Generation) Regulations 2007 immediately before this Code came into force, is deemed to have been approved to connect distributed generation under clause 3 of Schedule 6.1.
- (3) [Revoked]
Clause 17.17(1) and (3): revoked, on 20 December 2021, by clause 88 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.18
Obtaining approval to connect distributed generation over 10kW
- (1) An initial application made by a generator to a distributor to connect distributed generation capable of generating electricity above 10kW under clause 11 of Schedule 1 of the Electricity Governance (Connection of Distributed Generation) Regulations 2007, for which the generator had not made a final application in respect of the generation immediately before this Code came into force, is deemed to be an initial application under clause 11 of Schedule 6.1.
- (2) Information provided under clauses 12 and 13 of Schedule 1 of the Electricity Governance (Connection of Distributed Generation) Regulations 2007 before this Code came into force, is deemed to be information provided under clauses 12 and 13 of Schedule 6.1.
- (3) A final application made under clause 15 of Schedule 1 of the Electricity Governance (Connection of Distributed Generation) Regulations 2007, on which a distributor had not made a decision immediately before this Code came into force, is deemed to be a final application made under clause 15 of Schedule 6.1.
- (4) A generator approved to connect distributed generation under clause 18 of Schedule 1 of the Electricity Governance (Connection of Distributed Generation) Regulations 2007 immediately before this Code came into force, is deemed to have been approved to connect distributed generation under clause 18 of Schedule 6.1.
- (5) Any conditions specified by a distributor in its decision on an application under clause 18 of Schedule 1 of the Electricity Governance (Connection of Distributed Generation) Regulations 2007 immediately before this Code came into force, are deemed to be conditions specified by the distributor under clause 18 of Schedule 6.1.
- (6) A notice of an intention to proceed made by a generator under clause 20 of the Electricity Governance (Connection of Distributed Generation) Regulations 2007 that was in force immediately before this Code came into force, is deemed to be a notice under clause 20 of Schedule 6.1.
17.19
Confidentiality of information provided before connection
- Information provided with an application made under Schedule 1 of the Electricity Governance (Connection of Distributed Generation) Regulations 2007 before this Code came into force, is subject to the confidentiality provisions in clause 25 of Schedule 6.1.
17.20
[Revoked]
Clause 17.20: revoked, on 20 December 2021, by clause 89 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.21
Confidential information for regulated terms for connection of distributed generation
- (1) Conditions specified under clause 18 of Schedule 2 of the Electricity Governance (Connection of Distributed Generation) Regulations 2007 apply as if they were specified under clause 17 of Schedule 6.2.
- (2) Information that came within the definition of confidential information under clause 16 of Schedule 2 of the Electricity Governance (Connection of Distributed Generation) Regulations 2007, is deemed to be confidential information as defined in clause 1.1(1).
17.22
[Revoked]
Clause 17.22: revoked, on 20 December 2021, by clause 90 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.23
[Revoked]
Clause 17.23: revoked, on 20 December 2021, by clause 91 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.23A
[Revoked]
Clause 17.23A: inserted, on 9 January 2017, by clause 6 of the Electricity Industry Participation Code Amendment (Distributed Generation) 2016.
Clause 17.23A: revoked, on 5 October 2017, by clause 579 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
Transitional provisions relating to Part 7
17.24
[Revoked]
Clause 17.24: revoked, on 20 December 2021, by clause 92 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.25
[Revoked]
Clause 17.25: revoked, on 20 December 2021, by clause 93 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.26
[Revoked]
Clause 17.26: revoked, on 20 December 2021, by clause 94 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.27
[Revoked]
Clause 17.27: revoked, on 20 December 2021, by clause 95 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
Transitional provisions relating to Part 8
17.28
[Revoked]
Clause 17.28: revoked, on 20 December 2021, by clause 96 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.29
Existing contracts for higher levels of common quality
- (1) This clause applies if—
- (a) Transpower and any person have a contract or an arrangement to maintain voltage at a point of connection that—
- (i) was in force immediately before the rules came into force; and
- (ii) remained in force after this Code came into force; and
- (b) the effect of the contract or arrangement may cause the system operator to operate the grid voltage within a lesser range than the range set out in the AOPOs; and
- (c) Transpower and the system operator have a matching contract or arrangement in that respect under clause 8.6.
- (a) Transpower and any person have a contract or an arrangement to maintain voltage at a point of connection that—
- (2) When this clause applies, any incremental cost arising from the system operator operating within a lesser range under a contract or arrangement to which subclause (1)(c) applies—
- (a) must not be allocated according to clause 8.6; but instead
- (b) is an allocable cost and must be paid as set out in clauses 8.55 and 8.67.
- (3) Subclause (2) applies to the costs arising from a contract or arrangement to which subclause (1)(c) applies until the earlier of the following:
- (a) the expiry date of the contract or arrangement:
- (b) termination of the contract or arrangement:
- (c) the end of the life of the assets employed in providing the voltage service provided for in the contract or arrangement.
17.30
[Revoked]
Clause 17.30: revoked, on 20 December 2021, by clause 97 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.31
[Revoked]
Clause 17.31: revoked, on 20 December 2021, by clause 98 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.32
Information provisions
- (1) A notice given by the system operator to an embedded generator under rule 4.5 of section III of part C of the rules that was in force immediately before this Code came into force, is deemed to be a notice issued by the system operator to an embedded generator under clause 8.25(5)(b).
- (2) [Revoked]
- (3) An approval given by the Commission under rule 4.6 of section III of part C of the rules immediately before this Code came into force, is deemed to be an approval given by the Authority under clause 8.25(6).
Clause 17.32(2): revoked, on 20 December 2021, by clause 99 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.33
[Revoked]
Clause 17.33: revoked, on 20 December 2021, by clause 100 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.34
Equivalence arrangement or dispensation
- (1) An approval of an equivalence arrangement under rule 7.2 of section III of part C of the rules, unless cancelled under rule 8.2 of section III of part C or revoked under rule 8.3 of section III of part C, that was in force immediately before this Code came into force, is deemed to be an approval of an equivalence arrangement under clause 8.30 and clause 8 of Schedule 8.1, as modified in accordance with rule 8.1 of section III of part C of the rules.
- (2) A grant of a dispensation under rule 7.3 of section III of part C of the rules, unless cancelled under rule 8.2 of section III of part C, or revoked or varied under rule 8.3 of section III of part C, that was in force immediately before this Code came into force, is deemed to be a grant of a dispensation under clause 8.31 and clause 8 of Schedule 8.1 as modified in accordance with rule 8.1 of section III of part C of the rules.
- (3) [Revoked]
- (4) [Revoked]
- (5) An agreement relating to the processing costs for the approval of an equivalence arrangement or the grant of a dispensation under clause 5 of schedule C1 of part C of the rules that was in force immediately before this Code came into force, is deemed to be an agreement under clause 5 of Schedule 8.1.
- (6) [Revoked]
Clause 17.34(3), (4) and (6): revoked, on 20 December 2021, by clause 101 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.35
Excluded generating stations
- A directive issued by the Commission under rule 10 of section III of part C of the rules that was in force immediately before this Code came into force, is deemed to be a directive issued by the Authority under clause 8.38(2).
17.36
[Revoked]
Clause 17.36(1) and (2): expired, on 30 November 2012 by clause 17.36(3).
Clause 17.36: revoked, on 20 December 2021, by clause 102 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.37
[Revoked]
Clause 17.37: revoked, on 20 December 2021, by clause 103 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.38
Allocating ancillary services costs
- (1) [Revoked]
- (2) Actual administrative costs approved by the Commission under rule 11.1.2 of section IV of part C of the rules and in force immediately before this Code came into force, are deemed to be actual administrative costs under clause 8.55(1)(b).
- (3) [Revoked]
- (4) [Revoked]
- (5) [Revoked]
- (6) [Revoked]
- (7) [Revoked]
- (8) [Revoked]
- (9) [Revoked]
- (10) [Revoked]
- (11) [Revoked]
- (12) [Revoked]
- (13) [Revoked]
- (14) [Revoked]
Clause 17.38(1): revoked, on 20 December 2021, by clause 104(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
Clause 17.38(2): amended, on 20 December 2021, by clause 104(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
Clause 17.38(3) to (14): revoked, on 20 December 2021, by clause 104(3) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.39
[Revoked]
Clause 17.39: revoked, on 20 December 2021, by clause 105 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.40
Connection of local networks in parallel with the grid
- An agreement under clause 6 of technical code A of schedule C3 of part C of the rules that was in force immediately before this Code came into force, is deemed to be an agreement under clause 6 of Technical Code A of Schedule 8.3.
17.41
[Revoked]
Clause 17.41: revoked, on 20 December 2021, by clause 106 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.42
[Revoked]
Clause 17.42: revoked, on 20 December 2021, by clause 107 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.43
[Revoked]
Clause 17.43: revoked, on 20 December 2021, by clause 108 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.44
Retention of records
- The system operator and each participant must retain records of formal notices issued under clause 4 of technical code B of schedule C3 of part C of the rules.
17.45
Redistribution of automatic under-frequency load shedding
- An agreement to redistribute automatic under-frequency load shedding quantities between grid exit points under clause 6.4 of technical code B of schedule C3 of part C of the rules that was in force immediately before this Code came into force, is deemed to be an agreement under clause 7(8) of Technical Code B of Schedule 8.3
Clause 17.45: revoked, on 7 August 2014, by clause 34 of the Electricity Industry Participation Code Amendment (Extended Reserve) 2014.
Clause 17.45: replaced, on 21 December 2021, by clause 45 of the Electricity Industry Participation Code Amendment (Automatic Under-Frequency Load Shedding Systems) 2021.
17.46
Notice
- A notice in relation to a participant under clause 6.5A.2 of technical code B of schedule C3 of part C of the rules that was in force immediately before this Code came into force, is deemed to be a notice in relation to a participant under clause 7(11) of Technical Code B of Schedule 8.3.
17.47
Specific requirements for document transmission communication
- (1) [Revoked]
- (2) An approval of primary or backup means of document transmission communication under clauses 4.1 or 4.2 of technical code C of schedule C3 of part C of the rules that was in force immediately before this Code came into force, is deemed to be an approval under clause 5(2) or (3), as the case may be, of Technical Code C of Schedule 8.3.
Clause 17.47(1): revoked, on 20 December 2021, by clause 109 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.48
[Revoked]
Clause 17.48: revoked, on 20 December 2021, by clause 110 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.48A
[Revoked]
Clause 17.48A: inserted, on 7 August 2014, by clause 35 of the Electricity Industry Participation Code Amendment (Extended Reserve) 2014.
Clause 17.48A(3): amended, on 19 December 2014, by clause 43 of the Electricity Industry Participation Code Amendment (Minor Code Amendments) (No 3) 2014.
Clause 17.48A: revoked, on 5 October 2017, by clause 580 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
17.48B
[Revoked]
Clause 17.48B: inserted, on 7 August 2014, by clause 35 of the Electricity Industry Participation Code Amendment (Extended Reserve) 2014.
Clause 17.48B: revoked, on 5 October 2017, by clause 581 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
17.48C
Transitional provisions for exemptions to provide automatic under-frequency load shedding
- Exemptions under section 11 of the Act to clause 8.19(5) of this Code and clauses 7(1), 7(8) and 7(9) of Technical Code B of Schedule 8.3 of this Code that were in force prior to this clause coming into force will continue to be in force until the earlier of—
- (a) 30 June 2022:
- (b) the date on which the exemption is superseded by the system operator approving an equivalence arrangement under clause 8.30.
Clause 17.48C: inserted, on 21 December 2021, by clause 46 of the Electricity Industry Participation Code Amendment (Automatic Under-Frequency Load Shedding Systems) 2021.
Transitional provisions relating to Part 9
17.49
[Revoked]
Clause 17.49: revoked, on 20 December 2021, by clause 111 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.50
Participant rolling outage plans
- (1) A notice given by the Commission to a specified participant under regulation 8A(2) of the Electricity Governance (Security of Supply) Regulations 2008 that was in force immediately before this Code came into force, is deemed to be a notice given by the system operator under clause 9.6(2).
- (2) [Revoked]
- (3) [Revoked]
- (4) [Revoked]
- (5) [Revoked]
- (6) [Revoked]
- (7) [Revoked]
- (8) [Revoked]
- (9) [Revoked]
- (10) [Revoked]
- (11) [Revoked]
Clause 17.50(2) to (11): revoked, on 20 December 2021, by clause 112 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.51
[Revoked]
Clause 17.51: revoked, on 20 December 2021, by clause 113 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.52
[Revoked]
Clause 17.52: revoked, on 20 December 2021, by clause 114 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.53
[Revoked]
Clause 17.53: revoked, on 20 December 2021, by clause 115 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
Transitional provisions relating to Part 10
17.54
[Revoked]
Clause 17.54 revoked, on 20 December 2021, by clause 116 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.55
[Revoked]
Clause 17.55: revoked, on 20 December 2021, by clause 117 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.56
[Revoked]
Clause 17.56: revoked, on 20 December 2021, by clause 118 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.57
[Revoked]
Clause 17.57: revoked, on 20 December 2021, by clause 119 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.58
Approved test house
- (1) [Revoked]
- (2) [Revoked]
- (3) [Revoked]
- (4) A data logger certified under clause 3.4 of code of practice D3 of part D of the rules immediately before this Code came into force, is deemed to be a data logger certified under clause 3.4 of Code of Practice 10.3.
- (5) [Revoked]
Clause 17.58(1), (2), (3) and (5): revoked, on 20 December 2021, by clause 120 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.59
Certification of metering installations
- (1) A metering installation certified, or deemed by rule 6 of section III of part I of the rules to be certified, under clause 4 of code of practice D3 of part D of the rules immediately before this Code came into force, is deemed to be a metering installation certified under clause 4 of Code of Practice 10.3.
- (2) [Revoked]
- (3) A metering installation recertified under clause 5.4.2 of code of practice D3 of part D of the rules immediately before this Code came into force, is deemed to be a metering installation recertified under clause 7 of Code of Practice 10.3.
Clause 17.59(2): revoked, on 20 December 2021, by clause 121 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.60
[Revoked]
Clause 17.60: revoked, on 20 December 2021, by clause 122 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.61
Variation of requirements
- A variation granted under code of practice D5 of part D of the rules that had not expired immediately before this Code came into force, is deemed to be a variation granted under Code of Practice 10.5.
Transitional provisions relating to Part 11
17.62
Requirement to provide complete and accurate information
- For the purposes of clause 11.2(2), information provided by a participant under part E of the rules before this Code came into force, is deemed to be information provided under Part 11.
17.63
ICP identifiers for ICPs
- An ICP identifier that applied to an ICP immediately before this Code came into force, is deemed to be an ICP identifier for that ICP created under this Code.
17.64
[Revoked]
Clause 17.64: revoked, on 20 December 2021, by clause 123 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.65
Provision of ICP information
- Information provided by a distributor or a trader under rule 6 of part E of the rules before this Code came into force, is deemed to be information provided by a distributor or a trader, as the case may be, under clause 11.7.
17.66
Provision of and changes to ICP and NSP information
- A notification given by a participant under rule 8.2 of part E of the rules that had not been processed immediately before this Code came into force, is deemed to be a notification given under clause 11.8(2).
17.67
[Revoked]
Clause 17.67: revoked, on 20 December 2021, by clause 124 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.68
[Revoked]
Clause 17.68: revoked, on 20 December 2021, by clause 125 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.69
Process for maintaining shared unmetered load
- (1) A notification provided by a distributor to the registry under rule 14.2 of part E of the rules that had not been processed immediately before this Code came into force, is deemed to be a notification provided under clause 11.14(2).
- (2) A notification provided by a trader to a distributor under rule 14.2A of part E of the rules that had not been processed immediately before this Code came into force, is deemed to be a notification provided under clause 11.14(3).
- (3) A notification provided by a distributor to the registry and each trader under rule 14.2B of part E of the rules that had not been processed immediately before this Code came into force, is deemed to be a notification provided under clause 11.14(4).
- (4) A notification provided by a distributor to all traders under rule 14.3 of part E of the rules that was in force immediately before this Code came into force, is deemed to be a notification provided under clause 11.14(5).
17.70
[Revoked]
Clause 17.70: revoked, on 20 December 2021, by clause 126 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.71
[Revoked]
Clause 17.71: revoked, on 20 December 2021, by clause 127 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.72
[Revoked]
Clause 17.72: revoked, on 20 December 2021, by clause 128 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.73
[Revoked]
Clause 17.73: revoked, on 20 December 2021, by clause 129 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.74
[Revoked]
Clause 17.74: revoked, on 20 December 2021, by clause 130 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.75
Access to registry
- (1) [Revoked]
- (2) Terms and conditions specified by the Board under rule 25.2 of part E of the rules that were in force immediately before this Code came into force, are deemed to be terms and conditions specified under clause 11.28(2).
- (3) [Revoked]
Clause 17.75 heading: amended, on 20 December 2021, by clause 131(1) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
Clause 17.75(1) and (3): revoked, on 20 December 2021, by clause 131(2) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.76
[Revoked]
Clause 17.76: revoked, on 20 December 2021, by clause 132 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.77
[Revoked]
Clause 17.77: revoked, on 20 December 2021, by clause 133 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.78
Dispensations
- A dispensation granted by the Board under clause 1.4 of schedule E1 of part E of the rules that was in force immediately before this Code came into force, is deemed to be a dispensation granted by the Authority under clause 4 of Schedule 11.1.
17.79
Distributors to provide ICP information to registry
- Information provided by a distributor to the registry under clause 2 of schedule E1 of part E of the rules that had not been changed by the distributor under clause 2A of schedule E1 of part E of the rules immediately before this Code came into force, is deemed to be information provided to the registry under clause 7 of Schedule 11.1.
17.80
Traders to provide ICP information to registry
- Information provided by a trader to the registry under clause 3 of schedule E1 of part E of the rules that had not been changed by the trader under clause 3A of schedule E1 of part E of the rules immediately before this Code came into force, is deemed to be information provided to the registry under clause 9 of Schedule 11.1.
Clause 17.80: amended, on 1 March 2024, by clause 128 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2024.
17.81
[Revoked]
Clause 17.81: revoked, on 20 December 2021, by clause 134 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.82
Management of ICP status by distributors and traders
- (1) The status of an ICP recorded on the registry and managed in accordance with clause 4 of schedule E1 of part E of the rules immediately before this Code came into force, is deemed to be the status of the ICP recorded on the registry and managed by distributors or traders, as the case may be, in accordance with clauses 12 to 20 of Schedule 11.1, as the case may be.
- (2) [Revoked]
- (3) [Revoked]
- (4) [Revoked]
Clause 17.82(2), (3) and (4): revoked, on 20 December 2021, by clause 135 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.83
Updating table of loss category codes
- A loss category code entered in the table in the registry under clause 5 of schedule E1 of part E of the rules and in force immediately before this Code came into force, is deemed to be a loss category code entered in accordance with clause 21 of Schedule 11.1.
17.84
Updating loss factors for loss category codes
- A loss factor entered in the table in the registry under clause 5A of schedule E1 of part E of the rules that is in force immediately before this Code came into force, is deemed to be a loss factor entered in accordance with clause 22 of Schedule 11.1.
17.85
Updating table of price category codes
- A price category code entered in the table in the registry under clause 6 of schedule E1 of part E of the rules that is in force immediately before this Code came into force, is deemed to be a price category code entered in accordance with clause 23 of Schedule 11.1.
17.86
Balancing area information
- (1) A notification given to the reconciliation manager under clause 7.1 of schedule E1 of part E of the rules that was in force immediately before this Code came into force, is deemed to be a notification given under clause 24(1) of Schedule 11.1.
- (2) A notification of a change of information given to the reconciliation manager under clause 7.1A of schedule E1 of part E of the rules that was in force immediately before this Code came into force, is deemed to a notification given under clause 24(2) of Schedule 11.1.
- (3) A notification given by the reconciliation manager to the registry of changes to balancing areas under clause 7.2 of schedule E1 of part E of the rules that was in force immediately before this Code came into force, is deemed to be a notification given under clause 24(4) of Schedule 11.1.
- (4) A schedule published by the registry under clause 7.3 of schedule E1 of part E of the rules that was in force immediately before this Code came into force, is deemed to be a schedule published under clause 24(5) of Schedule 11.1.
17.87
[Revoked]
Clause 17.87: revoked, on 20 December 2021, by clause 136 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.88
[Revoked]
Clause 17.88: revoked, on 20 December 2021, by clause 137 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.89
[Revoked]
Clause 17.89: revoked, on 20 December 2021, by clause 138 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.90
Reconciliation manager to allocate new identifiers
- An NSP identifier allocated by the reconciliation manager under clause 11 of schedule E1 of part E of the rules and in force immediately before this Code came into force, is deemed to be an NSP identifier allocated under clause 28 of Schedule 11.1.
17.91
Obligations concerning change in network owner
- A notification given by a network owner under clause 12 of schedule E1 of part E of the rules that was in force immediately before this Code came into force, is deemed to be a notification given under clause 29 of Schedule 11.1.
17.92
[Revoked]
Clause 17.92: revoked, on 20 December 2021, by clause 139 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.93
[Revoked]
Clause 17.93: revoked, on 20 December 2021, by clause 140 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.94
[Revoked]
Clause 17.94: revoked, on 20 December 2021, by clause 141 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.95
[Revoked]
Clause 17.95: revoked, on 20 December 2021, by clause 142 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.96
[Revoked]
Clause 17.96: revoked, on 20 December 2021, by clause 143 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.97
Withdrawal of switch requests
- (1) Codes for withdrawing a switch request determined and published by the Board under clause 4.1 of schedule E2 of part E of the rules before this Code came into force, are deemed to be codes determined and published by the Authority under clause 18(b) of Schedule 11.3.
- (2) [Revoked]
- (3) [Revoked]
- (4) [Revoked]
- (5) [Revoked]
- (6) [Revoked]
Clause 17.97(2) to (6): revoked, on 20 December 2021, by clause 144 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.98
[Revoked]
Clause 17.98: revoked, on 20 December 2021, by clause 145 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.99
[Revoked]
Clause 17.99: revoked, on 20 December 2021, by clause 146 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.100
[Revoked]
Clause 17.100: revoked, on 20 December 2021, by clause 147 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.101
[Revoked]
Clause 17.101: revoked, on 20 December 2021, by clause 148 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.101A
[Revoked]
Clause 17.101A: inserted, on 9 October 2015, by clause 28 of the Electricity Industry Participation Code Amendment (ICP Switching) 2014.
Clause 17.101A(2): amended, on 9 October 2015, by clause 17 of the Electricity Industry Participation Code Amendment (ICP Switching) 2015.
Clause 17.101A: revoked, on 20 December 2021, by clause 149 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
Transitional provisions relating to Part 12
17.102
[Revoked]
Clause 17.102: revoked, on 20 December 2021, by clause 150 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.103
[Revoked]
Clause 17.103: revoked, on 20 December 2021, by clause 151 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.104
[Revoked]
Clause 17.104: revoked, on 20 December 2021, by clause 152 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.105
[Revoked]
Clause 17.105: revoked, on 20 December 2021, by clause 153 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.106
[Revoked]
Clause 17.106: revoked, on 20 December 2021, by clause 154 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.107
[Revoked]
Clause 17.107: revoked, on 20 December 2021, by clause 155 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.108
Increased services and reliability
- A certification given under rule 5.1 of section II of part F of the rules immediately before this Code came into force, is deemed to be confirmation given under clause 12.35.
Clause 17.108: amended, on 1 March 2024, by clause 129 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2024.
17.109
Approval of decreased services and reliability
- An approval given under rule 5.2 of section II of part F of the rules that was in force immediately before this Code came into force, is deemed to be an approval given under clause 12.36.
17.110
Approval of other variations to terms of benchmark agreement
- An approval given under rule 5.4 of section II of part F of the rules that was in force immediately before this Code came into force, is deemed to be an approval given under clause 12.38.
17.111
Customer specific value of unserved energy
- (1) [Revoked]
- (2) [Revoked]
- (3) An approval given under rule 5.5.4.1 of section II of part F of the rules that was in force immediately before this Code came into force, is deemed to be an approval given under clause 12.39(5)(a).
Clause 17.111(1) and (2): revoked, on 20 December 2021, by clause 156 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.112
[Revoked]
Clause 17.112: revoked, on 20 December 2021, by clause 157 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.113
[Revoked]
Clause 17.113: revoked, on 20 December 2021, by clause 158 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.114
[Revoked]
Clause 17.114: revoked, on 20 December 2021, by clause 159 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.115
[Revoked]
Clause 17.115: revoked, on 20 December 2021, by clause 160 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.116
[Revoked]
Clause 17.116: revoked, on 20 December 2021, by clause 161 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.117
[Revoked]
Clause 17.117: revoked, on 20 December 2021, by clause 162 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.118
Development of transmission pricing methodology
- The process and guidelines for the development of the transmission pricing methodology last published by the Board under rule 6 of section IV of part F of the rules immediately before this Code came into force, are deemed to be the process and guidelines for the development of transmission pricing methodology published by the Authority under clause 12.83.
17.119
[Revoked]
Clause 17.119: revoked, on 20 December 2021, by clause 163 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.120
[Revoked]
Clause 17.120: revoked, on 20 December 2021, by clause 164 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.121
[Revoked]
Clause 17.121: revoked, on 20 December 2021, by clause 165 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.122
[Revoked]
Clause 17.122 revoked, on 20 December 2021, by clause 166 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.123
[Revoked]
Clause 17.123: revoked, on 20 December 2021, by clause 167 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.124
[Revoked]
Clause 17.124: revoked, on 20 December 2021, by clause 168 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.125
[Revoked]
Clause 17.125: revoked, on 20 December 2021, by clause 169 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.126
[Revoked]
Clause 17.126: revoked, on 20 December 2021, by clause 170 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.127
[Revoked]
Clause 17.127: revoked, on 20 December 2021, by clause 171 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
Transitional provisions relating to Part 13
17.128
[Revoked]
Clause 17.128: revoked, on 20 December 2021, by clause 172 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.129
Approval process for industrial co-generating stations
- (1) [Revoked]
- (2) A generator approved as an industrial co-generating station by the Board under rule 3 of section I or schedule G9 of part G of the rules, whose approval had not been rescinded immediately before this Code came into force, is deemed to be a generator approved by the Authority as an industrial co-generating station under clause 13.3 and Schedule 13.4.
- (3) [Revoked]
Clause 17.129(1) and (3): revoked, on 20 December 2021, by clause 173 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.129A
[Revoked]
Clause 17.129A: inserted, on 27 May 2015, by clause 30 of the Electricity Industry Participation Code Amendment (Industrial Co-generation Dispatch Arrangements) 2015.
Clause 17.129A: revoked, on 20 December 2021, by clause 174 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.130
[Revoked]
Clause 17.130: revoked, on 20 December 2021, by clause 175 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.131
[Revoked]
Clause 17.131: revoked, on 20 December 2021, by clause 176 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.132
[Revoked]
Clause 17.132: revoked, on 20 December 2021, by clause 177 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.133
[Revoked]
Clause 17.133: revoked, on 20 December 2021, by clause 178 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.134
[Revoked]
Clause 17.134: revoked, on 20 December 2021, by clause 179 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.135
Offers made by unit of plant
- Notice given under rule 3.8 of section II of part G of the rules, that was in force immediately before this Code came into force, is deemed to be notice given under clause 13.11.
17.136
[Revoked]
Clause 17.136: revoked, on 20 December 2021, by clause 180 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.137
[Revoked]
Clause 17.137: revoked, on 1 March 2024, by clause 130 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2024.
17.138
[Revoked]
Clause 17.138: revoked, on 1 March 2024, by clause 131 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2024.
17.139
[Revoked]
Clause 17.139: revoked, on 20 December 2021, by clause 181 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.140
Retention of bids and offers
- The system operator must retain records of all bids and offers for electricity submitted by participants and all reserve offers submitted by ancillary service agents under section II of part G of the rules, including all revised bids and offers and revised reserve offers, all cancelled bids and offers and all cancelled reserve offers.
17.141
Special treatment of some grid exit points
- (1) [Revoked]
- (2) 2 or more grid exit points approved to be, or deemed to be approved to be, treated as 1 grid exit point under rule 4 of section II of part G of the rules immediately before this Code came into force, are deemed to be approved to be treated as 1 grid exit point under clause 13.28.
Clause 17.141(1): revoked, on 20 December 2021, by clause 182 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.142
[Revoked]
Clause 17.142: revoked, on 20 December 2021, by clause 183 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.143
Transmission grid capability information to be updated
- The period of time agreed between the system operator and each grid owner for updates to information described in rules 5.1 to 5.3 and rule 5.5 of section II of part G of the rules immediately before this Code came into force for the purposes of rule 5.4 of section II of part G of the rules, is deemed to be the period of time agreed between the system operator and each grid owner for updates to information described in clauses 13.29 to 13.31 and 13.33 as the case may be, for the purpose of clause 13.32.
17.144
[Revoked]
Clause 17.144: revoked, on 20 December 2021, by clause 184 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.145
[Revoked]
Clause 17.145: revoked, on 20 December 2021, by clause 185 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.146
[Revoked]
Clause 17.146: revoked, on 20 December 2021, by clause 186 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.147
[Revoked]
Clause 17.147: revoked, on 20 December 2021, by clause 187 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.148
[Revoked]
Clause 17.148: revoked, on 20 December 2021, by clause 188 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.149
[Revoked]
Clause 17.149: revoked, on 20 December 2021, by clause 189 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.150
[Revoked]
Clause 17.150: revoked, on 20 December 2021, by clause 190 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.151
Block dispatch may occur
- (1) A notification provided to the system operator under rules 3.6 to 3.6.2 of section III of part G of the rules immediately before this Code came into force, in respect of trading periods that occur after this Code came into force, is deemed to be a notification under clause 13.60 in respect of those trading periods.
- (2) An agreement or deemed agreement to treat a group of generating stations as a block dispatch group under rule 3.6 of section III of part G of the rules that was in force immediately before this Code came into force, is deemed to be an agreement under clause 13.60.
Clause 17.151(1): amended, on 20 December 2021, by clause 191(a) and (b) of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.152
System operator to notify block security constraints
- A notification of block security constraints under rule 3.6.5 of section III of part G of the rules immediately before this Code came into force, which applies to trading periods after this Code came into force, is deemed to be a notification of block security constraints under clause 13.61(1).
17.153
Station dispatch may occur
(1) A notification given, or deemed by rule 4.2 of section IV of part I of the rules to be given, by a generator to the system operator in accordance with rule 3.9 of section III of part G of the rules before this Code came into force, which applies to a period after this Code came into force, is deemed to be a notification given under clause 13.64.
(2) An election notified, or deemed by rule 4.2 of section IV of part I of the rules to be notified, by the system operator to a generator and the clearing manager in accordance with rule 3.9 of section III of part G of the rules before this Code came into force, which applies to a period after this Code came into force, is deemed to be an election notified under clause 13.64.
17.154
System operator to notify security constraints
- A notification of a dispatch made in accordance with rules 3.9.1 and 3.9.2 of section III of part G of the rules that was in force immediately before this Code came into force, which applies to a period after this Code came into force, is deemed to be a notice under clause 13.65.
Clause 17.154: amended, on 20 December 2021, by clause 192 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.155
Generator notifies change from station to unit dispatch
- A notification of a change from a station dispatch group to a generating unit under rule 3.9.3 of section III of part G of the rules that was in force immediately before this Code came into force, which applies to a period after this Code came into force, is deemed to be a notification under clause 13.66.
17.156
[Revoked]
Clause 17.156: revoked, on 20 December 2021, by clause 193 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.157
[Revoked]
Clause 17.157: revoked, on 20 December 2021, by clause 194 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.158
[Revoked]
Clause 17.158: revoked, on 20 December 2021, by clause 195 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.159
[Revoked]
Clause 17.159: revoked, on 20 December 2021, by clause 196 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.160
[Revoked]
Clause 17.160: revoked, on 20 December 2021, by clause 197 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.161
[Revoked]
Clause 17.161: revoked, on 20 December 2021, by clause 198 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.162
[Revoked]
Clause 17.162: revoked, on 20 December 2021, by clause 199 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.163
[Revoked]
Clause 17.163: revoked, on 20 December 2021, by clause 200 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.164
Clearing manager must conduct auctions
- The format specified by the clearing manager for bidding under rule 3.3 of section IV of part G of the rules that was in force immediately before this Code came into force, is deemed to be the format for bidding under clause 13.117(3), until further amended.
17.165
[Revoked]
Clause 17.165: revoked, on 20 December 2021, by clause 201 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.166
[Revoked]
Clause 17.166: revoked, on 20 December 2021, by clause 202 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.167
[Revoked]
Clause 17.167: revoked, on 20 December 2021, by clause 203 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.168
[Revoked]
Clause 17.168: revoked, on 20 December 2021, by clause 204 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.169
[Revoked]
Clause 17.169(2): revoked, on 20 December 2021, by clause 205 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
Clause 17.169: revoked, on 1 March 2024, by clause 132 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2024.
17.170
[Revoked]
Clause 17.170: revoked, on 20 December 2021, by clause 206 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.171
[Revoked]
Clause 17.171: revoked, on 20 December 2021, by clause 207 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.172
[Revoked]
Clause 17.172: revoked, on 20 December 2021, by clause 208 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.173
[Revoked]
Clause 17.173: revoked, on 20 December 2021, by clause 209 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.174
[Revoked]
Clause 17.174: revoked, on 20 December 2021, by clause 210 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.175
[Revoked]
Clause 17.175: revoked, on 20 December 2021, by clause 211 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.176
[Revoked]
Clause 17.176: revoked, on 20 December 2021, by clause 212 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.177
[Revoked]
Clause 17.177(4): amended, on 21 September 2012, by clause 41(1) of the Electricity Industry Participation (Minor Amendments) Code Amendment 2012.
Clause 17.177(5): amended, on 21 September 2012, by clause 41(2) of the Electricity Industry Participation (Minor Amendments) Code Amendment 2012.
Clause 17.177: revoked, on 20 December 2021, by clause 213 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.178
[Revoked]
Clause 17.178: revoked, on 20 December 2021, by clause 214 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.179
[Revoked]
Clause 17.179: revoked, on 20 December 2021, by clause 215 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.180
[Revoked]
Clause 17.180: revoked, on 20 December 2021, by clause 216 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.181
[Revoked]
Clause 17.181: revoked, on 20 December 2021, by clause 217 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.182
[Revoked]
Clause 17.182: revoked, on 20 December 2021, by clause 218 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.183
[Revoked]
Clause 17.183: revoked, on 20 December 2021, by clause 219 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.184
[Revoked]
Clause 17.184: revoked, on 1 March 2024, by clause 133 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2024.
17.185
[Revoked]
Clause 17.185: revoked, on 20 December 2021, by clause 220 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.186
[Revoked]
Clause 17.186: revoked, on 20 December 2021, by clause 221 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.187
[Revoked]
Clause 17.187: revoked, on 20 December 2021, by clause 222 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.188
[Revoked]
Clause 17.188: revoked, on 20 December 2021, by clause 223 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.189
[Revoked]
Clause 17.189: revoked, on 20 December 2021, by clause 224 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.190
[Revoked]
Clause 17.190: revoked, on 20 December 2021, by clause 225 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.191
Information that must be submitted
- The form specified by the Board for submission of information under rule 3 of section VI of part G of the rules immediately before this Code came into force, is deemed to be the form specified by the Authority under clause 13.219.
17.192
Calculation of contract price
- Guidelines issued by the Board under rule 4 of section VI of part G of the rules and in force immediately before this Code came into force, are deemed to be guidelines issued by the Authority under clause 13.220.
17.193
Information submitted
- Information submitted under rules 3, 7 and 8 of section VI of part of G of the rules immediately before this Code came into force, is deemed to be information submitted under clauses 13.219, 13.223, and 13.224 respectively.
17.194
Timeframes for submitting that information
- Information submitted in accordance with rule 9 of section VI of part G of the rules immediately before this Code came into force, is deemed to be information submitted under clause 13.225.
Transitional provisions relating to Part 14
17.195
Acceptable forms of security
- (1) A cash deposit paid under rule 2.4.1 of part H of the rules before this Code came into force, is deemed to be a cash deposit paid under clause 14.5(a).
- (2) A security agreement provided and maintained under rule 2.4.1 of part H of the rules immediately before this Code came into force, is deemed to be a security agreement provided and maintained under clause 14.5(a).
- (3) An unconditional guarantee or letter of credit provided and maintained under rule 2.4.2 of part H of the rules immediately before this Code came into force, is deemed to be an unconditional guarantee or letter of credit provided and maintained under clause 14.5(b).
- (4) An unconditional third party guarantee provided and maintained under rule 2.4.3 of part H of the rules immediately before this Code came into force, is deemed to be an unconditional third party guarantee provided and maintained under clause 14.5(c).
- (5) A security bond provided and maintained under rule 2.4.4 of part H of the rules immediately before this Code came into force, is deemed to be a security bond provided and maintained under clause 14.5(d).
- (6) A hedge settlement agreement lodged under rule 2.4.5 of part H of the rules immediately before this Code came into force, is deemed to be a hedge settlement agreement lodged under clause 14.5(e).
- (7) If the terms of a security were approved by the Commission under rule 2.4 of part H of the rules immediately before this Code came into force, those terms are deemed to be approved by the Authority under clause 14.5.
17.196
Cash deposits
- (1) A cash deposit account established under rule 2.6.1 of part H of the rules immediately before this Code came into force, is deemed to be a cash deposit account established under clause 14.7(1).
- (2) An acknowledgment obtained under rule 2.6.3 of part H of the rules immediately before this Code came into force, is deemed to be an acknowledgment obtained under clause 14.7(3).
- (3) A cash deposit received under rule 2.6.4 of part H of the rules immediately before this Code came into force, is deemed to be a cash deposit received under clause 14.8, and must be paid accordingly.
- (4) [Revoked]
- (5) [Revoked]
Clause 17.196(4) and (5): revoked, on 20 December 2021, by clause 226 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.197
[Revoked]
Clause 17.197: revoked, on 20 December 2021, by clause 227 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.198
[Revoked]
Clause 17.198: revoked, on 20 December 2021, by clause 228 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.199
[Revoked]
Clause 17.199: revoked, on 20 December 2021, by clause 229 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.200
[Revoked]
Clause 17.200: revoked, on 20 December 2021, by clause 230 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.201
[Revoked]
Clause 17.201: revoked, on 20 December 2021, by clause 231 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.202
[Revoked]
Clause 17.202: revoked, on 20 December 2021, by clause 232 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.203
[Revoked]
Clause 17.203: revoked, on 20 December 2021, by clause 233 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.204
[Revoked]
Clause 17.204: revoked, on 20 December 2021, by clause 234 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.205
Operating account
- (1) An operating account established under rule 7.11 of part H of the rules immediately before this Code came into force, is deemed to be an operating account established under clause 14.43(1).
- (2) An acknowledgment obtained under rule 7.12 of part H of the rules immediately before this Code came into force, is deemed to be an acknowledgment obtained under clause 14.43(2).
17.206
[Revoked]
Clause 17.206: revoked, on 20 December 2021, by clause 235 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.207
[Revoked]
Clause 17.207: revoked, on 20 December 2021, by clause 236 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.208
[Revoked]
Clause 17.208: revoked, on 20 December 2021, by clause 237 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.209
[Revoked]
Clause 17.209: revoked, on 20 December 2021, by clause 238 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.210
[Revoked]
Clause 17.210: revoked, on 20 December 2021, by clause 239 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2019.
17.210A
[Revoked]
Clause 17.210A: inserted, on 24 March 2015, by clause 28 of the Electricity Industry Participation (Settlement and Prudential Security) Code Amendment 2013.
Clause 17.210A: revoked, on 5 October 2017, by clause 582 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
17.210B
[Revoked]
Clause 17.210B: inserted, on 24 March 2015, by clause 28 of the Electricity Industry Participation (Settlement and Prudential Security) Code Amendment 2013.
Clause 17.210B: revoked, on 5 October 2017, by clause 582 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
17.210C
[Revoked]
Clause 17.210C: inserted, on 24 March 2015, by clause 28 of the Electricity Industry Participation (Settlement and Prudential Security) Code Amendment 2013.
Clause 17.210C: revoked, on 5 October 2017, by clause 582 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
17.210D
[Revoked]
Clause 17.210D: inserted, on 24 March 2015, by clause 28 of the Electricity Industry Participation (Settlement and Prudential Security) Code Amendment 2013.
Clause 17.210D: revoked, on 5 October 2017, by clause 582 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
17.210E
[Revoked]
Clause 17.210E: inserted, on 24 March 2015, by clause 28 of the Electricity Industry Participation (Settlement and Prudential Security) Code Amendment 2013.
Clause 17.210E: revoked, on 5 October 2017, by clause 582 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
17.210F
[Revoked]
Clause 17.210F: inserted, on 24 March 2015, by clause 28 of the Electricity Industry Participation (Settlement and Prudential Security) Code Amendment 2013.
Clause 17.210F: revoked, on 5 October 2017, by clause 582 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
17.210G
[Revoked]
Clause 17.210G: inserted, on 24 March 2015, by clause 28 of the Electricity Industry Participation (Settlement and Prudential Security) Code Amendment 2013.
Clause 17.210G: revoked, on 5 October 2017, by clause 582 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
17.210H
[Revoked]
Clause 17.210H: inserted, on 24 March 2015, by clause 28 of the Electricity Industry Participation (Settlement and Prudential Security) Code Amendment 2013.
Clause 17.210H: revoked, on 5 October 2017, by clause 582 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
17.210I
[Revoked]
Clause 17.210I: inserted, on 24 March 2015, by clause 28 of the Electricity Industry Participation (Settlement and Prudential Security) Code Amendment 2013.
Clause 17.210I: revoked, on 5 October 2017, by clause 582 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
17.210J
[Revoked]
Clause 17.210J: inserted, on 24 March 2015, by clause 28 of the Electricity Industry Participation (Settlement and Prudential Security) Code Amendment 2013.
Clause 17.210J: revoked, on 5 October 2017, by clause 582 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
17.210K
[Revoked]
Clause 17.210K: inserted, on 24 March 2015, by clause 28 of the Electricity Industry Participation (Settlement and Prudential Security) Code Amendment 2013.
Clause 17.210K: revoked, on 5 October 2017, by clause 582 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
17.210L
[Revoked]
Clause 17.210L: inserted, on 24 March 2015, by clause 28 of the Electricity Industry Participation (Settlement and Prudential Security) Code Amendment 2013.
Clause 17.210L(2) and (3): inserted, on 24 March 2015, by clause 27 of the Electricity Industry Participation Code Amendment (Settlement and Prudential Security) 2014.
Clause 17.210L: revoked, on 5 October 2017, by clause 582 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
17.210M
[Revoked]
Clause 17.210M: inserted, on 24 March 2015, by clause 28 of the Electricity Industry Participation (Settlement and Prudential Security) Code Amendment 2013.
Clause 17.210M: revoked, on 5 October 2017, by clause 582 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
17.210N
[Revoked]
Clause 17.210N: inserted, on 24 March 2015, by clause 28 of the Electricity Industry Participation (Settlement and Prudential Security) Code Amendment 2013.
Clause 17.210N: revoked, on 5 October 2017, by clause 582 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.
17.210O
[Revoked]
Clause 17.210O: inserted, on 24 March 2015, by clause 28 of the Electricity Industry Participation (Settlement and Prudential Security) Code Amendment 2013.
Clause 17.210O: revoked, on 5 October 2017, by clause 582 of the Electricity Industry Participation Code Amendment (Code Review Programme) 2017.