Electricity Industry Participation Code Amendment (Code Review Programme) 2018
Downloads
-
Electricity Industry Participation Code Amendment (Code Review Programme) 20181 November 2018, 34 pages
Related documents
-
Code review programme 2018 - Decision paper2 October 2018, 123 pages
-
Code review programme 2018 - Consultation paper16 January 2018, 156 pages
Explanatory note
This amendment to the Electricity Industry Participation Code 2010 ("Code") comes into force on 1 November 2018, except clauses 4(4), 4(7), 48(1), 57, 61(1), 62(2), 62(3), and 119, which come into force on 1 February 2019, and clauses 49(2) and 49(3), which come into force on 1 August 2019.
This amendment makes a variety of improvements to the Code that the Electricity Authority had identified either in the course of its work or as a result of suggestions received through the Authority's Code amendment proposal process. The amendment mostly comprises changes to the Code that would be beneficial, but that do not (of themselves) warrant a separate Code amendment.
This amendment amends Parts 1, 3, 6, 7, 8, 9, 10, 11, 12, 13, 14, 14A, and 15 of the Code. The changes include:
(a) the requirement for a metering equipment provider to update registry metering records;
(b) clarifying when a losing trader must respond to a switch move request;
(c) removing the requirement for a generator to give written notice to the system operator when the generator enters into, or amends, a block dispatch agreement;
(d) various changes to the process for amending or rescinding approved shorter post-default exit periods under Part 14A of the Code;
(e) clarifying the requirements for a distributor to enter chargeable capacity information into the registry;
(f) amending the timeframe for the clearing manager to calculate constrained off amounts and constrained on amounts;
(g) amending the process for determining switching event dates;
(h) adding a requirement that a trader must have an arrangement with a customer or embedded generator at an ICP before the trader commences switching at the ICP;
(i) clarifying the requirements for providing submission information to the reconciliation manager;
(k) removing repeated obligations to report breaches of the Code and then to publish those reports; removing the definition of "customer" from Part 1 of the Code, and making all consequential changes;
(l) updating the security forms set out in Schedules 14A.2 to 14A.5 of the Code;
(m) clarifying when a reconciliation participant may connect or electrically connect certain points of connection; and
(n) various editorial changes to the Code, to make it easier for participants to understand and comply with the obligations under the Code.
Legislative information
| Title | Electricity Industry Participation Code Amendment (Code Review Programme) 2018 |
|---|---|
| Principal or amendment | Amendment |
| Consolidated version | No |
| Empowering Act and provisions | Electricity Industry Act 2010, section 38 |
| Replacement empowering Act and provisions | Not applicable |
| Maker name | Electricity Authority |
| Administering agency | Electricity Authority |
| Date made | 24 September 2018 |
| Notification date | 27 September 2018 |
| Commencement date | 1 November 2018 |
| End date | Not applicable |
| Consolidation as at date | Not applicable |
| Related instruments | Electricity Industry Participation Code 2010 |