Explanatory note

This amendment to the Electricity Industry Participation Code 2010 comes into force on 1 October 2027.

The amendment amends Part 14 of the Electricity Industry Participation Code 2010 to require the clearing manager to make all loss and constraint excess available for settlement of financial transmission rights (FTR), removing the requirement for the FTR Manager to calculate the amount available for settlement.


Legislative information

Title Electricity Industry Participation Code (Settlement of Financial Transmission Rights) Amendment 2026
Principal or amendment Amendment
Consolidated version No
Empowering Act and provisions Electricity Industry Act 2010, section 38
Replacement empowering Act and provisions Not applicable
Maker name Electricity Authority
Administering agency Electricity Authority
Date made 28 September 2026
Publication date 2 October 2026
Notification date 2 October 2026
Commencement date 1 October 2027
End date Not applicable
Consolidation as at date Not applicable
Related instruments Electricity Industry Participation Code 2010