Electricity Industry Participation Code Amendment (COVID-19 Deferred Payment of Distribution Charges) 2020 - expired
Downloads
Explanatory note
This amendment to the Electricity Industry Participation Code 2010 (Code) comes into force on 20 May 2020 and expires on 20 February 2021.
The amendment makes changes to Part 12A of the Code to:
(a) provide for qualifying traders (which meet specified criteria, including in relation to facing liquidity problems as a result of the COVID-19 pandemic) to have an additional 60 days to pay amounts for the provision of distribution services under their agreements with the following distributors:
(i) Orion New Zealand Limited;
(ii) Powerco Limited;
(iii) Unison Networks Limited;
(iv) Vector Limited;
(v) Wellington Electricity Lines Limited; and
(vi) WEL Networks Limited; and
(b) restrict the ability of all distributors to change the prudential security required from the qualifying traders during the period that the changes are in force.
Legislative information
| Title | Electricity Industry Participation Code Amendment (COVID-19 Deferred Payment of Distribution Charges) 2020 - expired |
|---|---|
| Principal or amendment | Amendment |
| Consolidated version | No |
| Empowering Act and provisions | Electricity Industry Act 2010, section 40 |
| Replacement empowering Act and provisions | Not applicable |
| Maker name | Electricity Authority |
| Administering agency | Electricity Authority |
| Date made | 14 May 2020 |
| Notification date | 19 May 2020 |
| Commencement date | 20 May 2020 |
| End date | 20 February 2021 |
| Consolidation as at date | Not applicable |
| Related instruments | Electricity Industry Participation Code 2010 |