General news
Authority determines two Hāwera grid exit points as non-conforming
- Wholesale
The Electricity Authority Te Mana Hiko has reclassified two grid exit points at Hāwera (HWA1101 and HWA1102), from conforming to non-conforming.
This decision follows a reconsideration request from the System Operator.
We determined the grid exit points HWA1101 and HWA1102 as non-conforming because we expect they will not follow a predictable daily demand pattern from 1 August 2026 (after the installation of electrode boilers). This will make it hard for the System Operator to forecast their load.
This decision is based on Criterion 2 (forecasting accuracy at industrial GXP).
What this means
Purchasers at these locations will now be required to prepare their own forecasts of electricity usage for market scheduling purposes (in the form of nominated bids).
This classification will come into effect at 1pm, Saturday 1 August 2026.
Right to reconsideration
All purchasers have the right to request a reconsideration of this and other grid exit point classifications (clause 13.27H of the Code) by email to info@ea.govt.nz
Related News
Decision paper on improving prudential security arrangements
The Electricity Authority Te Mana Hiko has today published a decision paper to improve prudential security arrangements by reducing the post-default exit perio…
Stress test disclosures due next month
The spot price risk disclosure regime requires certain participants in the wholesale electricity market to assess their financial exposure to hypothetical move…
First mandatory trading session for standardised super-peak contracts
The first mandatory trading session for standardised super-peak contracts takes place on 11 August. The session, to be conducted on the new over-the-counter tr…