General news
Decision on 11 April 2024 under-frequency event
- Generation
- Compliance
The Electricity Authority Te Mana Hiko's final determination is that Genesis Energy Limited, as the generator that owns Huntly Unit 4, was the causer of the 11 April 2024 under-frequency event (UFE).
The Authority's reasons for this final determination are:
- A UFE occurred at 12.25am on 11 April 2024 when frequency dropped to 49.17Hz in the North Island and 49.25Hz in the South Island
- The interruption/reduction of electricity occurred at the grid injection point for Huntly Unit 4, which belongs to Genesis
- No other asset was identified as having caused or potentially caused the UFE
- Genesis agreed with the system operator’s assessment that Genesis was the causer of the UFE
- The Authority did not receive any feedback that disputed its draft determination.
In accordance with clause 8.65 of the Electricity Industry Participant Code, the clearing manager will rebate the event charges to the relevant participants. The event charge calculated in the system operator’s report to the Authority is $205,003.75.
Any dispute of this final determination can be lodged with the Rulings Panel via registrar@electricityrulingspanel.nz by 5pm, 17 December 2024.
Related News
Decision on 21 April 2025 under-frequency event
An under-frequency event occurred at 4.43pm on 21 April 2025 when Huntly Unit 4 tripped offline reducing North Island frequency to 49.16 Hz.
Proposals to improve visibility of distributed generation and load pipeline
We want to collect, aggregate and publish information about significant generation and load connecting to distribution networks and want to hear your views abo…
Electricity market performance from January to June
During the first half of 2025, the electricity market responded to changing levels of hydro, thermal and wind generation. Hydro inflows were unusually low unti…