Parts 1, 7 and 8 Common quality requirements review
Decision
We've decided to amend the Code to give effect to the six Code amendments described in the decision paper.
These six Code amendments address issues relating to Code terminology and clarify various common quality obligations in Parts 1, 7 and 8 of the Code.
The Code amendments will come into effect on 1 December 2026.
The Procurement Plan updates required under the FSR-103 Code amendment will come into effect before the FSR-103 Code amendment. In accordance with clause 7.20(5) of the Code, the System Operator is not consulting on these changes to the Procurement Plan as the Authority has consulted sufficiently on this matter.
Thanks to all who provided feedback.
Consultation
We sought feedback on proposals aimed at addressing six common quality issues in the Code.
The six proposed amendments will update Code terminology, clarify requirements, and remove inconsistencies in Parts 1, 7 and 8 of the Code.
The proposals are expected to help maintain the security and resilience of the power system and keep downward pressure on consumers’ power bills by:
- reinforcing the ability of the System Operator to take necessary actions
- promoting the efficient operation of the electricity industry
- increasing competition by promoting competitive neutrality.
Consultation paper
Submissions
-
Nova Energy1 page
-
Transpower5 pages
-
University of Auckland5 pages
-
WEL Networks4 pages