Electricity Industry Participation Code Amendment (Transmission Pricing Methodology Related Amendments) (No 2) 2022
Downloads
Related documents
-
Existing notional embedding contracts under the new TPM - Decision paper19 July 2022, 15 pages
-
Consultation paper - Appendix C - Transpower Letter to the Authority December 202126 May 2022, 3 pages
Explanatory note
This amendment to the Electricity Industry Participation Code 2010 comes into force on 1 April 2023.
The amendment removes certain exceptions to the requirement on Transpower to charge for transmission services only in accordance with the transmission pricing methodology.
Legislative information
| Title | Electricity Industry Participation Code Amendment (Transmission Pricing Methodology Related Amendments) (No 2) 2022 |
|---|---|
| Principal or amendment | Amendment |
| Consolidated version | No |
| Empowering Act and provisions | Electricity Industry Act 2010, section 38 |
| Replacement empowering Act and provisions | Not applicable |
| Maker name | Electricity Authority |
| Administering agency | Electricity Authority |
| Date made | 15 July 2022 |
| Notification date | 19 July 2022 |
| Commencement date | 1 April 2023 |
| End date | Not applicable |
| Consolidation as at date | Not applicable |