The Transmission Pricing Methodology (TPM) provides for an adjustment of a transmission customer’s residual charge when a transmission customer experiences a substantial decrease in demand prior to the new TPM coming into effect on 1 April 2023. The formula for calculating this is called the reduction event adjustment factor (REAF) formula.

Errors have been identified in the formula that would result in adjustments that differ from the policy intent.

To correct the formula, we are making an urgent Code amendment (with a limited duration of 9 months) to ensure it is in force in time for the commencement of the new TPM on 1 April this year. We intend to progress a permanent Code amendment in May.

Related News

Decision on 21 April 2025 under-frequency event

An under-frequency event occurred at 4.43pm on 21 April 2025 when Huntly Unit 4 tripped offline reducing North Island frequency to 49.16 Hz.

New rules to improve application processes for network connections: technical consultation opens

We are inviting feedback on the draft Code for recently announced new rules that make it easier and faster to connect to the electricity network, or to upgrade…

Connection pricing methodologies Code amendment finalised and FAQs published

We’ve published a new webpage of frequently asked questions for the new rules to improve connection pricing methodologies. These FAQs are designed to help dist…