The Electricity Authority Te Mana Hiko has decided to make three discrete amendments to the Electricity Industry Participation Code 2010 to:
- amend Part 8 to clarify use and availability of controllable load – effective 1 May 2024
- amend Part 6A to include all generation technology – effective 1 June 2024
- update and clarify the scope and effect of Part 6A obligations – effective 1 June 2024.
All three amendments mainly apply to distributors and, in the case of Part 8 amendments, the system operator. Retailers and generators which are connected to a distributor, and people involved in these businesses, also need to be aware of these amendments.
We would like to thank all submitters who provided feedback on these amendments. We received 15 submissions and made changes to all three of our proposals in response to submitters’ suggestions.
Read our decision paper to find out the reasons for our decisions, our responses to submissions and the final Code drafting.
Related News
Join our webinar on proposals to maximise benefits of local generation
Registrations are open for our webinar at 11.15am–12pm on Thursday 30 October 2025. The webinar is about our proposed new rules to make export limits more ef…
Electricity Authority consults on rule changes to level the power playing field
We are seeking feedback on proposed rule changes to level the playing field between the four large gentailers and independent participants in the electricity m…
Feedback sought on proposed SOSFIP changes
The System Operator has begun consultation on proposed changes to its Security of Supply Forecasting and Information Policy.