Barriers to developing new electricity generation
This dashboard shows the challenges hindering new electricity generation projects in New Zealand, based on the results of the Electricity Authority’s 2025 Generation Investment Survey.
- Generation
- Investment
- Security of supply
- Wholesale
New electricity generation
This dashboard summarises the key insights from the Electricity Authority’s 2025 Generation Investment Survey into barriers to new electricity generation projects. Key findings from the survey include:
- Solar developers rated the consenting process as significantly more difficult than in 2023, when the previous survey was carried out
- Securing offtake arrangements was rated the second-most significant challenge
- Requirements under the Overseas Investment Act are no longer considered a major barrier.
About the survey
In April 2025, the Electricity Authority invited developers investing in new electricity generation to complete a survey about barriers to electricity generation development.
There were 24 survey responses, of which three were gentailers and the rest were independent developers. Projects included 14 solar or combined solar plus batteries, 13 wind projects (11 onshore and two offshore), and four batteries without solar.
We interviewed seven developers to understand the reasons behind their survey responses. These conversations provided valuable detail about the barriers they face and how these affect the timing, cost and risk of new generation projects.
We compared the results with our more comprehensive 2023 Generation Investment Survey.
About this dashboard
The below dashboard shares the findings from the Generation Investment Survey and interviews.
This work has provided valuable insights into what factors create delays, increase costs or add risk to generation investment projects. It helped the Authority identify gaps in our understanding of barriers to new generation and will inform our ongoing efforts to strengthen security of supply.
The dashboard highlights the Authority’s work to help alleviate barriers, including improving access to firming through standardised flexibility products and level playing field work. Our regulatory roadmap on battery-related work will also help manage some of the uncertainty these projects face.
Review of connections process
In 2026, the Authority commissioned an independent review of the network connections process after it was identified as one of the main challenges facing generation developers in this 2025 Generation Investment Survey.
The review found Transpower's process for connecting new generation projects to the national grid has improved significantly since Transpower introduced a Connections Management Framework in 2022.
The generation connections process is generally effective, efficient and fair, and is working as intended. It has enabled more projects to progress through the connections process, reduced backlogs and helped focus resources on projects that are ready to proceed.
It also identified five focus areas for ongoing attention: refining process settings, improving transparency and predictability, strengthening commercial responsiveness, improving performance measurement, and managing future system pressures as demand for connections grows.
The suggested focus areas are with Transpower to consider as part of its ongoing management and improvement of the connections process. The Authority is not responsible for implementing the review's findings but will continue to monitor the performance and effectiveness of the connections framework.