Code amendments
Electricity Industry Participation Code (Connected Asset Commissioning, Testing and Information Standard) Amendment 2026
Downloads
Related documents
-
Code amendment proposal on common quality-related information - Consultation paper1 July 2025, 137 pages
Explanatory note
This amendment to the Electricity Industry Participation Code 2010 (Code) comes into force on 1 July 2026.
The amendment amends provisions in the Code relating to common quality and incorporates a new system operation document into the Code, the Connected Asset Commissioning, Testing and Information Standard. The Standard updates and replaces existing obligations in the Code relating to technical specifications for assets connected or connecting to the power system.
Legislative information
| Title | Electricity Industry Participation Code (Connected Asset Commissioning, Testing and Information Standard) Amendment 2026 |
|---|---|
| Principal or amendment | Amendment |
| Consolidated version | No |
| Empowering Act and provisions | Electricity Industry Act 2010, section 38 |
| Replacement empowering Act and provisions | Not applicable |
| Maker name | Electricity Authority |
| Administering agency | Electricity Authority |
| Date made | 26 May 2026 |
| Publication date | 27 May 2026 |
| Notification date | 26 May 2026 |
| Commencement date | 1 July 2026 |
| End date | Not applicable |
| Consolidation as at date | Not applicable |
| Related instruments | Electricity Industry Participation Code 2010 |